Tender For Execution Of Works Against Various Public Demands On Turnkey Basis
Tender Overview
Project Description
Execution Of Works Against Various Public Demands On Turnkey Basis- 1 Detail Of Public Demand- Public Demand For Creation Of 250 Kva Sub-Station Along With Ht / Lt Line Bhallar W.No. Barnoti 2 Creationof 250 Kvasub Station At Bhallar W.No. Barnoti On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 3 11 / 0.433Kv, 250 Kva, 3-Phase Distribution Transformers With Bimetallic Terminal Connectors Energy Level-2, ( Al Wound ) Up To200 Kva, Copper Woundandwithlv Cable Box Having Detachable Aluminium Gland Plate. 4 Gapless Surge Arrestor, 9 Kv , 10 Ka , La With Polymer Housing, Stn. Type 5 11Kv Go, Ab Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type 6 11 Kv Horn Gapfuse Set 3 Phase 200A 7 185 Mm² ( 1Ckt ) Single Phasecable, 1.1K V Grade, Pvc Insulated Stranded Conductor Frls Type 8 9 Mtr. Long Pole ( Wl-300 Kg ) 9 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 10 Gi Channel / Angle / Flat Of Sizes Including Clamps For L.A Set / G.O Set / Horn Gap 11 Galvinized Nuts And Bolts. 12 Earthing Of Substation --Excavation Ofearth Pit Of Dia650 Mm & Depth 3000 Mm, Installation Ofearthing Pipe Of 40 Mm Nominal Bore & 4Mm Wall Thickness & Length 2.5 Mtr Long As Per Is 1239.Gi Strip For Neutral Earthing Of Size 25 Mm X 3 Mm For Connection Of Transformer Body, G.O Set & Lightening Arrestor As Per Is 2629 / 85, Gi Nuts & Bolts, Refilled With Earth Enhancement Materials And Earth Chamber Made Of Brick Masonary With Rcc Slab Cover. 13 Pre Fabricated Lt Distribution Box 14 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lightening Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 15 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 16 Danger Plates With Clamps 17 Gi Wire For Anti Climbing 18 Cement Bottoming 1:2:4 Mix As Per Rec Standards 19 Sundary Items 20 Laying Ofht Line On 9 Mtrs.Pcc Poles With Acsr Weasel Conductor At Bhallar W.No. Barnoti On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 21 9 Mtr. Long Pole Pcc Pole ( Wl-300 Kg ) 22 Gi V Cross-Arm / Horizontal With Top Bracket Including Clamp 23 Gi Channel X-Arm Includingclaps And Braces 24 30 Mm² Acsr Conductor 25 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 26 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 27 Galvanized Nuts And Bolts 28 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 29 Danger Plates With Clamp 30 Anti Climbing Devices With Clamps 31 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 32 Laying Oflt Line On 8 Mtrs.Pcc Poles With Acsr Weasel Conductor 3 Phase 4 Wire At Bhallar W.No. Barnoti On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 33 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 34 Gi U-Clamp For Shackle Insulators 35 Shackle Insulator 16 Kn 36 30 Mm² Acsr Conductor 37 Galvanized Nuts And Bolts 38 Danger Plates With Clamps 39 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 40 Detail Of Public Demand- Public Demand For Creation Of25 Kva Sub-Station Along With Ht / Lt At Village Sahar, Logate 41 Creation Of 25 Kva Sub Station At Sahar On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 42 11 / 0.433Kv, 25 Kva, 3-Phase Distribution Transformers With Bimetallic Terminal Connectors Energy Level-2, ( Al Wound ) , And With Lv Cable Box Having Detachable Aluminium Gland Plate. 43 Gapless Surge Arrestor, 9 Kv , 10 Ka , La With Polymer Housing, Stn. Type 44 11Kv Go, Ab Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type 45 11 Kv Horn Gapfuse Set 3 Phase 200A 46 50 Mm² ( 1Ckt ) Single Phasecable, 1.1K V Grade, Pvc Insulated Stranded Conductor Frls Type 47 9 Mtr. Long Pcc Pole ( Wl-300Kg ) 48 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 49 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lightening Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 50 Gi Channel / Angle / Flat Of Sizes Including Clamps 51 Galvinized Nuts And Bolts. 52 Cement Bottoming 1:2:4 Mix As Per Rec Standards 53 Earthing Of Substation-Excavation Ofearth Pit Of Dia650 Mm & Depth 3000 Mm, Installation Ofearthing Pipe Of 40 Mm Nominal Bore & 4Mm Wall Thickness & Length 2.5 Mtr Long As Per Is 1239.Gi Strip For Neutral Earthing Of Size 25 Mm X 3 Mm For Connection Of Transformer Body, G.O Set & Lightening Arrestor As Per Is 2629 / 85, Gi Nuts & Bolts, Refilled With Earth Enhancement Materials And Earth Chamber Made Of Brick Masonary With Rcc Slab Cover. 54 Pre Fabricated Lt Distributionswitch 55 Danger Plates With Clamps 56 Sundary Items 57 Gi Barbed Wire For Anticlimbing 58 Laying Ofht Line On 9 Mtrs.Pcc Poles With Acsr Weasel Conductor At Sahar On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 59 9 Mtr. Long Pole Pcc ( Wl-300 Kg ) 60 Gi V Cross-Arm With Top Bracket Including Clamp 61 Gi Channel X-Arm Including Clamps And Braces 62 30 Mm² Acsr Conductor ( Weasel ) 63 Pg Clamps For Weasel Conductor 64 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 65 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 66 Galvanized Nuts And Bolts 67 Danger Plates With Clamp 68 Anti Climbing Devices With Clamps 69 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 70 Stone Pad ( 300Mmx300 Mmx75mm ) 71 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 72 Laying Oflt Line On 8 Mtrs.Pcc Poles 3Phase 4 Wirewith Acsr Weasel Conductorat Saharon Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 73 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 74 Gi U-Clamp For Shackle Insulators 75 Shackle Insulator 16 Kn 76 30 Mm² Acsr Weaselconductor 77 Galvanized Nuts And Bolts 78 Danger Plates With Clamp 79 Anti Climbing Devices With Clamp 80 Earthing Complete Bu Gi Pipe40mm Or Gi Rod20 Mm 2.5 Mtr Long Through Gi Strip 81 Stone Pad ( 300Mmx300 Mmx75mm ) 82 Aluminium Jointing Sleeves 83 Detail Of Public Demand- Public Demand For Shifting Of 11 Kv Line At Village Kathua. Smt Mahesh Lata W No 11 Kathua 84 Shifting Of Ht Line On 9 Mtrs.Pcc Poles At Village Kathua Smt Mahesh Lata W No 11 Kathuaon Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 85 9 Mtr. Long Pcc Pole ( Wl-300 Kg ) 86 Gi V Cross-Arm With Top Bracket Including Clamp 87 Gi Channel X-Arm Including Clamps And Braces 88 30 Mm² Acsr Conductor ( Weasel ) 89 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 90 Galvanized Nuts And Bolts 91 Danger Plates With Clamp 92 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 93 Stone Pad ( 300Mmx300 Mmx75mm ) 94 Detail Of Public Demand- Public Demand For Creation Of100 Kva Sub-Station Along With Ht / Lt At Sukhu Chak 95 Creationof 100 Kvasub Station At Sukhu Chackon Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 96 11 / 0.433Kv, 100Kva, 3-Phase Distribution Transformers With Bimetallic Terminal Connectors Energy Level-2, ( Al Wound ) , And With Lv Cable Box Having Detachable Aluminium Gland Plate. 97 Gapless Surge Arrestor, 9 Kv , 10 Ka , La With Polymer Housing, Stn. Type 98 11Kv Go, Ab Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type 99 11 Kv Horn Gapfuse Set 3 Phase 200A 100 185 Mm² ( 1Ckt ) Single Phasecable, 1.1K V Grade, Pvc Insulated Stranded Conductor Frls Type 101 9 Mtr. Long Pcc Pole ( Wl-300Kg ) 102 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 103 Gi Channel / Angle / Flat Of Sizes Including Clamps For L.A Set / G.O Set / Horn Gap 104 Galvinized Nuts And Bolts. 105 Earthing Of Substation --Excavation Ofearth Pit Of Dia650 Mm & Depth 3000 Mm, Installation Ofearthing Pipe Of 40 Mm Nominal Bore & 4Mm Wall Thickness & Length 2.5 Mtr Long As Per Is 1239.Gi Strip For Neutral Earthing Of Size 25 Mm X 3 Mm For Connection Of Transformer Body, G.O Set & Lightening Arrestor As Per Is 2629 / 85, Gi Nuts & Bolts, Refilled With Earth Enhancement Materials And Earth Chamber Made Of Brick Masonary With Rcc Slab Cover. 106 Pre Fabricated Lt Distribution Box 107 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lightening Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 108 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 109 Danger Plates With Clamps 110 Gi Wire For Anti Climbing 111 Cement Bottoming 1:2:4 Mix As Per Rec Standards 112 Wedge Connector / Pg Clamps 113 Sundary Items 114 Laying Ofht Line On 9 Mtrs.Pcc Poles With Acsr Weasel Conductorat Sukhu Chack On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 115 9 Mtr. Long Pole Pcc ( Wl-300 Kg ) 116 Gi V Cross-Arm / Horizontal With Top Bracket Including Clamp 117 Gi Channel X-Arm Includingclaps And Braces 118 30 Mm² Acsr Conductor 119 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 120 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 121 Galvanized Nuts And Bolts 122 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 123 Danger Plates With Clamp 124 Anti Climbing Devices With Clamps 125 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 126 Aluminium Jointing Sleeves 127 Stone Pad ( 300Mmx300 Mmx75mm ) 128 Laying Oflt Line On 8 Mtrs.Pcc Poles With Acsr Weasel Conductor 3 Phase 4 Wireat Sukhu Chack On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 129 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 130 Gi U-Clamp For Shackle Insulators 131 Shackle Insulator 16 Kn 132 30 Mm² Acsr Conductor 133 Galvanized Nuts And Bolts 134 Danger Plates 135 Anit Climbing Device With Clamps 136 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 137 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 138 Lt Line Spacers 139 Stone Pad 140 Alm.Jointing Sleeves 141 Laying Oflt Line On 8 Mtrs.Pcc Poles With Acsr Weasel Conductor 1 Phase 2 Wireat Sukhu Chack On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 142 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 143 Gi U-Clamp For Shackle Insulators 144 Shackle Insulator 16 Kn 145 30 Mm² Acsr Conductor 146 Galvanized Nuts And Bolts 147 Danger Plates 148 Anit Climbing Device With Clamps 149 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 150 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 151 Lt Line Spacers 152 Stone Pad 153 Alm.Jointing Sleeves 154 Replacement For Old Acsr Weasel Conductorof Lt Line At Sukhu Chack On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 155 30Mm2 Acsr Weaselconductor 156 Gi U Clamp For Shackle Insulator 157 16Kn Polymer Shackle Insulstor 158 Galvanized Nuts And Bolts 159 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 160 Danger Plate 161 Lt Spacer 162 Stone Pad 163 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 164 Detail Of Public Demand- Public Demand For Creation Of100 Kva Sub-Station Along With Ht / Lt At W No 4 Chadwal 165 Creationof 100 Kvasub Station At W No 04 Chadwal On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 166 11 / 0.433Kv, 100Kva, 3-Phase Distribution Transformers With Bimetallic Terminal Connectors Energy Level-2, ( Al Wound ) , And With Lv Cable Box Having Detachable Aluminium Gland Plate. 167 Gapless Surge Arrestor, 9 Kv , 10 Ka , La With Polymer Housing, Stn. Type 168 11Kv Go, Ab Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type 169 11 Kv Horn Gapfuse Set 3 Phase 200A 170 185 Mm² ( 1Ckt ) Single Phasecable, 1.1K V Grade, Pvc Insulated Stranded Conductor Frls Type 171 9 Mtr. Long Pcc Pole ( Wl-300Kg ) 172 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 173 Gi Channel / Angle / Flat Of Sizes Including Clamps For L.A Set / G.O Set / Horn Gap 174 Galvinized Nuts And Bolts. 175 Earthing Of Substation --Excavation Ofearth Pit Of Dia650 Mm & Depth 3000 Mm, Installation Ofearthing Pipe Of 40 Mm Nominal Bore & 4Mm Wall Thickness & Length 2.5 Mtr Long As Per Is 1239.Gi Strip For Neutral Earthing Of Size 25 Mm X 3 Mm For Connection Of Transformer Body, G.O Set & Lightening Arrestor As Per Is 2629 / 85, Gi Nuts & Bolts, Refilled With Earth Enhancement Materials And Earth Chamber Made Of Brick Masonary With Rcc Slab Cover. 176 Pre Fabricated Lt Distribution Box 177 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lightening Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 178 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 179 Danger Plates With Clamps 180 Gi Wire For Anti Climbing 181 Cement Bottoming 1:2:4 Mix As Per Rec Standards 182 Wedge Connector / Pg Clamps 183 Sundary Items 184 Laying Ofht Line On 9 Mtrs.Pcc Poles With Acsr Weasel Conductorat W No 04 Chadwalon Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 185 9 Mtr. Long Pole Pcc ( Wl-300 Kg ) 186 Gi V Cross-Arm / Horizontal With Top Bracket Including Clamp 187 Gi Channel X-Arm Includingclaps And Braces 188 30 Mm² Acsr Conductor 189 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 190 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 191 Galvanized Nuts And Bolts 192 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 193 Danger Plates With Clamp 194 Anti Climbing Devices With Clamps 195 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 196 Aluminium Jointing Sleeves 197 Stone Pad ( 300Mmx300 Mmx75mm ) 198 Laying Oflt Line On 8 Mtrs.Pcc Poles With Acsr Weasel Conductor 3 Phase 4 Wireat W No 04 Chadwalon Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 199 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 200 Gi U-Clamp For Shackle Insulators 201 Shackle Insulator 16 Kn 202 30 Mm² Acsr Conductor 203 Galvanized Nuts And Bolts 204 Danger Plates 205 Anit Climbing Device With Clamps 206 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 207 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 208 Lt Line Spacers 209 Stone Pad 210 Alm.Jointing Sleeves 211 Insertionofpoles &Replacementofold Acsr Weasel Conductorof Lt Lineat W No 04 Chadwal On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 212 30Mm2 Acsr Weaselconductor 213 Gi U Clamp For Shackle Insulator 214 16Kn Polymer Shackle Insulstor 215 Nuts And Bolts 216 Earthing Completed 217 Danger Plate 218 Lt Spacer 219 Stone Pad 220 Stay Set Completed 221 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 222 Detail Of Public Demand- Creation Of 100 Kva Sub-Station Alongiwth Ht / Lt At Village Mukundpur Choudhrian 223 Creationof 100 Kvasub Stationat Mukendpur Choudrian On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 224 11 / 0.433Kv, 100Kva, 3-Phase Distribution Transformers With Bimetallic Terminal Connectors Energy Level-2, ( Al Wound ) , And With Lv Cable Box Having Detachable Aluminium Gland Plate. 225 Gapless Surge Arrestor, 9 Kv , 10 Ka , La With Polymer Housing, Stn. Type 226 11Kv Go, Ab Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type 227 11 Kv Horn Gapfuse Set 3 Phase 200A 228 185 Mm² ( 1Ckt ) Single Phasecable, 1.1K V Grade, Pvc Insulated Stranded Conductor Frls Type 229 9 Mtr. Long Pcc Pole ( Wl-300Kg ) 230 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 231 Gi Channel / Angle / Flat Of Sizes Including Clamps For L.A Set / G.O Set / Horn Gap 232 Galvinized Nuts And Bolts. 233 Earthing Of Substation --Excavation Ofearth Pit Of Dia650 Mm & Depth 3000 Mm, Installation Ofearthing Pipe Of 40 Mm Nominal Bore & 4Mm Wall Thickness & Length 2.5 Mtr Long As Per Is 1239.Gi Strip For Neutral Earthing Of Size 25 Mm X 3 Mm For Connection Of Transformer Body, G.O Set & Lightening Arrestor As Per Is 2629 / 85, Gi Nuts & Bolts, Refilled With Earth Enhancement Materials And Earth Chamber Made Of Brick Masonary With Rcc Slab Cover. 234 Pre Fabricated Lt Distribution Box 235 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lightening Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 236 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 237 Danger Plates With Clamps 238 Gi Wire For Anti Climbing 239 Cement Bottoming 1:2:4 Mix As Per Rec Standards 240 Wedge Connector / Pg Clamps 241 Sundary Items 242 Laying Ofht Line On 9 Mtrs.Pcc Poles With Acsr Weasel Conductorat Mukendpur Choudrian On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 243 9 Mtr. Long Pole Pcc ( Wl-300 Kg ) 244 Gi V Cross-Arm / Horizontal With Top Bracket Including Clamp 245 Gi Channel X-Arm Includingclaps And Braces 246 30 Mm² Acsr Conductor 247 11Kv Polymeric Composite Pin Insulator 12Kv, 5Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 248 11Kv Polymeric Composite Disc Insulator 12Kv, Min Failing Load 45Kn, Lighting Impulse 75Kv Positive And 80Kv Negative, Creepage Distance 320Mm 249 Galvanized Nuts And Bolts 250 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 251 Danger Plates With Clamp 252 Anti Climbing Devices With Clamps 253 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 254 Aluminium Jointing Sleeves 255 Stone Pad ( 300Mmx300 Mmx75mm ) 256 Laying Oflt Line On 8 Mtrs.Pcc Poles With Acsr Weasel Conductor 3 Phase 4 Wireat Mukendpur Choudrian On Turnkey Basis By Way Of Supply, Erection / Installation, Testing, Commissioning Etc Of The Following Material: 257 8 Mtr. Long Pole ( Pcc Wl-200Kg ) 258 Gi U-Clamp For Shackle Insulators 259 Shackle Insulator 16 Kn 260 30 Mm² Acsr Conductor 261 Galvanized Nuts And Bolts 262 Danger Plates 263 Anit Climbing Device With Clamps 264 Earthing Complete By Gi Pipe 40Mm Dia Or Gi Rod 20Mm , 2.5 Mtrs Long Through Gi Strip 265 Galvanised Stay Set With 50X8mm Stay Clamp, Guy Insulator ( 2Nos. ) , Anchor Plate ( 200X 200 X 6 Mm ) , Nut-Bolts, 2 Nos Turn-Buckles, 1.8M Long, 16 Mm Diameter Solid Gs Stay Rod & 7 / 3.15 Mm Dia Gi Stranded Wire Complete 266 Lt Line Spacers 267 Stone Pad 268 Alm.Jointing Sleeves
BOQ
| Sl. No. | Item Description |
| 1 | Detail of Public Demand- Public Demand for Creation of 250 KVA Sub-Station along with HT/LT line Bhallar W.No. Barnoti |
| 2 | Creationof 250 KVASub Station at Bhallar W.No. Barnoti on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 3 | 11/0.433kV, 250 KVA, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, (Al wound ) up to200 KVA, copper WoundandwithLV Cable Box having detachable Aluminium Gland plate. |
| 4 | Gapless Surge Arrestor,9 kV ,10 KA ,LA with polymer housing, Stn. Type |
| 5 | 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 6 | 11 kV Horn GapFuse Set 3 Phase 200A |
| 7 | 185 mm² (1Ckt) Single PhaseCable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 8 | 9 Mtr. Long Pole(WL-300 Kg) |
| 9 | 11KV Polymeric composite Disc Insulator 12kV,min failing load 45KN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 10 | GI Channel/Angle/Flat of sizes including clamps for L.A set/G.O set/Horn Gap |
| 11 | Galvinized Nuts and Bolts. |
| 12 | Earthing of substation --Excavation ofearth pit of dia650 mm & depth 3000 mm, installation ofEarthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 13 | Pre fabricated LT Distribution box |
| 14 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 15 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 16 | Danger Plates with Clamps |
| 17 | GI wire for Anti Climbing |
| 18 | Cement Bottoming 1:2:4 mix as per REC Standards |
| 19 | Sundary Items |
| 20 | Laying ofHT line on 9 Mtrs.PCC poles with ACSR Weasel Conductor at Bhallar W.No. Barnoti on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 21 | 9 Mtr. Long Pole PCC POle(WL-300 Kg) |
| 22 | GI V cross-arm/Horizontal with top Bracket including clamp |
| 23 | GI Channel x-arm includingclaps and braces |
| 24 | 30 mm² ACSR Conductor |
| 25 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 26 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 27 | Galvanized Nuts and Bolts |
| 28 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 29 | Danger Plates with Clamp |
| 30 | Anti Climbing Devices with clamps |
| 31 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 32 | Laying ofLT line on 8 Mtrs.PCC poles with ACSR Weasel Conductor 3 Phase 4 wire at Bhallar W.No. Barnoti on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 33 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 34 | GI U-Clamp for Shackle insulators |
| 35 | Shackle insulator 16 KN |
| 36 | 30 mm² ACSR Conductor |
| 37 | Galvanized Nuts and Bolts |
| 38 | Danger Plates with Clamps |
| 39 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 40 | Detail of Public Demand- Public Demand for Creation of25 KVA Sub-Station along with HT/LT at Village Sahar, Logate |
| 41 | Creation of 25 KVA Sub Station at Sahar on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 42 | 11/0.433kV, 25 KVA, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, (Al wound ), and with LV Cable Box having detachable Aluminium Gland plate. |
| 43 | Gapless Surge Arrestor,9 kV ,10 KA ,LA with polymer housing, Stn. Type |
| 44 | 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 45 | 11 kV Horn GapFuse Set 3 Phase 200A |
| 46 | 50 mm² (1Ckt) Single PhaseCable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 47 | 9 Mtr. Long PCC Pole( WL-300Kg) |
| 48 | 11KV Polymeric composite Disc Insulator 12kV,min failing load 45KN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 49 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 50 | GI Channel/Angle/Flat of sizes including clamps |
| 51 | Galvinized Nuts and Bolts. |
| 52 | Cement Bottoming 1:2:4 mix as per REC Standards |
| 53 | Earthing of substation-Excavation ofearth pit of dia650 mm & depth 3000 mm, installation ofEarthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 54 | Pre fabricated LT Distributionswitch |
| 55 | Danger Plates with Clamps |
| 56 | Sundary Items |
| 57 | GI Barbed wire for anticlimbing |
| 58 | Laying ofHT line on 9 Mtrs.PCC poles with ACSR Weasel Conductor at Sahar on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 59 | 9 Mtr. Long Pole PCC (WL-300 Kg) |
| 60 | GI V cross-arm with top Bracket including clamp |
| 61 | GI Channel x-arm including clamps and braces |
| 62 | 30 mm² ACSR Conductor ( Weasel) |
| 63 | PG Clamps for Weasel Conductor |
| 64 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 65 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 66 | Galvanized Nuts and Bolts |
| 67 | Danger Plates with Clamp |
| 68 | Anti Climbing Devices with clamps |
| 69 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 70 | Stone Pad (300mmx300 mmx75mm) |
| 71 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 72 | Laying ofLT line on 8 Mtrs.PCC poles 3Phase 4 wirewith ACSR Weasel Conductorat Saharon Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 73 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 74 | GI U-Clamp for Shackle insulators |
| 75 | Shackle insulator 16 KN |
| 76 | 30 mm² ACSR WeaselConductor |
| 77 | Galvanized Nuts and Bolts |
| 78 | Danger Plates with Clamp |
| 79 | Anti climbing Devices with Clamp |
| 80 | Earthing Complete bu GI Pipe40mm or GI rod20 mm 2.5 Mtr long through GI Strip |
| 81 | Stone Pad (300mmx300 mmx75mm) |
| 82 | Aluminium Jointing Sleeves |
| 83 | Detail of Public Demand- Public Demand for Shifting of 11 KV line at village Kathua. Smt Mahesh Lata W no 11 Kathua |
| 84 | Shifting of HT line on 9 Mtrs.PCC poles at Village Kathua Smt Mahesh Lata W NO 11 Kathuaon Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 85 | 9 Mtr. Long PCC Pole(WL-300 Kg) |
| 86 | GI V cross-arm with top Bracket including clamp |
| 87 | GI Channel x-arm including clamps and braces |
| 88 | 30 mm² ACSR Conductor ( Weasel) |
| 89 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 90 | Galvanized Nuts and Bolts |
| 91 | Danger Plates with Clamp |
| 92 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 93 | Stone Pad (300mmx300 mmx75mm) |
| 94 | Detail of Public Demand- Public Demand for Creation of100 KVA Sub-Station along with HT/LT at Sukhu Chak |
| 95 | Creationof 100 KVASub Station at Sukhu chackon Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 96 | 11/0.433kV, 100KVA, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, (Al wound ), and with LV Cable Box having detachable Aluminium Gland plate. |
| 97 | Gapless Surge Arrestor,9 kV ,10 KA ,LA with polymer housing, Stn. Type |
| 98 | 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 99 | 11 kV Horn GapFuse Set 3 Phase 200A |
| 100 | 185 mm² (1Ckt) Single PhaseCable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 101 | 9 Mtr. Long PCC Pole( WL-300Kg) |
| 102 | 11KV Polymeric composite Disc Insulator 12kV,min failing load 45KN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 103 | GI Channel/Angle/Flat of sizes including clamps for L.A set/G.O set/Horn Gap |
| 104 | Galvinized Nuts and Bolts. |
| 105 | Earthing of substation --Excavation ofearth pit of dia650 mm & depth 3000 mm, installation ofEarthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 106 | Pre fabricated LT Distribution box |
| 107 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 108 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 109 | Danger Plates with Clamps |
| 110 | GI wire for Anti Climbing |
| 111 | Cement Bottoming 1:2:4 mix as per REC Standards |
| 112 | Wedge Connector/PG Clamps |
| 113 | Sundary Items |
| 114 | Laying ofHT line on 9 Mtrs.PCC poles with ACSR Weasel Conductorat Sukhu chack on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 115 | 9 Mtr. Long Pole PCC (WL-300 Kg) |
| 116 | GI V cross-arm/Horizontal with top Bracket including clamp |
| 117 | GI Channel x-arm includingclaps and braces |
| 118 | 30 mm² ACSR Conductor |
| 119 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 120 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 121 | Galvanized Nuts and Bolts |
| 122 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 123 | Danger Plates with Clamp |
| 124 | Anti Climbing Devices with clamps |
| 125 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 126 | Aluminium Jointing Sleeves |
| 127 | Stone Pad (300mmx300 mmx75mm) |
| 128 | Laying ofLT line on 8 Mtrs.PCC poles with ACSR Weasel Conductor 3 Phase 4 wireat Sukhu chack on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 129 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 130 | GI U-Clamp for Shackle insulators |
| 131 | Shackle insulator 16 KN |
| 132 | 30 mm² ACSR Conductor |
| 133 | Galvanized Nuts and Bolts |
| 134 | Danger plates |
| 135 | Anit Climbing Device with Clamps |
| 136 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 137 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 138 | LT line Spacers |
| 139 | Stone Pad |
| 140 | Alm.Jointing Sleeves |
| 141 | Laying ofLT line on 8 Mtrs.PCC poles with ACSR Weasel Conductor 1 Phase 2 wireat Sukhu chack on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 142 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 143 | GI U-Clamp for Shackle insulators |
| 144 | Shackle insulator 16 KN |
| 145 | 30 mm² ACSR Conductor |
| 146 | Galvanized Nuts and Bolts |
| 147 | Danger plates |
| 148 | Anit Climbing Device with Clamps |
| 149 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 150 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 151 | LT line Spacers |
| 152 | Stone Pad |
| 153 | Alm.Jointing Sleeves |
| 154 | Replacement for old ACSR Weasel Conductorof LT line at Sukhu chack on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 155 | 30mm2 ACSR WeaselConductor |
| 156 | GI U Clamp for shackle insulator |
| 157 | 16KN Polymer shackle insulstor |
| 158 | Galvanized Nuts and Bolts |
| 159 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 160 | Danger plate |
| 161 | LT Spacer |
| 162 | Stone pad |
| 163 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 164 | Detail of Public Demand- Public Demand for Creation of100 KVA Sub-Station along with HT/LT at W No 4 Chadwal |
| 165 | Creationof 100 KVASub Station at W No 04 chadwal on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 166 | 11/0.433kV, 100KVA, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, (Al wound ), and with LV Cable Box having detachable Aluminium Gland plate. |
| 167 | Gapless Surge Arrestor,9 kV ,10 KA ,LA with polymer housing, Stn. Type |
| 168 | 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 169 | 11 kV Horn GapFuse Set 3 Phase 200A |
| 170 | 185 mm² (1Ckt) Single PhaseCable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 171 | 9 Mtr. Long PCC Pole( WL-300Kg) |
| 172 | 11KV Polymeric composite Disc Insulator 12kV,min failing load 45KN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 173 | GI Channel/Angle/Flat of sizes including clamps for L.A set/G.O set/Horn Gap |
| 174 | Galvinized Nuts and Bolts. |
| 175 | Earthing of substation --Excavation ofearth pit of dia650 mm & depth 3000 mm, installation ofEarthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 176 | Pre fabricated LT Distribution box |
| 177 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 178 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 179 | Danger Plates with Clamps |
| 180 | GI wire for Anti Climbing |
| 181 | Cement Bottoming 1:2:4 mix as per REC Standards |
| 182 | Wedge Connector/PG Clamps |
| 183 | Sundary Items |
| 184 | Laying ofHT line on 9 Mtrs.PCC poles with ACSR Weasel Conductorat W no 04 Chadwalon Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 185 | 9 Mtr. Long Pole PCC(WL-300 Kg) |
| 186 | GI V cross-arm/Horizontal with top Bracket including clamp |
| 187 | GI Channel x-arm includingclaps and braces |
| 188 | 30 mm² ACSR Conductor |
| 189 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 190 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 191 | Galvanized Nuts and Bolts |
| 192 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 193 | Danger Plates with Clamp |
| 194 | Anti Climbing Devices with clamps |
| 195 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 196 | Aluminium Jointing Sleeves |
| 197 | Stone Pad (300mmx300 mmx75mm) |
| 198 | Laying ofLT line on 8 Mtrs.PCC poles with ACSR Weasel Conductor 3 Phase 4 wireat W NO 04 Chadwalon Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 199 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 200 | GI U-Clamp for Shackle insulators |
| 201 | Shackle insulator 16 KN |
| 202 | 30 mm² ACSR Conductor |
| 203 | Galvanized Nuts and Bolts |
| 204 | Danger plates |
| 205 | Anit Climbing Device with Clamps |
| 206 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 207 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 208 | LT line Spacers |
| 209 | Stone Pad |
| 210 | Alm.Jointing Sleeves |
| 211 | Insertionofpoles &replacementofold ACSR Weasel Conductorof LT lineat W No 04 Chadwal on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 212 | 30mm2 ACSR WeaselConductor |
| 213 | GI U Clamp for shackle insulator |
| 214 | 16KN Polymer shackle insulstor |
| 215 | Nuts and bolts |
| 216 | Earthing completed |
| 217 | Danger plate |
| 218 | LT Spacer |
| 219 | Stone pad |
| 220 | Stay set completed |
| 221 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 222 | Detail of Public Demand- Creation of 100 KVA Sub-station alongiwth HT/LT at village Mukundpur Choudhrian |
| 223 | Creationof 100 KVASub Stationat Mukendpur Choudrian on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 224 | 11/0.433kV, 100KVA, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, (Al wound ), and with LV Cable Box having detachable Aluminium Gland plate. |
| 225 | Gapless Surge Arrestor,9 kV ,10 KA ,LA with polymer housing, Stn. Type |
| 226 | 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 227 | 11 kV Horn GapFuse Set 3 Phase 200A |
| 228 | 185 mm² (1Ckt) Single PhaseCable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 229 | 9 Mtr. Long PCC Pole( WL-300Kg) |
| 230 | 11KV Polymeric composite Disc Insulator 12kV,min failing load 45KN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 231 | GI Channel/Angle/Flat of sizes including clamps for L.A set/G.O set/Horn Gap |
| 232 | Galvinized Nuts and Bolts. |
| 233 | Earthing of substation --Excavation ofearth pit of dia650 mm & depth 3000 mm, installation ofEarthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 234 | Pre fabricated LT Distribution box |
| 235 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 236 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 237 | Danger Plates with Clamps |
| 238 | GI wire for Anti Climbing |
| 239 | Cement Bottoming 1:2:4 mix as per REC Standards |
| 240 | Wedge Connector/PG Clamps |
| 241 | Sundary Items |
| 242 | Laying ofHT line on 9 Mtrs.PCC poles with ACSR Weasel Conductorat Mukendpur Choudrian on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 243 | 9 Mtr. Long Pole PCC(WL-300 Kg) |
| 244 | GI V cross-arm/Horizontal with top Bracket including clamp |
| 245 | GI Channel x-arm includingclaps and braces |
| 246 | 30 mm² ACSR Conductor |
| 247 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 248 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 249 | Galvanized Nuts and Bolts |
| 250 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 251 | Danger Plates with Clamp |
| 252 | Anti Climbing Devices with clamps |
| 253 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 254 | Aluminium Jointing Sleeves |
| 255 | Stone Pad (300mmx300 mmx75mm) |
| 256 | Laying ofLT line on 8 Mtrs.PCC poles with ACSR Weasel Conductor 3 Phase 4 wireat Mukendpur Choudrian on Turnkey Basis by way of Supply, Erection/Installation, Testing, commissioning etc of the following material: |
| 257 | 8 Mtr. Long Pole(PCC WL-200Kg ) |
| 258 | GI U-Clamp for Shackle insulators |
| 259 | Shackle insulator 16 KN |
| 260 | 30 mm² ACSR Conductor |
| 261 | Galvanized Nuts and Bolts |
| 262 | Danger plates |
| 263 | Anit Climbing Device with Clamps |
| 264 | Earthing Complete by GI Pipe 40mm dia or GI Rod 20mm ,2.5 mtrs long through GI Strip |
| 265 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 266 | LT line Spacers |
| 267 | Stone Pad |
| 268 | Alm.Jointing Sleeves |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender