| 1 | Earthwork in excavation of foundation in all kinds of soil within initial lead and initial lift including rough dressing and breaking rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3 m in depth including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 2 | Supplying, Filling sand infoundation & plinth well watered and rammed including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 3 | Cement Concrete (1:4:8) by using 40 mm size hard granite crusher broken chips of approved quality and form approved quarry including lowering laying concrete, watering and curing etc. complete for required levels laid in layers including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 4 | Plain cement concrete (1:2:4) using 12 mm size hard granite crusher broken chips of approved quality and form approved quarry including lowering laying concrete, watering and curing etc. complete for required levels laid in layers including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 5 | Rigid and smooth centering & shutering for RCCwork including false works & dismentalling then after casting including cost, conveyance and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC.- RCC foundation and plinth band footings,bases of columns. Mass concrete & pre cast slabs |
| 6 | Rigid and smooth centering & shutering for RCCwork including false works & dismentalling then after casting including cost, conveyance and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC.- R.C.C. beams, column, grider and bressmer, etc |
| 7 | Supplying MS round / deformed / tor steel reinforcement bars ofmanufacturing approved companies & approved grade of required diameters of approved quality including straightening, cutting to size, bending, and binding, lifting and placing in positionas per design, complete including cost of bars, binding wires 18 gauge, including cost, conveyance and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. (Linear measurement will be taken and quantity will be calculated on standard weight for all heights). |
| 8 | Random rubble hard granite stone masonry in clay or sand or gravel grouted in foundation and plinth of approved quality and form approved quarry including lowering laying concrete, watering and curing etc. complete for required levels laid in layers including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 9 | Random rubble H.G. stone Masonry in cement mortar (1:6) in foundation and plinth of approved quality and form approved quarry including lowering laying concrete, watering and curing etc. complete for required levels laid in layers including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 10 | Providing 2.5 cm Damp proof Course [DPC] with CC [1:2:4] using 12 mm size crusher broken chips of approved quality and from approved quarry including hoisting, lowering. Laying. Compacting, vibrating the concrete watering and curing for required period complete including cost, conveyance, royalty and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 11 | Providing Fly Ash brick masonry workusing 230 mm X 110 mm X 80 mm (with dimensional tolerance of ± 2% ) Fly Ash bricks having crushing strength not less than 75 kg. / sq cm, mortar of mix 1:6 (1 cement : 6 sand) (Using Branded Cement), immersing the bricks for minimum 6 hrs in water before use, with all necessary projections, splay cutting, circular moulding, corbelling, etc., including cost of all materials, labour, conveyance, loading and unloading, taxes, cess, royalties, scaffolding, watering, curing, sundries, tools and plants,etc., completeas per the direction of the EIC.- Superpstrucutre work in ground floor |
| 12 | 6 mm thick cement plaster (1:4) to RCC surfaces finished smooth including closed deep chipping and slurry treatment complete including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 13 | 20 mm thick cement plaster (1:6) for stone work with watering and curing etc. complete including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 14 | 16 mm thick cement plaster in cement mortar (1:6) with watering and curing etc. complete including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 15 | 12 mm thick cement plaster in cement mortar (1:6) with watering and curing etc. complete including cost, conveyance, royalty and taxes of all materials and cost of labour, T&P, Labour Welfare cess @1% required for the work etc. complete as per specification and direction for the EIC. |
| 16 | Colour washing two coats with shell lime and colouring mateials complete including cost, conveyance and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 17 | Supply, fitting and fixing of \" Y \" type pole of Fabricated Mild Steel Angle 50505 as per approved drawing and design, cutting to required size and welding properly, finished smooth and sand papering, including complete including cost, conveyance and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 18 | Labour for fixing barbed wire fencing and post by means of staples and straining hooks by means of tying with G.I. wire and including cost of staples, hooks and tying wires excluding GST but including all labour charges cost and T&P etc. Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 19 | Supplying and providing of Barbed wire (I.S.I.)[ Main wire 12 SWG, Barbs wire 14 SWG, Barbs spacing 100 mm & weight 0.122 kg/mt.] excluding GST but including all labour charges cost and conveyance of all materials with T&P etc. Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 20 | Supply, fitting and fixing of Mild Steel FabricatedGrill Gate made of angle/Hollow Square/Rectangle sectionas per approved drawing and design, cutting to required size and welding properly, finished smooth and sand papering, including complete including cost, conveyance and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 21 | Priming one coat to surface with Red oxide Primer complete including cost, conveyance and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |
| 22 | Painting two coats with approved Enamel paint on new wood work complete including cost, conveyance and taxes of all materials and cost of all labour with T&P required for the work ,Labour welfare cess@1% etc. complete as per the direction for the EIC. |