Tripura State Electricity Corporation Limited-TSECL has published Extension Of Ht / Ltline In / Csub Stationfor Providingservice Connection To Sevaral Dtw Schemes Under Jurisdiction Of Esd-Amarpur , Ompi, Jatanbari & Karbook Ofelectrical Sub-Division Amarpur ( Partial Turnkey Basis ) . Submission Date for this Tender is 11-08-2022. Overhead Line Tenders in amarpur Tripura. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 04-Aug-2022 | Technical Corrigendum | Technical Bid | 11-08-2022 |
2 | 05-Aug-2022 | Modified BOQ | BOQ | 11-08-2022 |
Sl. No. | Item Description |
1 | SUPPLY |
2 | 8 mtr. Long PCC Pole |
3 | 9 mtr. Long PCC Pole |
4 | Steel Tubular Pole 9 mtr long (SP 30) |
5 | GI Stay set HT 20 sq mm |
6 | GI Stay set LT 16 sq mm |
7 | Stay wire 7/2.50 sqmm |
8 | 11 KV Stay/Guy insulator (Porcelin) |
9 | LT Stay/Guy insulator (Porcelin) |
10 | Stay clamp |
11 | Strain Screw |
12 | LT Shackle Insulator(3x3.5 )" |
13 | LT Straps And bolts |
14 | MS Channel (100 x 100x50x 6 mm ) |
15 | MSl Channel ( 75 x 40x40x 6 mm ) |
16 | MS Angle ( 65x 65x 6 mm) |
17 | Nut & bolts 16X50 mm |
18 | Nut & bolts 16X75 mm |
19 | Nut & bolts 12X250 mm |
20 | Nut & bolts 12X300 mm |
21 | Nut & bolts 12X90 mm |
22 | 11 KVG.O.S (three phase)(Polymeric type) |
23 | 11 KV D O F (three phase)(Polymeric type) |
24 | 11 KV PolymericLA,9 KV,5KA |
25 | 11 KV Polymer composite 45 KN Disc Insulator |
26 | 11 KV Disc fittings(6/1/2.59 & 6/1/3.35) |
27 | 11 KV 320 mm CD Polymer composite PIN Insulator |
28 | ACSRweasel (30 sq mm ) conductor |
29 | 8 SWG Gi wire |
30 | 11 KV Danger plate |
31 | LT Danger plate |
32 | M.S clampsof assorted size of MS flat (50x6mm) |
33 | Rewireable porcelinCut Out 200 amp |
34 | PVC single core 16 mm sq |
35 | Bi mettalic lugs 120 sqmm |
36 | PG Clamp for weasel |
37 | Bi mettalic lugs 70 sqmm |
38 | PVC Pipe half in. dia |
39 | Supply of3-Phase Static with LCD Display 415V,50 Hz KWH Meter for LT supply 20-100Amps |
40 | Supply of 2.5 mtr. Long 40 mm dia G.I Pipe (Make: TATA JINDAL) |
41 | Supply of 60 Kg Salt and 55 Kg Charcoal (For 1 Pit). |
42 | Supply of MS Nuts & Bolts in/c washer of assorted size ISI Marked machine made |
43 | Reel Insulator |
44 | ERECTION |
45 | 8 mtr. Long PCC Pole |
46 | 9 mtr. Long PCC Pole at any kind of soil upto a depth of 1/6th of pole heightin/c excavation, refilling the pit with soil up to the ground level , ramming & making complete in all respect i/c hand cart carriage & manual carriage with necessary loading & unloading |
47 | 9 mtr. Long steel Pole at any kind of soil upto a depth of 1/6th of pole heightin/c excavation, refilling the pit with soil up to the ground level , ramming & making complete in all respect i/c hand cart carriage & manual carriage with necessary loading & unloading etc as reqd.( ST Pole 9 mtr long (SP 30) |
48 | Painted stay set complete direct in earth with 19 mm dia 1.8 mtr long painted stay rod ,anchor plate of size 300x300x8 mm ,thimble, turn buckle ,7/3.15 mm dia GI stranded wire & stain insulatorinsulator etc in/c supply of MS Clamp,Nut & Bolts etc asa reqd. & making complete in all respectas (GI Stay set HT 20 sq mm) |
49 | Painted stay set complete direct in earth with 19 mm dia 1.8 mtr long painted stay rod ,anchor plate of size 300x300x8 mm ,thimble, turn buckle ,7/3.15 mm dia GI stranded wire & stain insulatorinsulator etc in/c supply of MS Clamp,Nut & Bolts etc asa reqd. & making complete in all respectas (GI Stay set LT 16 sq mm) |
50 | Shackle insulator of size 75mm x 90mm/100mm x 15mm with straps & bolts/ U clamp on poles (excluding the cost of straps U clamp, Nuts & Bolts)LT Shackle Insulator(3x3.5 )" |
51 | 0.8 mtr long MS Channel (100 x 100x50x 6 mm ) for sub stn. etc |
52 | 2.8 mtr long MS Channel (100 x 100x50x 6 mm ) for sub stn. etc |
53 | 2.8 mtr long MS Channel ( 75 x 40x40x 6 mm )for sub stn. GO,DO fixing bkt. Etc |
54 | MS Channel ( 75 x 40x40x 6 mm ) 0.3mtr longfor single poletopcross arm |
55 | MS Channel ( 75 x 40x40x 6 mm ) 1.2mtr longfor single polebottamcross arm |
56 | MS Channel ( 75 x 40x40x 6 mm ) 2.2mtr longfor single polebottamcross arm |
57 | MS Angle ( 65x 65x 6 mm) 1.5 mtr long SPGuarding cross arm |
58 | MS Angle ( 65x 65x 6 mm) 2.8 mtr long DPGuarding cross arm |
59 | MS Angle ( 65x 65x 6 mm) 2.5 mtr long DP cross arm |
60 | Three phase 5-wire C-type Bracket( MS Angle 65x 65x 6 mm) |
61 | 11 KV 200 Amp GOS unit set of three nos inc. necessary connection complete as per technical specification (Excluding the cost of back clamp, nuts & bolts)11 KVG.O.S (three phase)(Polymeric type) |
62 | 11 KV DOF unit set of three nos inc. necessary connection complete as per technical specification (Excluding the cost of back clamp, nuts & bolts) 11 KV D O F (three phase)(Polymeric type) |
63 | 9 KV, 5 KA single pole metel oxide gapless type LA, inc. necessary connection complete as per technical specification.11 KV PolymericLA,9 KV,5KA |
64 | 11 KV disc insulator with fittings, nuts & bolts, washers etc. as reqd. as per direction of Engineer-in-charge. (11 KV Polymer composite 45 KN Disc Insulator) |
65 | 11 KV 320 mm CD Polymer composite PIN Insulator |
66 | Laying & stringing ofACSRweasel (30 mm ) cable in/c hoisting &binding etc. complete as required |
67 | Laying & stringing of8 SWG Gi wirein/c hoisting &binding etc. complete as required |
68 | Insttalation/ Positioning of 11/0.430 KV , 3 phase 63 KVA distribution transformer on polewithnecessary connections & fitting & fixing of all allied assessories , components as redq.For making complete in all respect for energizingDTR 63 KVA 11/0.433KV |
69 | Fitting & fixing of 11 KV Danger plate |
70 | Fitting & fixing of LT Danger plate |
71 | Earthing with GI pipe 2.5 mtr Long and 40 mm dia, inc. excavation, refilling with alternate layer of salt & charcoal as per drawing (excluding supply of GI wire, nuts & bolts, etc. as required) |
72 | Laying of 8 SWG GI wire at 300mm below the ground level for earthing of Sub-Station equipments from the earth electrode. |
73 | Providingthree phase Service Connection with laying PVC Cable from nearby electrical Pole to premises upto 35 mtrs in length supported by GI wire Reel insulators i/c fitting fixing of energy meter as required. |
74 | Erection of protective guarding / cross lacing for 415/240 volt line by GI wire 98/10 SWG as per technical specificationacross road/river/telecom line etc.in horizontal/verticle formation complete with spool/Reel insulator |
75 | Carriage of 11/0.43 three phase 63 KVA Transformer by mechanical transport from A.D Nagar Store Yard, Agartala to Work site Vis-à-vis including unloading and placing on pole mounted structure as required. |
76 | Providing Sub-Station protective fencing by 75 x25 mesh of 2.5x3.5 mtr.and height of 1.5 mtr. As per Engineering recruitment by 01 nos. MS Angle post (50x50x6mm) of height 2.0mtr .Horizontal Bar 6x3.5 mtr and 6x2.5 mtr and vertical Bar 10x1.5 mtr of MS flat (35x6mm) and single part of MS Grildoor of size L-1.5 / B-1.2 mtr with locking arrangement including necessary grouding and painting by Aluminium paint over red oxide priming of approved quality as reqd . as per TS including supply of all materials (MS Angle will be supplied by the Deptt) |
77 | Grouting of steel tubular poles with CC of ratio 1 :2:4 (1 cement: 2 river sand: 4 jhama brick aggregate of 20 mm. nominal size) ilc supply of cement, sand and brick aggregate complete with excavation, refilling of earth, ramming alongwith centering and shutterirtg as required.(@ 0.273 Cum per steel tubular pole as per TSECL specification ). |