1 Earthwork Excavation Earthwork Excavation For Foundation / Culvert / Pipeline / Spillage In All Types Of Loose / Hard Soil And Depositing The Spoils With An Initial Lead Of 200M And Lift Upto 2M Including Refilling Etc., Complete As Per The Direction Of The Engineer-In-Charge. 2 2 Picking The Existing Bt / Concrete Surface Picking The Existing Bt / Concrete Surface With Required Depth As Directed By The Departmental Officers And Collecting The Picked Up Salvaged Metal And Stacking The Same For Reuse / Remove The Unused Debris Within A Lead Of 500M Excluding Cost Of Materials Including All Labour Charges For Picking And All Other Tools And Plants Employed Of The Work With All Incidental Charges Etc., Complete As Per Standard Specifications Of Morth Rev. 5 And Directed By Engineer-In-Charge. 3 3 Supplying, Providing And Laying Of Gravel Supplying, Providing And Laying Of Gravel Including Cost And Conveyance Of The Same To The Work Site With An Average Lead Of 1 Km Including Stacking The Same To Departmental Gauge For Premeasurement Including All Labour Charges For Mixing, Watering, Laying, Spreading, Levelling, Compaction ( Vibrating Power Roller ) Etc. Complete As Per Standard Specifications Of Morth Rev. 5 And Directed By Engineer-In-Charge. 4 4 Supplying, Providing, Laying, Etc To Wet Mix Mecadam Supplying, Providing, Laying, Spreading And Compacting Graded Hard Blue Irc Standard Machine Crushed Stone Material Aggregate To Wet Mix Macadam ( Wmm ) 250Mm / 150Mm Thick Specification Including Premixing The Materials With Water At Omc In Mechanical Mix Plant Carriage Of Mixed Material By Tipper To Site Laying In Uniform Layers In Sub Base / Base Course On Well Prepared Surface And Compacting With Vibratory Power Roller To Achieve The Desired Density Including All Other Incidental Charges With Necessary Picking Of Existing Surface ( Bitumen / Concrete ) Etc., Complete As Per Clause 406 Of Morth Rev-5 And Directed By Engineer-In-Charge. ( Test Certificate Has To Be Provided At The Time Of Supply ) . 5 5 Supplying, Providing And Laying Soling Stone Supplying, Providing And Laying Soling Stone 230Mm Thick Over The Existing Sub Base / Sub Grade Including Levelling And Consolidation To Form A Compact Surface Using Hard Blue Granite Soling Stone Including Hand Packing, Wedging Them Tightly And Filling The Voids With Loose Sand, Watering And Sweeping The Sand Into The Joints So That The Hole Is Formed As Solid Mass, Etc. Complete As Per Standard Specification And As Per The Direction Of Engineer-In-Charge. 6 6 Supplying, Providing And Laying Pcc 1:4:8 Mix Supplying, Providing And Laying Pcc 1:4:8 Mix For Foundation / Flooring / Base Course Work Using 40Mm And Below Grade Hard Blue Granite Jelly Including All Form Works, Mixing, Laying, Compaction, Consolidation And Curing, Etc. Complete As Per Standard Specifications And As Directed By The Engineer-In-Charge. 7 7 Supplying, Providing And Laying Pcc 1:2:4 Supplying, Providing And Laying Pcc 1:2:4 Mix For Foundation / Flooring / Base Course Work / Kerb Wall Drainage Wall Using 20Mm And Below Grade Hard Blue Granite Jelly Including All Form Works, Mixing, Laying Consolidation And Curing, Etc. Complete As Per Standard Specifications And As Directed By The Engineer-In-Charge. 8 8 Supplying, Providing And Fixing Twisted Reinforcement Supplying, Providing And Fixing Twisted Reinforcement Is 1786 Hysd Bars Fe500d / Fe550d ( Tmt Bars - Tata / Agni / Jsw ) Including Fabrication, Cutting, Bending, Cold Tying, With Overlapping To The Standard Length Wherever Necessary And Placing The Reinforcement In Position As Per The Direction Of Engineer-In-Charge Including Binding, Provision Of Spacer Bars, Cover Blocks And All Other Incidental Charges, Etc. Complete For All Rcc Works As Per Standard Specification And As Per The Direction Of Engineer-In-Charge. 9 9 Supplying, Providing And Laying Cement Concrete 1:1.5:3 For Rcc Supplying, Providing And Laying Cement Concrete 1:1.5:3 For Rcc Works Using 20Mm And Below Grade Hard Blue Granite Jelly With Specified Reinforcement ( Rate Excluding The Cost Of Reinforcement ) And All Mixing, Laying, Compaction, Leveling, Consolidation And Curing, Etc., Including The Cost Of Centering / Shuttering Work, Complete As Per The Specification And As Per The Direction Of Engineer-In-Charge. 10 10 Supplying, Providing And Laying 450Mm Dia Np3 Class Rcc Pipe Supplying, Providing And Laying 450Mm Dia Np3 Class Rcc Pipe Conforming To Is 458 / 2003 Including Cost Of Pipe As A Finished Work, Fixing, Collars In Proper Gradient Including All Other Incidental Charges, Loading, Unloading, Transport And Delivery In Good Condition At Work Site, Etc., Complete, As Directed By The Engineer-In-Charge, As Per Standard Specification. 11 11 Supplying, Providing And Laying Prime Coat Supplying, Providing And Laying Prime Coat Over Wbm / Wmm Surface Using 7Kg Of Emulsion Bitumen ( Ss1 ) Per 10 Sqm For Preparatory To Bituminous Construction Over It, Including Cost Of Material, Labour Charges, Rentals For Machinery, Fuel And All Other Incidental Charges Etc., Complete As Per Clause 502 Of Morth Rev-5 And Directed By Engineer-In-Charge. 12 12 Supplying, Providing And Laying Tack Coat Supplying, Providing And Laying Tack Coat Over Wbm / Wmm / Existing Bitumen / Concrete Surface Using 2.50 Kg Of Bitumen Emulsion ( Rs1 ) Per 10 Sqm For Preparatory To Another Bituminous Construction Over It Including Cost Of Material, Labour Charges, Rentals For Machinery, Fuel And All Other Incidental Charges Etc., Complete As Per Clause 503 Of Morth Rev-5 And Directed By Engineer-In-Charge. 13 13 Patch Work Patch Work: Supplying, Providing And Laying 50Mm Consolidated Thick Bituminous Macadam As Per Sl.No. 13 14 14 Dense Bituminous Macadam Supplying, Providing And Laying 50Mm Consolidated Thick Dense Bituminous Macadam ( Dbm ) As Per Sl.No. 14 15 15 Supplying, Providing And Laying Premix Carpet With Seal Coat Supplying, Providing And Laying Premix Carpet With Seal Coat As Per Sl.No. 15 16 16 Excavation Including Neat Cleaning, Removal And Satisfactory Disposal Of All Materials Excavation Including Neat Cleaning, Removal And Satisfactory Disposal Of All Materials ( Manually / Mechanically ) Necessary For The Construction Of Roadway And Side Drains In Accordance With The Specifications And The Lines, Grades And Cross Sections For Making Up Berms Using Side Earth ( Upto 1 M Deep ) , Etc., Complete As Per Standard Specifications Of Morth Rev. 5 And As Per The Direction Of Engineer-In-Charge. 17 17 Supplying & Painting Road Marking With Thermoplastic Paint Supplying & Painting Road Marking With Thermoplastic Paint ( 2.50 Mm Thick ) Confirming To Clause 803.4 Of Morth Rev.5 Including Preparation Of Surface And Application With All Other Incidental Charges Etc., Complete As Per The Direction Of 18 18 Supplying, Providing & Fixing Retro Reflective Sign Boards Supplying, Providing & Fixing Retro Reflective Sign Boards As Per Sl.No.18