Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track, kalamassery-Kerala

Department Of Sports And Youth Affairs has published Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track. Submission Date for this Tender is 27-08-2022. Sports Complex Tenders in kalamassery Kerala. Bidders can get complete Tender details and download the document.




Tender Notice

33409865
Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track
Open Tender
Indian
Kerala
kalamassery
27-08-2022

Tender Details

Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track Development Of Sports Infrastructure Facilities In Cusat Campus, Kalamassery - Construction Of 400M Synthetic Athletic Track

Key Value

Document Fees
INR 8850 /-
EMD
INR 100000.0 /-
Tender Value
INR 4.28 Crore /-

BOQ Items

Work Name : Development of Sports Infrastructure facilities in CUSAT Campus, Kalamassery-Construction of 400 m Synthetic Athletic Track
Sl. No. Item Description
1Sub base Preparation
24.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
35.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
45.2.b : Providing and applying tack coat with bitumen emulsion (RS) using emulsion pressure distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared Granular Surface cleaned with mechanical broom.
55.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
65.3.2.a : Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder (VG 30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.
For Grading II - (19 mm nominal size)
75.6.2.a : Providing and laying bituminous concrete with 80-100 TPHhot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder( NRMB)@ 5.4 per centof mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects Grading - II (13.2 mm Nominal Size)
8Synthetic Track
9od74518/2022_2023 : SKF_OD 5/2022-2023 Supply of full PUR , World Athletics ( formerIAAF) approved Synthetic Track Surfacing system in accordance with World Athletics standard suitable for conducting World Athletics approved international Athletic events. Total thickness of the synthetic track surfacing system shall be 14 to 15mm comprising 9.4 to 10.0 mm force reduction layer comprising 4.7mm Bottom Layer made with Black SBR granules embedded in PUR coating ,4.7mm Middle Layer(s): Black SBR granules embedded in PUR coating and final resilient wearing layer of granular texture, red-brown. Full PUR coating with EPDM granules embedded 5.0 mm. In high stress areas thickness should be as per World Athletics requirement. Laying and installation according to World Athletics specifications and approved methodology and drawings including provisions of installation of sleeves for throwing events, inlay equipment for pole vault, long & triple jump and steeple chase. This rate also include lane marking.
10od123624/2022_2023 : SKF_OD 15/2022-2023 Supply and Filling Fine Sand of approved quality in Long Jump Pit as per the direction of officer in charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail