| 1 | Item Description/ Heading |
| 2 | (A) Erection of 3.3 KV Overhead line from P-2 Sump of Bhatgaon CHP to BVG Solar Power Plant |
| 3 | Providing and fixing of 3.3KV cross arm with back clamp, top channel and suitable nut & Bolt, 3.3KV Pin Insulator with pin and hardware fixing and tightening. (Job -1) |
| 4 | Providing and fixing of DC cross arm set with suitable Nut & Bolt, , 3.3KV composite DiscInsulator set with hardwarefixing and tightening for 1 DP. (Job -2) |
| 5 | Providing and fixing of DC cross arm set with suitable Nut & Bolt, 3.3KV Pin Insulator with pin and hardware,3.3KV composite Disc Insulator set with hardwarefixing and tightening for 1 TP. (Job -3) |
| 6 | Providing and fixing of complete stay set 16 mm with stay wire 7/10 SWG @ 8.5Kg/stay and stay clamp, stay insulator , stay pit digging with 0.86 cmt/stay excavation andconcreting of stay @ 0.2 cmt per stay and all required nut bolts.. (Job -4) |
| 7 | Transportation of pole from road side to pole pit for a lead upto 1 km, pole pit digging, pole erection complete including earthing and concreting of pole @ 0.07 cmt/pole & 2.15 cmt/pole excavation (Pole will be provided by SECL). (Job -5) |
| 8 | Stringing of line all three phase conductors, twisting of jointing sleeve and pin winding by using Binding Wire (6SWG GI Wire) (Conductor will be provided by SECL). (Job -6) |
| 9 | Providing and fixing of complete AB Switch 3.3 KV Grade, 200 Amp. (Job -7) |
| 10 | Providing and fixing of complete MCCB 200A (01 No.) and 100A Kit Kat Fuse (03 Nos.). (Job -8) |
| 11 | Installation of25KVA, 3.3KV/440V oil cooled transformer to the site (Crane and Trnasformer will be provided departmentally). (Job-9) |
| 12 | (B) Erection of 3.3 KV Overhead line from Incoming 3.3 KV Dugga Feeder Junction point to Wharf Wall substation of Bhatgaon CHP. |
| 13 | Providing and fixing of 3.3KV cross arm with back clamp, top channel and suitable nut & Bolt, 3.3KV Pin Insulator with pin and hardware fixing and tightening. (Job -1) |
| 14 | Providing and fixing of DC cross arm set with suitable Nut & Bolt, , 3.3KV composite DiscInsulator set with hardwarefixing and tightening for 1 DP. (Job -2) |
| 15 | Providing and fixing of complete stay set 16 mm with stay wire 7/10 SWG @ 8.5Kg/stay and stay clamp, stay insulator , stay pit digging with 0.86 cmt/stay excavation andconcreting of stay @ 0.2 cmt per stay and all required nut bolts. (Job -4) |
| 16 | Transportation of pole from road side to pole pit for a lead upto 1 km, pole pit digging, pole erection complete including earthing and concreting of pole @ 0.07 cmt/pole & 2.15 cmt/pole excavation (Pole will be provided by SECL). (Job -5) |
| 17 | Stringing of line all three phase conductors, twisting of jointing sleeve and pin winding by using Binding Wire (6SWG GI Wire) (Conductor will be provided by SECL). (Job -6) |
| 18 | Total impact of GST for the purpose of CTC |