Supply Erection And Commissioning Of 02 Nos. 50 Cs Afvt Pumps ( P1 And P10 ) , With 02 Nos. Transformers 1.25 Mva And Other Electromechanical Equipments Like Ltdb Panels With Acb, Motors, Starters And Capacitor Bank Of Various Capacity, Cables Of Var, rewari-Haryana

Irrigation Department has published Supply Erection And Commissioning Of 02 Nos. 50 Cs Afvt Pumps ( P1 And P10 ) , With 02 Nos. Transformers 1.25 Mva And Other Electromechanical Equipments Like Ltdb Panels With Acb, Motors, Starters And Capacitor Bank Of Various Capacity, Cables Of Var. Submission Date for this Tender is 07-11-2022. Air Circuit Breaker Tenders in rewari Haryana. Bidders can get complete Tender details and download the document.




Tender Notice

34296164
Corrigendum : Supply Erection And Commissioning Of 02 Nos. 50 Cs Afvt Pumps ( P1 And P10 ) , With 02 Nos. Transformers 1.25 Mva And Other Electromechanical Equipments Like Ltdb Panels With Acb, Motors, Starters And Capacitor Bank Of Various Capacity, Cables Of Var
Open Tender
Indian
Haryana
rewari
07-11-2022

Tender Details

Supply Erection And Commissioning Of 02 Nos. 50 Cs Afvt Pumps ( P1 And P10 ) , With 02 Nos. Transformers 1.25 Mva And Other Electromechanical Equipments Like Ltdb Panels With Acb, Motors, Starters And Capacitor Bank Of Various Capacity, Cables Of Variou

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 21-Oct-2022 Corrigendum Date 07-11-2022

Key Value

Document Fees
INR 15000 /-
EMD
INR 808000.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: Supply, Erection and Commissioning of 02 Nos. 50 Cs AFVT pumps (P1 & P10), with 02 Nos. Transformers 1.25 MVA and other Electromechanical Equipments like LTDB Panels with ACB, Motors, Starters and Capacitor Bank of various capacity, cables of various size at PH JC-3.
Sl. No. Item Description
1Supply, erection and commissioning of 50Cs. Axial flow VT Pump of 760 RPM having static lift 24ft with epoxy coating, incl. welding, etc. complete in all respect as per site requirement and compatible with existing delivery pipe as per approved specification of the deptt.
2Supply, erection and commissioning of solid shaft squirrel cage LT 3 phase 415V induction Motor for continuous duty, vertical flange mounted of 250 HP of 6 pole, 760 rpm, TEFC Motor of IE 2 as per IS 12615. The colour shade shall be RAL 7031, suitable for existing 50Cs pump complete in all respect & as per approved specification of deptt. (as per Annexure-B)
3Supply, erection and commissioning of hollow shaft squirrel cage LT 3 phase 415V induction Motor for continuous duty, vertical flange mounted of 60 HP of 4 pole, 1440 rpm, TEFC Motor of IE 2 as per IS 12615. The colour shade shall be RAL 7031, suitable for 10Cs pump complete in all respect & as per approved specification of deptt. (as per Annexure-B)
4Supply, erection and commissioning of LT Panel in control room of pump house of 2000Amp(should be having enough space for connection of 02 incomer cables from transformer and 01 cable for capacitor bank) with incomer ACB 2000amp 4 pole with 5 nos outgoings each of having MCCB of 630Amp along with D Plug Socket in front side of panel for lighting Load, indicators, relays, meters, push buttons, bus bars & other allied accessories with a stand of MS Channel (1 feet up from floor) & degree of protection as per IP-54 as per approved technical specification.
5Supply, erection and commissioning of Capacitor bank of 240 KVAR capacity IP-54 with 04 step APFCR, Suitable Size MCCB, Selector Switch, duty contractors, discharge resistors, digital display instruments with XLPE insulated Armoured cable of suitable size of length 35ft to connect the capacitor bank with existing LT Panel& other allied accessories for automatic as well as manual operation of Capacitor Bank & as per design & load of existing panelwith a stand of MS Channel/angle (1 feet height from floor level) & as per approved specification of deptt. (as per Annexure-C)
6Supply, erection and commissioning of 75HP Fully Automatic ATS Starter with a MCCB of 250amp, 415 V, 50 Hz with air breaker power contactors of 200A / 110A / 80A with meter, relays, indicators complete in all respect, with degree of protection IP 54 including connection and small item like thimble, Nut Bolts Lugs etc. with a stand of MS Angle (50x50x6mm) of 1 feet height from floor level and with allied accessories as per makes and specifications approved in Annexure-C attached.
7Supply, erection and commissioning of 1.25 MVA, three-phase 11 kV/433-250V, dry type, naturally air cooled, copper wound, outdoor type distribution transformers as per IS 2026 and as per latest electrical specifications/ISS along with all accessories/fittingslike be directional rollers, WTI scanner with 3 PT-100 sensors, connection boxes, lugs, nut bolts, cable kit, thimbles, tap changer (± 5%) and complete with base channel mounting, provision for support of cable at transformer near thimbles etc. including any left over item, complete in all aspect including platform with wheelsand as per requirement at site.
8Supply, erection and commissioning of Capacitor bank of 400 KVAR capacity with resin cast insulation to be coupled with 1.25 MVA transformer to compensate its losses, 11 KV complete with cable connection. & other allied accessories for automatic as well as manual operation of Capacitor Bank
9Providing and fixing of chemical earthing by digging 200mm bore, 20 feet depth complete with copper electrode, copper strip for neutral of each transformer and coke & salt etc along with name plate complete as per requirement.
10Providing and fixing of chemical earthing by digging 200mm bore, 20 feet depth complete with GI electrode with GI strip (02 nos. for each transformer and 02 nos. for LTDB panels and motors in the Pump House) and coke & salt etc. along with name plate complete as per site requirement.
11Supply and laying of 11Kv Aluminum Conductor, XLPE insulated, Armored cable 3 core 120 mm2 HT cable for connection of VCB to transformer by fixing suitable size cable boxes with thimble at both ends.
12Supply and laying of 1000 mm2 LT cable single core Aluminum Conductor, XLPE insulated, Armored cable (from Transformer to Motor Control Centre) with thimble at both ends.
13Supply and laying of 400 mm2LT cable 3.5 core Aluminum Conductor, XLPE insulated, Armored cable from Motor Control Centre to Starter Panel with dismantling of old cables from duct with thimble at both ends.
14Providing and fixing of Lightening Arrester with lightening striking counter within protection radius of 100 mtr alongwith its earthing as per site requirement.
15Supply and laying of 120 mm2LT cable 3.5 core Aluminum Conductor, XLPE insulated, Armored cable from ACB to Starter Panel of Nikhri disty with thimble at both ends.
16Make of Pumps-Kirloskar, Wilo, Flowmore, WPIL, Xylem, GITA(upto 60 Cs) & Sintech (upto 60 Cs). Make of Motors - LV Motor- Marathon, ABB, Kirloskar Electric, Siemans, Crompton, Jyoti, BCH, Bharat Bijli. Make of Panels - LV Panel- Siemans, ABB, L&T, Schneider, G.E. C&S, Havells, BCH, Legrand, AE & PSG(upto 30HP). Make of Transformer- ABB, Siemans, Schneider & G.E. Terms & Conditions:- 1. The tender rate will be inclusive all taxes as applicable including GST. 2. The tender rate will be for F.O.R. destination and inclusive of all incidental charges, enroute & at destination. Nothing extra shall be paid separately. 3. WWC@1% will be deducted from the each bill of the agency. 4. The rate should be inclusive carriage, fitting and allied parts complete in all respect with left over items (if any) as per site requirement. 5. Goods which to be used / supplied should be as per sample and conforming to the site condition & also conforming to I.S. Specification. 6. Department will not be responsible for non submission of BOQ / Bid Document online by due date, due to any fault of internet/ E-tendering. 7. Third Party Testing by T.P.I.A. will be carried out in the presence of departmental representative at the manufacturer premises and cost of the same will be borne by the successful agency. 8. The warranty of the work shall be as per Service Level agreement from the date of commissioning. 9. Time period for completion of work 8 Months from the issue date of order to proceed with the work. 10. Payment schedule, as per bidding documents & 70% payment be made as per pro-rata basis. 11. Payment shall be made on finished goods and not on casting only. 12. The material will be supplied as per drawing and newly approved technical specifications laid down in tender documents & subsequent submission by bidder in this regard. 13. Successful agency will submit drawing of the work within week period from the date of approval of rate by competent authority. 14. Authorization from OEM (Pump, Motor, Panel & Transformer) be attached if tenderer is not a manufacturer. 15. Panels be manufactured by original manufacturer either by approved brands themselves or their authorized original equipment manufacturers under their brand name. The inspection is also allowed at their channels partner’s work with the condition that all drawings / test certificates shall be from the original equipment manufacturer. System house of approved brand are not acceptable and rating IP 54. 16. Each page of bid book will be signed by the tenderer as a token of acceptance of terms and conditions. 17. Bidders may visit to the sites before quoting the tender rates. 18. Bidders should have executed similar nature work in any Center Government / State Government/ Public Sector Undertaking / Central Autonomous Body for minimum value equivalent to 50 % of quoted value or 2 works of30 % of quoted value in last 3 years alongwith existing criteria as per bid i.e. bidder should have completed at least 25% of quantity of similar nature work. 19. ln case, the material offered for inspection by the firm fails to meet the specifications stipulated in NIT/order/Contract and the samples are rejected by the Inspecting Committee, the Department will have the right to levya penalty at 0.1% of the total value of that particular item. 20. Bidders who will be rejected during technical scrutiny, will submit their representation within 5 days from issue of minutes of TSC. 21. The bidders must create their contractor ID on HEW Portal (https://works.haryana.gov.in ) and accordingly upload the contractor profile summary in bidding documents.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail