Tender Details

Hv Capacitor Bank And Apfc Panel Design, Engineering, Manufacturing, Procurement Of Materials And Bought Out Components, Assembly At Shop, Testing At Manufacturers Works, Inspection By Tpia, Packing, Supply Of Hv Capacitor Bank And Apfc Panel , 6.6 Kv, 4000 Kvar Indoor Type Capacitor Bank ( 4 Steps: 2000 Kvar+1000 Kvar+2 Nos. Of 500 Kvar ) Along With Isolator & Earth Switch, Series Reactor ( 6% ) , Residual Voltage Transformer ( Rvt ) , Lightning Arrestor, Automatic Power Factor Controller Panel ( Apfc ) , Necessary Relay, Potential Transformer And Current Transformer ( Summation Ct ) As Required And All Associated Components & Accessories. The Apfc Panel Shall Be Communicable With The Substation Electrical Control System ( Ecs ) As Per Details Attached Herein. , Mandatory Spares As Per Mr , Third Party Inspection Charges , Transportation: Lumpsum Inland Transportationby Road Of All Supplies From Vendor’S Works / Shop To Project Site, Numaligarh Refinery, Golaghat, Asaam / Rail Transportation Up To Nmgs / Numaligarh Refinery Project Siding. ( Excluding Gst ) , Post Warranty Annual Maintenance ( For First ( 1St ) Year After Expiry Of Warranty / Defect Liability Period ) : Pwamc Visits Through Oem For 3 Years After The Completion Of The Warranty / Defect Liability Period As Per Details Mentioned In Mr. Bidder To Consider Minimum 2 Visits Per Year, For Further Detail Refer To Mr Document. , Post Warranty Annual Maintenance ( For Second ( 2Nd ) Year After Expiry Of Warranty / Defect Liability Period ) : Pwamc Visits Through Oem For 3 Years After The Completion Of The Warranty / Defect Liability Period As Per Details Mentioned In Mr. Bidder To Consider Minimum 2 Visits Per Year, For Further Detail Refer To Mr Document. , Post Warranty Annual Maintenance ( For Third ( 3Rd ) Year After Expiry Of Warranty / Defect Liability Period ) : Pwamc Visits Through Oem For 3 Years After The Completion Of The Warranty / Defect Liability Period As Per Details Mentioned In Mr. Bidder To Consider Minimum 2 Visits Per Year, For Further Detail Refer To Mr Document. , Unit Rate Forsupervision Sevices Of Erection And Commissioning / Performance Testingas Per Details Mentioned In Material Requisition For Quoted Items As Per Enclosed Instructions To Vendor Per Diem Charges Upto 8 Hrs On Normal Working Days. ( Bidders To Quoteunit Rate For Diem Charges ) , Unit Rate Forsupervision Sevices Of Erection And Commissioning / Performance Testingas Per Details Mentioned In Material Requisition For Quoted Items As Per Enclosed Instructions To Vendor Overtime Rate Per Hour ( Beyond Normal 8 Hours On Normal Working Days ) . ( Bidders To Quote Over Timerate Per Hour ) , Unit Rate Forsupervision Sevices Of Erection And Commissioning / Performance Testingas Per Details Mentioned In Material Requisition For Quoted Items As Per Enclosed Instructions To Vendor Overtime Rate Per Hour For Work On Weekly Off Days / Holidays ( As Applicable To Refinery Site ) . ( Bidders To Quote Over Timerate Per Hour ) => Limited

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 04-Oct-2022 Corrigendum-1 Date 25-10-2022
2 20-Oct-2022 CORRIGENDUM-3 Date 02-11-2022
3 20-Oct-2022 Corrigendum-2 Technical Bid 02-11-2022
4 02-Nov-2022 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 09-11-2022
5 10-Nov-2022 Corrigendum-4 Date 14-11-2022
6 10-Nov-2022 Corrigendum-5 Other 14-11-2022

Key Value

Document Fees
Refer document
EMD
Refer document
Tender Value
Refer document

BOQ Items

Name of Work: Design, engineering, procurement, fabrication, inspection, testing, transportation, documentation and supply of the HV CAPACITOR BANK AND APFC PANELto be installed at Numaligarh Refinery Limited(NRL),Assam including Erection & Commissioning Spares, Mandatory Spares , Special Tools and tackles, Supervision & Training charges at site as per the enclosed Tender standard specifications, Job specification, data sheets etc. and other codes and standards attached or referred as per Material Requisition for Numailgarh Refinery Limited, Golaghat, Assam, India.
Sl. No. Item Description
16.6 kV, 4000 kVAR Indoor type Capacitor Bank (4 steps: 2000 kVAR+1000 kVAR+2 nos. of 500 kVAR) along with Isolator & Earth Switch, Series Reactor (6%), Residual Voltage Transformer (RVT), Lightning Arrestor, Automatic Power Factor Controller Panel (APFC), necessary Relay, Potential Transformer and Current Transformer (Summation CT) as required and all associated components & accessories. The APFC Panel shall be communicable with the substation Electrical Control System (ECS) as per details attached herein.
2Mandatory Spares as per MR
3THIRD PARTY INSPECTION CHARGES
4TRANSPORTATION: Lumpsum Inland transportationby road of all supplies from Vendor’s works / shop to Project site, Numaligarh Refinery, Golaghat, Asaam/ Rail Transportation up to NMGS/Numaligarh Refinery Project Siding.( Excluding GST)
5Post Warranty Annual Maintenance(For First (1st) year after expiry of warranty /defect liability period) : PWAMC visits through OEM for 3 years after the completion of the warranty /defect liability period as per details mentioned in MR. Bidder to consider minimum 2 visits per year, for further detail refer to MR Document.
6Post Warranty Annual Maintenance(For Second (2nd) year after expiry of warranty /defect liability period) : PWAMC visits through OEM for 3 years after the completion of the warranty /defect liability period as per details mentioned in MR. Bidder to consider minimum 2 visits per year, for further detail refer to MR Document.
7Post Warranty Annual Maintenance(For Third (3rd) year after expiry of warranty /defect liability period) : PWAMC visits through OEM for 3 years after the completion of the warranty /defect liability period as per details mentioned in MR. Bidder to consider minimum 2 visits per year, for further detail refer to MR Document.
8Unit rate forSupervision Sevices of erection and commissioning / Performance testingas per details mentioned in material requisition for quoted items as per enclosed instructions to vendor Per Diem charges upto 8 hrs on normal working days. ( BIDDERS TO QUOTEUNIT RATE FOR DIEM CHARGES )
9Unit rate forSupervision Sevices of erection and commissioning / Performance testingas per details mentioned in material requisition for quoted items as per enclosed instructions to vendor Overtime rate per hour (beyond normal 8 hours on normal working days). ( BIDDERS TO QUOTE OVER TIMERATE PER HOUR )
10Unit rate forSupervision Sevices of erection and commissioning / Performance testingas per details mentioned in material requisition for quoted items as per enclosed instructions to vendor Overtime rate per hour for work on weekly off days / holidays (as applicable to Refinery Site). ( BIDDERS TO QUOTE OVER TIMERATE PER HOUR )
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail