Augmentation Of Transformer Fromm 100Kva To 200Kva At Adkhar Aishmuqam And Augmentation Of Transformer From 63Kva To 100Kva At New Colony Wopzan Bijbehaa Under Ut Capex 2022-23.
Tender Value
11 Lakhs
Estimated cost
Bid Submission
26 Aug 2022
0 days left
EMD
22000
Bank guarantee accepted
Document Fee
1000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
bijbehara → Jammu And Kashmir
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Augmentation Of Transformer Fromm 100Kva To 200Kva At Adkhar Aishmuqam And Augmentation Of Transformer From 63Kva To 100Kva At New Colony Wopzan Bijbehaa Under Ut Capex 2022-23.
BOQ
| Sl. No. | Item Description |
| 1 | Augmentation of 100 KVA to 200 kva and 63kva tok 100kva transformers |
| 2 | Supply, Installation, Testing and commissioning of 200kVA,11/0.433KV, 3-phase Distribution Transformers (level-II)with Bimetallic Terminal connrction and withLV Cable box having detachable Aluminium Gland Plateat Adkher Siligam. Transformer should be arranged for vertical takeoff. |
| 3 | Supply, Installation, Testing and commissioning of 100kVA,11/0.433KV, 3-phase Distribution Transformers (level-II)with Bimetallic Terminal connrction and withLV Cable box having detachable Aluminium Gland Plate at Wopzan. Transformer should be arranged for vertical takeoff. |
| 4 | Supply,erection, testing and commissioning of S.T Pole 9mtr Long SP-33 with base plate & cap for HT. Strictly as per REC standards |
| 5 | Supply,erection, testing and commissioning of S.T Pole 8mtr Long SP-15 with base plate & cap for LT. Strictly as per REC standards |
| 6 | Supply, laying, strininging and commissiong of ACSR 30mmsq (Weasel) Conductor |
| 7 | Supply, laying, strininging and commissiong of ACSR 50mmsq (Rabbit) Conductor |
| 8 | Providing & fixing of GI Channel/Angle/Flat of sizes including clamps |
| 9 | Supplying and fixing of Earthing Complete by GI Pipe 40 mm or GI Rod 20mm 2.5 mtr long through GI Strip as per REC standards. |
| 10 | Painting of poles with one coat of red oxide and two coats of Aluminium paint as per Standards. This also includes numbering of ploes with paint,submission of Pre and Post Execution photographs duly anthenticated by AEE concrened. |
| 11 | Supply,fixing, testing & commissioning of 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type as per IS Standards |
| 12 | Supply,fixing, testing & commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A as per IS Standards |
| 13 | Supply,fixing, testing & commissioning of 11 kV Gapless Surge Arrestor,9 kV ,10 kA ,LA with polymer housing, Stn. Type as per IS Standards |
| 14 | Supply,fixing, testing & commissioning of 11 KV Pin Insulators (polymer/porcelain) with Pins(5KN) |
| 15 | Cement bottoming 1:2:4 mix as per REC Standards 0.5cum/pole |
| 16 | Providing & fixing of Sundry items like aluminium lugs, Jumpers, binding Tape etc |
| 17 | Providing & fixing of LT Shackles Insulator with GI mukhi clamps including nuts & bolts |
| 18 | Supply and laying of 300sqmm Cable, 1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type |
| 19 | Supply, laying of 150 mmsq Single Core 1.1kv gradeXLPE, FRLS unaroumed Cable |
| 20 | Supplying and fixing of Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 21 | Providing, Fixing of nuts and bolts for fixing of x-arms and other accessories. |
| 22 | Cement bottoming 1:2:4 mix as per REC Standards 0.45cum/pole |
| 23 | Supply,Installation and commissioning of LTDB for 100KVA DT with MCCB for incommer and SFU/MCB for outgoing circuit. |
| 24 | Back Carriage of old 100kva spared transformer from Adkher Siligam to Divisional Stores. |
| 25 | Back Carriage of 63kva spared transformer from wopzan to Divisional Stores. |
AI Tender Summary
Tender Timeline
Aug 04, 2022
11:30 IST
Tender Published
Tender notice published.
CompletedAug 26, 2022
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedAug 27, 2022
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender