Execution Of Clubbed 04 Nos Individual Rural Piped Water Supply Schemes To Village Sasankhas, Banapinjara, Sunagadia, Bantala In Baro, Sendhatira, Gobindpur, Kadabarang G.P Under Tihidi & Bonth Blockinthe District Of Bhadrak
Tender Overview
Project Description
Execution Of Clubbed 04 Nos Individual Rural Piped Water Supply Schemes To Village Sasankhas, Banapinjara, Sunagadia, Bantala In Baro, Sendhatira, Gobindpur, Kadabarang G.P Under Tihidi & Bonth Blockinthe District Of Bhadrak
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 15-Sep-2022 | 1st Corrigendum | Technical Bid | 17-Sep-2022 |
BOQ
| Sl. No. | Item Description |
| 1 | Supplying all materials, labour, T&P, design, drawing ,soil testing etc. complete in all respect for construction of RCC RoofPump House building , construction of Compound wall for Pump House , construction of approach road along with site development including laying, testing and commissioning of Rising main & Distribution system with pipe line such as UPVC,HDPE,ASTM, G.I pipe lines etcalong with required fittings & specials and construction of valve chamber, stand post in pump house, individual house hold connection ,Stand alone, Installation of Chlorination system using bleaching powder solution, installation of submersible pump with motor in deep Tube well etc.(including supply of standby pump motor), internal wiring of Pump house & installation ofvoltage Stabilizer ,external Electrification etc. as per supplied Drawings in Section-7 and detail scope of work & technical specification, quantity of work mentioned in Section-8 and the BOQ in (Annexure-A to I) of Village SASANKHAS.. All materials required shall be supplied by the Contractor and the work shall be executed as per terms and condition of DTCN &all construction should be guided by supplied drawings and as per direction of Engineer in Charge |
| 2 | Design, drawing, construction errection, testing and commissioning of 1.00 lakh ltr. capacity 15 mtr staging RCC Elevated storage reservoir(Circular type with spherical dome) with RCC stair caseas per detailed scope of work & technical specificationmentioned in Section - 5 and in Annexure - H including testing of soil and vetting of the Design & Drawing by the approved State Technical Agency (STA) complete as per direction of Engineer in Charge |
| 3 | The contractor shall maintain the PWS project for Five (5) calendar years from the completion and official handing over date in a such a manner that all the house hold of the PWS Scheme covered area will get (adequate) required quantity of supply water taking supply hour as 8hours / day without facing any problem. The contractor shall repair and replace any types of defect arising within 24 hr of receipt of complaint either from public or from the Department . The contractor shall maintain all structure of the PWS schemes as per terms and conditions of DTCN &technical specificationmentioned in Section-5 |
| 4 | Supplying all materials, labour, T&P, design, drawing ,soil testing etc. complete in all respect for construction of RCC RoofPump House building , construction of Compound wall for Pump House , construction of approach road along with site development including laying, testing and commissioning of Rising main & Distribution system with pipe line such as UPVC,HDPE,ASTM, G.I pipe lines etcalong with required fittings & specials and construction of valve chamber, stand post in pump house, individual house hold connection ,Stand alone, Installation of Chlorination system using bleaching powder solution, installation of submersible pump with motor in deep Tube well etc.(including supply of standby pump motor), internal wiring of Pump house & installation ofvoltage Stabilizer ,external Electrification etc. as per supplied Drawings in Section-7 and detail scope of work & technical specification, quantity of work mentioned in Section-8 and the BOQ in (Annexure-A to I) of Village BANAPINJARA All materials required shall be supplied by the Contractor and the work shall be executed as per terms and condition of DTCN &all construction should be guided by supplied drawings and as per direction of Engineer in Charge |
| 5 | Design, drawing, construction errection, testing and commissioning of 1.00 lakh ltr. capacity 15 mtr staging RCC Elevated storage reservoir(Circular type with spherical dome) with RCC stair caseas per detailed scope of work & technical specificationmentioned in Section - 5 and in Annexure - H including testing of soil and vetting of the Design & Drawing by the approved State Technical Agency (STA) complete as per direction of Engineer in Charge |
| 6 | The contractor shall maintain the PWS project for Five (5) calendar years from the completion and official handing over date in a such a manner that all the house hold of the PWS Scheme covered area will get (adequate) required quantity of supply water taking supply hour as 8hours / day without facing any problem. The contractor shall repair and replace any types of defect arising within 24 hr of receipt of complaint either from public or from the Department . The contractor shall maintain all structure of the PWS schemes as per terms and conditions of DTCN &technical specificationmentioned in Section-5 |
| 7 | Supplying all materials, labour, T&P, design, drawing ,soil testing etc. complete in all respect for construction of RCC RoofPump House building , construction of Compound wall for Pump House , construction of approach road along with site development including laying, testing and commissioning of Rising main & Distribution system with pipe line such as UPVC,HDPE,ASTM, G.I pipe lines etcalong with required fittings & specials and construction of valve chamber, stand post in pump house, individual house hold connection ,Stand alone, Installation of Chlorination system using bleaching powder solution, installation of submersible pump with motor in deep Tube well etc.(including supply of standby pump motor), internal wiring of Pump house & installation ofvoltage Stabilizer ,external Electrification etc. as per supplied Drawings in Section-7 and detail scope of work & technical specification, quantity of work mentioned in Section-8 and the BOQ in (Annexure-A to I) of Village SUNAGADIA All materials required shall be supplied by the Contractor and the work shall be executed as per terms and condition of DTCN &all construction should be guided by supplied drawings and as per direction of Engineer in Charge |
| 8 | Design, drawing, construction errection, testing and commissioning of 0.50 lakh ltr. capacity 15 mtr staging RCC Elevated storage reservoir(Circular type with spherical dome) with RCC stair caseas per detailed scope of work & technical specificationmentioned in Section - 5 and in Annexure - H including testing of soil and vetting of the Design & Drawing by the approved State Technical Agency (STA) complete as per direction of Engineer in Charge |
| 9 | The contractor shall maintain the PWS project for Five (5) calendar years from the completion and official handing over date in a such a manner that all the house hold of the PWS Scheme covered area will get (adequate) required quantity of supply water taking supply hour as 8hours / day without facing any problem. The contractor shall repair and replace any types of defect arising within 24 hr of receipt of complaint either from public or from the Department . The contractor shall maintain all structure of the PWS schemes as per terms and conditions of DTCN &technical specificationmentioned in Section-5 |
| 10 | Supplying all materials, labour, T&P, design, drawing ,soil testing etc. complete in all respect for construction of RCC RoofPump House building , construction of Compound wall for Pump House , construction of approach road along with site development including laying, testing and commissioning of Rising main & Distribution system with pipe line such as UPVC,HDPE,ASTM, G.I pipe lines etcalong with required fittings & specials and construction of valve chamber, stand post in pump house, individual house hold connection ,Stand alone, Installation of Chlorination system using bleaching powder solution, installation of submersible pump with motor in deep Tube well etc.(including supply of standby pump motor), internal wiring of Pump house & installation ofvoltage Stabilizer ,external Electrification etc. as per supplied Drawings in Section-7 and detail scope of work & technical specification, quantity of work mentioned in Section-8 and the BOQ in (Annexure-A to I) of Village BANTALA. All materials required shall be supplied by the Contractor and the work shall be executed as per terms and condition of DTCN &all construction should be guided by supplied drawings and as per direction of Engineer in Charge |
| 11 | Design, drawing, construction errection, testing and commissioning of1.50 lakh ltr. capacity 15 mtr staging RCC Elevated storage reservoir(Circular type with spherical dome) with RCC stair caseas per detailed scope of work & technical specificationmentioned in Section - 5 and in Annexure - H including testing of soil and vetting of the Design & Drawing by the approved State Technical Agency (STA) complete as per direction of Engineer in Charge |
| 12 | The contractor shall maintain the PWS project for Five (5) calendar years from the completion and official handing over date in a such a manner that all the house hold of the PWS Scheme covered area will get (adequate) required quantity of supply water taking supply hour as 8hours / day without facing any problem. The contractor shall repair and replace any types of defect arising within 24 hr of receipt of complaint either from public or from the Department . The contractor shall maintain all structure of the PWS schemes as per terms and conditions of DTCN &technical specificationmentioned in Section-5 |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender