| 1 | Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) - For a lead upto 5 KM |
| 2 | Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) - Above 5 KM of lead of every KM |
| 3 | Transportation of all types and sizes of poles and other associated materials from road side to pole pit and vice versa upto 0.50 KM |
| 4 | Transporting of distribution transformer / line materials from stores to office / site upto 10 KM distance by engaging 1 Ton capacity Minidor (Lorry) |
| 5 | Transporting of distribution transformer / line materials from stores to office / site above 10 KM distance by engaging 1 Ton capacity Minidor (Lorry) |
| 6 | Transporting of conductors of all sizes from road side to pit locations upto one KM of Conductor |
| 7 | Loading of REC, RCC, PSC pole upto 8.00 m length |
| 8 | Loading of all REC, RCC, PSC pole above 8.00 m length |
| 9 | Loading of metal poles all sizes |
| 10 | Unloading of REC, RCC, PSC pole upto 8.00 m length |
| 11 | Unloading of all REC, RCC, PSC pole above 8.00 m length |
| 12 | Unloading of metal poles all sizes |
| 13 | Loading of distribution transformer upto 100 KVA |
| 14 | Loading of distribution transformer above 100 KVA and upto 500 KVA |
| 15 | Unloading of distribution transformer upto 100 KVA |
| 16 | Unloading of distribution transformer above 100 KVA and upto 500 KVA |
| 17 | Loading of conductor |
| 18 | Unloading of conductor |
| 19 | Loading of iron & steel items |
| 20 | Unloading of iron & steel items |
| 21 | Loading of line materials |
| 22 | Unloading of line materials |
| 23 | Loading of 11 KV strain disc |
| 24 | Unloading of 11 KV strain disc |
| 25 | Loading of LT pin insulator, shackle, guy shackle, LT pin, metal parts, HT pin etc., |
| 26 | Unloading of LT pin insulator, shackle, guy shackle, LT pin, metal parts, HT pin etc., |
| 27 | Excavation & backfilling of pole pit for pole upto 8.00 m length by using JCB / manual |
| 28 | Excavation & backfilling of pole pit for pole above 8.00 m length by using JCB / manual |
| 29 | Excavation & backfilling of pole pit in hard soil (common to all size of poles) |
| 30 | Excavation & backfilling of pole pit in rocky area (common to all size of poles) by blasting / manual |
| 31 | Excavation & backfilling of structure pole pit 3 x 3 x 6 feet by using JCB or Manual for single pole DT structure |
| 32 | Erection of RCC, REC, PSC pole upto 8.00 m length by using crane / manual |
| 33 | Erection of RCC, REC, PSC pole above 8.00 m length by using crane / manual |
| 34 | Erection of metal support above 9 m / RSJ / rail pole / tubular pole |
| 35 | Mass concreting of pole with 1:4:8 mix using 40 mm jally including curing (material + labour) |
| 36 | Sleeve concreting with 1:4:8 mix using 40 mm jally including curing (material + labour) |
| 37 | Stay concreting with 1:4:8 mix using 40 mm jally including curing (material + labour) |
| 38 | Earthing of pole with GI wires 4 or 6 SWG by coil earthing |
| 39 | Provision of spike including earthing arrangement |
| 40 | Pipe earthing including excavation of earth pit and fixing earth pipe 3 m length |
| 41 | Excavation & backfilling of stay pit of 4.5\" to 5 feet depth using JCB / Manual |
| 42 | Excavation & back filling of stay pit per location - hard rock requires blasting |
| 43 | Excavation & back filling of stay pit per location - hard rock without blasting |
| 44 | Excavation & back filling of stay pit per location - medium rock and dense medium rock requires blasting |
| 45 | Erection of stay set complete with fixing up stay wire Eye, Bow, Guy Shackle, Binding etc. |
| 46 | Erection of additional stay in the same stay rod, excluding excavation of stay pit and burial of stay rod |
| 47 | Replacement of stay rod only (including stay pit excavation & refilling & erection) |
| 48 | Replacement of guy shackle only in existing stay |
| 49 | Fixing of V cross arm 3.5 feet |
| 50 | Fixing of V cross arm 4.5 feet |
| 51 | Fixing of LT single phase cross arm |
| 52 | Fixing of LT 3 phase cross arm |
| 53 | Fixing of HT / LT TI fitting |
| 54 | Fixing of HT pin insulator with pin 11 KV |
| 55 | Fixing of HT pin insulator with pin 22 KV |
| 56 | Fixing of LT pin insulator |
| 57 | Fixing of HT disc 11 KV |
| 58 | Fixing of HT disc 22 KV |
| 59 | Fixing of shackle |
| 60 | Fixing of aluminium knob |
| 61 | Fixing of HT LAS (3 Nos.) |
| 62 | Fixing of LT LAS (3 Nos.) |
| 63 | Fixing of guarding cross arm |
| 64 | Fixing of tapping channel cross arm |
| 65 | Fixing of double channel cross arm |
| 66 | Fixing of open type fuse unit |
| 67 | Paving and stringing of conductor of sizes upto 7/2.59 mm ACSR or other equivalent conductor (for Route Length per Phase) |
| 68 | Paving and stringing of conductor of above 7/2.59 mm ACSR or other equivalent conductor upto 7/3.35 mm ACSR or other equivalent conductor (for Route Length per Phase) |
| 69 | Paving and stringing of conductor of 7/4.09 mm ACSR or other equivalent conductor (for Route Length per Phase) |
| 70 | Paving and stringing of conductor of one run of PVC cable line of all sizes with GI wire and reel insulator |
| 71 | Provision of guarding arrangement with two numbers earth pits excluding stay set erection - Flat guarding |
| 72 | Provision of guarding arrangement - Split neutral guarding |
| 73 | Erection of 11 / 22 KV AB switch (Horizontal) |
| 74 | Erection of 11 / 22 KV AB switch (Vertical) |
| 75 | Erection of HG Fuse Set, 3 Nos. (in Double Pole or Single Pole Structure) |
| 76 | Erection of top channel for double pole DT structure |
| 77 | Erection of bed channel 2 Nos. for double pole DT structure |
| 78 | Erection of belting angle 2 Nos. for double pole DT structure |
| 79 | Structure earthing complete with 3 pits and earth loops for double pole DT structure |
| 80 | Feeder arrangements with open type fuse unit for 2 feeders for double pole DT structure |
| 81 | HT jumpering complete for double pole DT structure |
| 82 | Painting of all clamps and other iron materials and painting of structure pole for double pole DT structure |
| 83 | LT bus arrangement for double pole DT structure |
| 84 | Fixing of support insulator angle and erection of 3 Nos. pin insulator for double pole DT structure |
| 85 | Fixing of danger board for double pole DT structure |
| 86 | DT yard cleaning and making uniform surface for double pole DT structure |
| 87 | Erection of double pole DT structure complete as per TNEB standard including painting, feeders arrangement, colour washing of poles etc., fixing of HT / LT LAS and jumpering, 3 Nos. earth pits with earth trough except erection of DT |
| 88 | Erection of tapping channel for single pole DT structure |
| 89 | Erection of transformer bed structure for single pole DT structure |
| 90 | Structure earthing complete with 3 pits and earth loops for single pole DT structure |
| 91 | Fixing of MCD box / 2 Nos. open type fuse unit arrangements for single pole DT structure |
| 92 | HT jumpering complete for single pole DT structure |
| 93 | Painting of all clamps, other materials and painting of structure pole for single pole DT structure |
| 94 | LT cable arrangement for single pole DT structure |
| 95 | Fixing of danger board for single pole DT structure |
| 96 | Erection of central supporting arrangement for single pole DT structure |
| 97 | Erection of 11 KV single pole structure completewithout centre support without erection of DT |
| 98 | Erection of 11 KV single pole structure complete with centre support without erection of DT |
| 99 | Erection of distribution transformer at structure - Upto 25 KVA |
| 100 | Erection of distribution transformer at structure - Above 25 KVA to 100 KVA |
| 101 | Erection of distribution transformer at structure - Above 100 KVA to 250 KVA |
| 102 | Erection of distribution transformer at structure - 500 KVA and above |
| 103 | Erection of Intergrated DT Metering Arrangements / Whole Current Meter |
| 104 | Fixing of Modem including accessories |
| 105 | Erection of metering set 11 KV / 22 KV |
| 106 | Erection of DP structure with stay as per TNEB standard including fixing of top channel, cross bracing, concreting, painting, colour washing etc. - With 11 KV AB switch using all types of poles of size 9 m and above length |
| 107 | Erection of DP structure with stay as per TNEB standard including fixing of top channel, cross bracing, concreting, painting, colour washing etc. - With 22 / 33 KV AB switch using all types of poles of size 9 m and above length |
| 108 | Erection of single pole DP complete and with single earth |
| 109 | Dismantling of RCC, REC, PSC & metal pole of all sizes including the closing of the pit |
| 110 | Destruction of pole concreting at site |
| 111 | Retrieving grill from deteriorated RCC pole |
| 112 | Breaking the mass concrete of all supports |
| 113 | Dismantling of stay set complete including stay rod |
| 114 | Dismantling of stay set complete without stay rod |
| 115 | Dismantling of conductor of size upto 7/2.59 mm including transporting the conductors to the nearest road side and stocking in coils |
| 116 | Dismantling of conductor of size above 7/2.59 mm and upto 7/3.35 mm including transporting the conductors to the nearest road side and stocking in coils |
| 117 | Dismantling of conductor of size 7/4.09 mm including transporting the conductors to the nearest road side and stocking in coils |
| 118 | Releasing and reerection (resagging) of one run of all sizes of conductor (for Route Length per Phase) |
| 119 | Resagging of lines for all sizes at cut point location per wire / span |
| 120 | Dismantling of V cross arm 3.5 feet |
| 121 | Dismantling of V cross arm 4.5 feet |
| 122 | Dismantling of LT single phase cross arm |
| 123 | Dismantling of LT 3 phase cross arm |
| 124 | Dismantling of HT / LT TI fitting |
| 125 | Dismantling of HT pin insulator with pin 11 KV |
| 126 | Dismantling of HT pin insulator with pin 22 KV |
| 127 | Dismantling of LT pin with insulator |
| 128 | Dismantling of HT disc 11 KV with metal parts |
| 129 | Dismantling of HT disc 22 KV with metal parts |
| 130 | Dismantling of LT shackle with metal parts |
| 131 | Dismantling of aluminium knob |
| 132 | Dismantling of HT LAS (3 Nos.) |
| 133 | Dismantling of LT LAS (3 Nos.) |
| 134 | Dismantling of guarding cross arm |
| 135 | Dismantling of tapping channel cross arm |
| 136 | Dismantling of double channel cross arm |
| 137 | Dismantling of open type fuse unit |
| 138 | Dismantling of 11 / 22 KV AB switch (Horizontal) |
| 139 | Dismantling of 11 / 22 KV AB switch (Vertical) |
| 140 | Dismantling of HG Fuse Set (3 Nos.) |
| 141 | Dismantling of top channel from double pole DT structure |
| 142 | Dismantling of bed channel 2 Nos. from double pole DT structure |
| 143 | Dismantling of belting angle 2 Nos. from double pole DT structure |
| 144 | Dismantling of structure earthing complete of double pole DT structure |
| 145 | Dismantling of feeder arrangements with open type fuse unit 2 Nos. from double pole DT structure |
| 146 | Dismantling of HT jumpering complete of double pole DT structure |
| 147 | Dismantling of LT bus arrangement from double pole DT structure |
| 148 | Dismantling of support insulator angle and 3 Nos. pin insulator from double pole DT structure |
| 149 | Dismantling of danger board from double pole DT structure |
| 150 | Dismantling of double pole transformer structure materials complete set and transporting the same from the location to the road side |
| 151 | Dismantling of tapping channel from single pole DT structure |
| 152 | Dismantling of transformer bed structure from single pole DT structure |
| 153 | Dismantling of structure earthing complete from single pole DT structure |
| 154 | Dismantling of MCD box / 2 Nos. open type fuse unit arrangements from single pole DT structure |
| 155 | Dismantling of HT jumpering complete of single pole DT structure |
| 156 | Dismantling of LT cable arrangement from single pole DT structure |
| 157 | Dismantling of danger board from single pole DT structure |
| 158 | Dismantling of central supporting arrangement from single pole DT structure |
| 159 | Dismantling of 11 KV single pole structure completewithout centre support |
| 160 | Dismantling of 11 KV single pole structure complete with centre support |
| 161 | Releasing of DT below 200 KVA from structure |
| 162 | Releasing of DT 200 KVA & above but below 500 KVA from structure |
| 163 | Releasing of DT 500 KVA from strcuture |
| 164 | Releasing of metering set 11 KV / 22 KV from strcuture |
| 165 | Manufacturing / altering of clamp |
| 166 | Drilling of hole in the structure materials, clamps, etc., |
| 167 | AB switch or open type side arm stud cutting and drilling holes |
| 168 | Manufacturing of earth pipe clamp for structure including of drilling holes and welding with earth pipe |
| 169 | Fixing of one set of street light fixture with clamp and fitting of all sizes including cable jumpering and including transportation |
| 170 | Provision of street light switching arrangement including fixing of meter, wiring & service board etc. |
| 171 | Fixing of street light |
| 172 | Dismantling of street light switch box with pipe |
| 173 | Dismantling of one set of street light fixture with clamp and fitting of all types |
| 174 | Erection of MV / sodium vapour lamp including wiring and fixing at street light location including transportation |
| 175 | Dismantling of MV / sodium vapour lamp including wiring |
| 176 | Releasing and erection single phase SC wire [during conductor or support change] |
| 177 | Releasing and erection 3 phase SC wire [during conductor or support change] |
| 178 | Fixing and Dismantling of Single Phase Meter |
| 179 | Fixing and Dismantling of Three Phase Meter |
| 180 | Painting of distribution transformer of all capacities (paint to be supplied by the TANGEDCO) including cleaning of DT |
| 181 | Painting of iron pole up to 36 ft length with double coats including cost of paint |
| 182 | Painting of iron pole up to 40 ft length with double coats including cost of paint |
| 183 | Painting of structure materials, distribution transformers with aluminium paint of structure poles and writing of transformer details (Brush to be owned by the contractor) (Paint to be supplied by Department) |
| 184 | Numbering of pole including base painting and with cost of paint |
| 185 | Service connection details painting |
| 186 | Setting right the leaning pole in HT / LT at pin point location |
| 187 | Setting right the leaning pole in HT / LT at cutpoint location |
| 188 | Jungle clearance such as kattu karuvai in the various area without uprooting |
| 189 | Jungle clearance such as kattu karuvai in the various area with uprooting |
| 190 | Clearing of tree branches of coconut tree |
| 191 | Clearing of tree branches of neem, tamarin, country, etc., |
| 192 | Leveling of ground using Bul Dozer |
| 193 | Clearing of branches / trees with JCB |
| 194 | Engaging crane per hour (for handling of poles, metering set, DT, etc.,) |
| 195 | Engaging JCB per hour (for extension works & maintenance works etc.,) |
| 196 | Fencing of distribution transformer structure at road side, fabrication and erection (including all materials) |
| 197 | Providing of line spacers in LT line 1 phase |
| 198 | Providing of line spacers in LT line 3 phase |
| 199 | Fixing of LT shunt capacitor |
| 200 | SUB TOTAL(Items 1 to 191) |
| 201 | EPF @ 13.00 % on 100 % of (Items 1 to 191) |
| 202 | ESI @ 3.25 % on 100 % of (Items 1 to 191) |
| 203 | SGST% |
| 204 | CGST% |
| 205 | IGST% |