| 1 | Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :- |
| 2 | STP Pole 13 mtr long |
| 3 | PCC Pole 8.5 Mtr Long/ST Pole 11 Mtr. Long. |
| 4 | Line material such as 11 KV Cross arms 11 KV pin, 11 KV pin insulator, 11 KV Disc, Stay rod, Stay wire ACSR weasel conductor, GI Wire, MS angle iron & MS Channel, TPMO, Fuse set etc. |
| 5 | XLPE 11 KV Cable 3x70 to 185 mm |
| 6 | Joint kit 11 KV XLP out door in door joint kit |
| 7 | CT PT Unit Complete |
| 8 | Meter Cubical |
| 9 | 11 kv Out Going VCB Penal |
| 10 | Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :- |
| 11 | STP Pole 13 mtr long |
| 12 | PCC Pole 8.5 Mtr Long/ST Pole 11 Mtr. Long. |
| 13 | Line material such as 11 KV Cross arms 11 KV pin, 11 KV pin insulator, 11 KV Disc, Stay rod, Stay wire ACSR weasel conductor, GI Wire, MS angle iron & MS Channel, TPMO, Fuse set etc. |
| 14 | XLPE 11 KV Cable 3x70 to 185 mm |
| 15 | Joint kit 11 KV XLP out door in door joint kit |
| 16 | CT PT Unit Complete |
| 17 | Meter Cubical |
| 18 | 11 kv Out Going VCB Penal |
| 19 | Erection of Singal pole on PCC pole 8.5 mtr after digging a pitt of size 1.20 x 0.60 x 1.6 mtr in all type of Soil for each pole including back filling of the pole with proper ramming after completion of work. |
| 20 | Fabrication and fixing of all 11 KV HT/LT line accessories. |
| 21 | Erection of Double pole on PCC pole 8.5 mtr after digging a pitt of size 1.20 x 0.60 x 1.6 mtr in all type of Soil for each pole including back filling of the pole with proper ramming after completion of work. |
| 22 | Fabrication and fixing of MS angle and MS channel, fixing all 11 KV accessories TPMO, Fuse set 11 KV pin insulators. |
| 23 | Erection of stay rod complete after digging a pit of size 1.20 x0.60 x 1.6 mtr and grouting the same in block of size 0.60 x 0.60 x 0.30 mtr and nuzzling at the both ends and filling the pit with excavated earth soil with proper ramming. |
| 24 | Mounting and Fixing CT/PT Double pole and proper jumpring and wiring |
| 25 | Fixing of meter cubical including grouting the bolt and Nut and connection of cable |
| 26 | Mounting and Fixing 11 kv Out Going VCB Penal Proper Jumpring and urthing complite Bus bar etc work |
| 27 | Laying lifting stringing of proper sagging of ACSR Dog conductor for 3 phase. |
| 28 | XLP Cable laying lifting 3*185 mm |
| 29 | Laying of 11 KV XLPE cable in cable tranch after digging of tranch. Then filling the cable tranch with excavated earth soil bricks over the cable. |
| 30 | Fixing the cable jointing kit with the end of XLPE cable including mounting the same on pole with proper binding. |
| 31 | Earthingh of each 11 KV line pople & T/F properly after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GL wire. |
| 32 | Guarding of line with G.I. wire having 2 no. horizontal wire & 3 Mtr distance odf laces of ten SWG G.I. wire after fabrication of guard cross arms of & fixing the same in supports. |
| 33 | grouting of STP Pole 1.5 mtr |
| 34 | providing and fixing stay clamps. |
| 35 | Providing and fixing Holding clamps. |
| 36 | Providing and fixing LT clamps. |
| 37 | Providing and fixing F clamps. |
| 38 | Providing and fixing Bolt and Nuts. |
| 39 | Providing and fixing of G.I. Pipe |
| 40 | Water level earthing with GI Pipe 32 mm Dia and MS Flat of size 45x5mm |