Consultancy Services For Feasibility Study And Preparation Of Dpr For 4-Laning Of Nangal-Anandpur Sahib-Kiratpur Sahib Of Nh-503 Extn. ( 32.83 Km ) In The State Of Punjab, Kiratpur-Punjab

Ministry Of Road Transport And Highways has published Consultancy Services For Feasibility Study And Preparation Of Dpr For 4-Laning Of Nangal-Anandpur Sahib-Kiratpur Sahib Of Nh-503 Extn. ( 32.83 Km ) In The State Of Punjab. Submission Date for this Tender is 07-11-2022. Consultancy Service Tenders in Kiratpur Punjab. Bidders can get complete Tender details and download the document.




Tender Notice

34080522
Corrigendum : Consultancy Services For Feasibility Study And Preparation Of Dpr For 4-Laning Of Nangal-Anandpur Sahib-Kiratpur Sahib Of Nh-503 Extn. ( 32.83 Km ) In The State Of Punjab
Indian
Punjab
Kiratpur
07-11-2022

Tender Details

Consultancy Services For Feasibility Study And Preparation Of Dpr For 4-Laning Of Nangal-Anandpur Sahib-Kiratpur Sahib Of Nh-503 Extn. ( 32.83 Km ) In The State Of Punjab

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 11-Oct-2022 Corrigendum_I Other 07-11-2022

Key Value

Document Fees
INR 5000 /-
EMD
Refer document
Tender Value
Refer document

BOQ Items

Name of Work:Consultancy Services for Feasibility Study & Preparation of DPR for 4-laning of Nangal-Anandpur Sahib-Kiratpur Sahib of NH-503 Extn. (32.83 Km) in the State of Punjab
Sl. No. Item Description
1I. Remuneration for Local Staff (Including per diem allowance) Profesional Staff
2Team Leader cum Senior Highway Engineer
3Senior Bridge Engineer
4Highway cum Pavement Engineer
5Meterial cum Geotechnical Engineer - Geologist
6Senior Survey Engineer
7Traffic and Safety Expert
8Environmental Specilist
9Quantity Surveyor / Documentation Expert
10Land Acquistion Expert
11Utility Expert
12Sub-Total-1
13SUB-PROFESSIONAL STAFF :(To be assessed by consultant as per requirement of assignment and one sub professional be a fresh graduate)
14Sub-Professional-1
15Sub-Professional-2
16Sub-Professional-3
17Sub-Professional-4
18Sub-Professional-5
19Sub-Professional-6
20Sub-Professional-7
21Sub-Total-2
22Total(Sub Total 1 + Sub Total 2)
23II. SUPPORT STAFF
24Office Manager
25Typist
26Office Boy
27Night Watch men
28Total:
29III. Transportation (Fixed Costs)
30The vehicles provided by the consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. A. For use of consultants
31Total:
32IV. Duty Travel to Site(Fixed Costs):
33Duty Travel to Site (LS)
34Total:
35V. Office Rent (Fixed Costs) The rent cost includes maintenance, cleaning, repairing etc. (Rate per Month)
36Office Rent (Fixed Costs)
37Total:
38VI. OFFICE SUPPLIES, UTILITIES AND COMMUNICATIONS (Fixed Costs)
39Office Supplies
40Drafting Supplies
41Computer Running Costs
42Domestic and International Communication
43Total:
44VII. OFFICE FURNITURE AND EQUIPMENT (Rental)
45Office Furniture and Ecquipment (LS)
46Total:
47VIII. REPORTS & DOCUMENTS PRINTING
48Monthly report (3 copies per Month)
49Inception Report & QAP
50Environment and Social Impact Screening Report
51Draft Feasibility Report
52Final Feasibility Report
53Strip Plan with LA Reports
54Draft LA and Clearances I Report
55Final LA and Clearances I Report
56Draft Environmental Assessment Report & RAP
57Final Environmental Assessment Report and RAP
58Draft Detailed Design Report & Drawings etc.
59Draft EMP
60Draft Bidding Documents
61Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc.
62Final EMP.
63Final Bidding Documents
64Draft 3(a),3(A) and 3(D) notification for land acquisition (3 copies each)
65LA & Clearances II Report
66Total:
67IX. Survey and Investigation: A. Topographical Survey (Fixed Rate)
68Topographic Survey including hire charges for equipment and supply of survey teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer.
69Detailed topographic surveys using mobile / aerial LiDAR or better Technology
70B. Investigation (Fixed Cost)
71Road and Bridge Inventory
72FWD Test and Pavement Evaluation
73Roughness Survey
74Axle Load Survey
75Material Survey and Investigation
76Sub-grade Investigation
77Traffice Survey
78Socio-economic & Census Survey/Studies
79Land Acquisition Studies
80Any other Investigations/Surveys
81Sub-Soil Investigation (Boring) Note:*Quantities of boring shall be taken from Financial Proposal Form No.V. for financial evaluation, the sequantities and rates quoted by the consultant will be considered. However, payment shall be made on the actual quantity of boring at rates quoted above by the consultant, which may be substantially more or less than the estimated quantities.
82a) Boring in all type of soils (other than hard rock)
83b) Boring in hard rock
84Total:
85C. Network Survey and GPR
86Network Survey of the existing Highways as a repository for civil works as per directions from Authority.
87GPR Survey for detection of under ground utilities
88Total:
89X. Cost of Supply and Fixing Boundary pillars
90Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967: Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed atan interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/ or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval. (lumpsum )
91Total:
92XI. Land Acquisition Team including support staff and logistics/ transportation. A. Land Acquisition Team including support staff :
93Ex-Land Revenue Inspector/ Officer or equivalent
94Ex-Kanoogo/Girdwar or equivalent
95Ex-Patwari or Equivalent
96Typist
97Peon
98Number of Land acquisition Teams (One Only)
99Grand Total for All Land acquisition Teams(A)
100B. Logistics for Land Acquisition Team
101Computer including necessary peripherals (1 Nos)
102Printers (1 Nos)
103Vehicles (Bolero or Equivalent) with monthly running limit of 3000 km (1 Nos)
104Number of Land acquisition Teams (One Only)
105Grand Total (B)
106Grand Total for All Land acquisition Teams and Logistics (A) + (B)
107Note: The consultant shall provide one land acquisition expert along with allied team and supporting logistic as envisaged in clause 5.1.5.1 of TOR for easch 100 km stretches proposed for DPR preparation or part thereof (For example total length of package is 343 km, there will be four team).
108Estimate of costs for Expatriate consultants (in Indian Rupees) I. REMUNERATION OF EXPATRIATE STAFF including per diem allowances.
109Staff
110Sub-Professional-1
111Sub-Professional-2
112Sub-Professional-3
113Sub-Professional-4
114Sub-Professional-5
115Sub-Professional-6
116Sub-Professional-7
117Sub-Total-I
118II. Mobiliation and Demobilization
119A. International Airfares (Fixed costs)
120B. Inland Travel in Home Country (Fixed costs)
121C. Other Misscexpenses (like DA, internal travel expenses other incidentals)
122Sub-Total-II
123Total (I+II)
124Total cost net of Tax
125Taxes and Duties
126A. Income Tax (Expatriate)
127B. Other Taxes/Duties (if any) Specify clearly
128Total
129Total cost net of Goods and service Tax **Total cost net of Goods and Service Tax shall be considered for financial evaluation.
130Goods and service Tax
131TOTAL COSTS (Including GST)
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail