Thanjavur District - Creating And Upgradation Of Streets And Lanes In Habitation - Construction Of Cement Concrete Road In 11 Works Package No.95, Thiruvaiyaru Block Of Under Agamt Ii-(10 Percent Deviation) -2021-2022. Thanjavur District - Creating And Up
Tender Overview
Project Description
Thanjavur District - Creating And Upgradation Of Streets And Lanes In Habitation - Construction Of Cement Concrete Road In 11 Works Package No.95, Thiruvaiyaru Block Of Under Agamt Ii-(10 Percent Deviation) -2021-2022. Thanjavur District - Creating And Upgradation Of Streets And Lanes In Habitation - Construction Of Cement Concrete Road In 11 Works Package No.95, Thiruvaiyaru Block Of Under Agamt Ii-(10 Percent Deviation) -2021-2022.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 22-Aug-2022 | Date Corrigendum - Thanjavur District - Creating and Upgradation of streets and Lanes in Habitation - Construction of Cement Concrete Road in 11 works Package No.95, Thiruvaiyaru Block of under AGAMT II-(10 Percent Deviation) -2021-2022. | Date | 29-Aug-2022 |
BOQ
| Sl. No. | Item Description |
| 1 | Ammaiyagaram Panchayat. |
| 2 | Part.1 Providing Paver Block Road at Kudiyana theru (30M) in Ammaiyagaram Panchayat. |
| 3 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 4 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 5 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 6 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 7 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 8 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 9 | Paving with paver blocks - 60mm thick laid as interlocking blocks including cost and conveyance and other labour charges etc complete., |
| 10 | Provision for Name board charges |
| 11 | Part.2 Providing Paver Block Road at Karuppusamykovil street (100M) in Ammaiyagaram Panchayat. |
| 12 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 13 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 14 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 15 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 16 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 17 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 18 | Paving with paver blocks - 60mm thick laid as interlocking blocks including cost and conveyance and other labour charges etc complete., |
| 19 | Part.3 Providing Paver Block Road at Kudiyana street at Kovathakudi (55M) in Ammaiyagaram Panchayat. |
| 20 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 21 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 22 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 23 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 24 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 25 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 26 | Paving with paver blocks - 60mm thick laid as interlocking blocks including cost and conveyance and other labour charges etc complete., |
| 27 | Provision for Name board charges |
| 28 | Part.4 Providing Paver Block Road at Puthu theru at Kovathakudi (74M) in Ammaiyagaram Panchayat. |
| 29 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 30 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 31 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 32 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 33 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 34 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 35 | Paving with paver blocks - 60mm thick laid as interlocking blocks including cost and conveyance and other labour charges etc complete., |
| 36 | Provision for Name board charges |
| 37 | Part.5 Providing Paver Block Road at Piramanpettai AD Street(43M) in Ammaiyagaram Panchayat. |
| 38 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 39 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 40 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 41 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 42 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 43 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 44 | Paving with paver blocks - 60mm thick laid as interlocking blocks including cost and conveyance and other labour charges etc complete., |
| 45 | Provision for Name board charges |
| 46 | Part.6 Providing Cement Road at Kudiyana street at Adanjur (50M) in AmmaiyagaramPanchayat . |
| 47 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 48 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 49 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 50 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 51 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 52 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 53 | Kalyanapuram I sethi Panchayat . |
| 54 | Part.7 Providing Cement Road at Star Nagar at Ponnavarai (150M) in Kalyanapuram I sethi Panchayat. |
| 55 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 56 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 57 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 58 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 59 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 60 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 61 | Provision for Name board charges |
| 62 | Part.8 Providing Cement Road atDurgai amman kovilat Chinnakandiyur (70M) in Kalyanapuram I sethi Panchayat . |
| 63 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 64 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 65 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 66 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 67 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 68 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 69 | Provision for Name board charges |
| 70 | Part.9 Providing Cement Road at Ganapathi nagar at Chinnakandiyur (45M) in Kalyanapuram I sethi Panchayat. |
| 71 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 72 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 73 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 74 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 75 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 76 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 77 | Provision for Name board charges |
| 78 | Part.10 Providing Cement Road at Exetension of Vayal theru at Nadukadai (70M) in Kalyanapuram I sethi Panchayat. |
| 79 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 80 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 81 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 82 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 83 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 84 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 85 | Provision for Name board charges |
| 86 | Part.11 Providing Cement Road at Vahap Nagar at Nadukadai (66M) in Kalyanapuram I sethi Panchayat . |
| 87 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m (For roads, supply channels, desilting of MI Tanks, Pond & Kulam) - upto 0.30m depth |
| 88 | Sand filling with river sand including all cost and conveyence and labour charges etc complete. |
| 89 | Cement concrete 1:4:8 mix using 40mm iss HBG metal for foundation & flooring including labour charges etc., complete |
| 90 | Cement concrete 1:3:6 Mix using 20mm ISS HBG metal including all cost and conveyenc and labour charges etc comple |
| 91 | Supply and errection of steel centring including all cost and conveyence and labour charges etc complete. |
| 92 | Cement concrete 1:2:4 mix using 20mm ISS metal including costand conveyance and other labour charges etc complete., |
| 93 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender