Work Of Repair Of Damaged / Burnt Power Transformer Of Assorted Ratings 5 Mva, 8 Mva And 10 Mva 37.5 / 11 Kv Or 33 / 11 Kv 37.5 / 11 Kv Or 33 / 11 Kv Work Of Repair Of Damaged / Burnt Power Transformer Of Assorted Ratings 5 Mva, 8 Mva And
Tender Overview
Project Description
Work Of Repair Of Damaged / Burnt Power Transformer Of Assorted Ratings 5 Mva, 8 Mva And 10 Mva 37.5 / 11 Kv Or 33 / 11 Kv 37.5 / 11 Kv Or 33 / 11 Kv Work Of Repair Of Damaged / Burnt Power Transformer Of Assorted Ratings 5 Mva, 8 Mva And 10 Mva 37.5 / 11 Kv Or 33 / 11 Kv 37.5 / 11 Kv Or 33 / 11 Kv , Preliminary Inspection Of Transformers At Pvvnl Site / Workshop Involving Minor Repairs At Site / Workshop , Preliminary Inspection Of Transformers At Pvvnl Site / Workshop For Estimation Involving Major Repairs Unloading Of Trnasformers, At Contractors Work & Repair Of Transformer Cover, Draining Of Oil, If Any, Di-Tanking Core And Coil Assembly, And Replacement Of Damaged Parts, Minor Repair Of Core And Tank ( If Required ) Cleaning Washing Of Dust & Dirt Etc. From All Parts Including Core Tank & Cooling Tubes Of Radiators Removal Of Damaged Parts, Requiring Replacement, Fitting, Fixing Of New Parts, Making Connection & Assembly, Complete In All Respect, Re-Tanking After Repairs, Filling Fresh Transformer Oil, Making Transfomer Ready For Tests & Testing For All Tests As Per Clause 16.0 Of Technical Specification. , Hv Leg Coils Complete With Insulation, Varnishing By Vacuum Impregnation ( If Required As Per Sample ) And Baking Of Coil Assembly ( Variable Base Date 01.07.22 ) , Lv Leg Coils Complete With Insulation, Vanishing By Vacuum Impregnation ( If Required As Per Sample ) And Baking Of Coil Assembly ( Variable Base Date 01.07.22 ) , Hv Bushing 33 / 37.5 Kv , Lv Bushing 11 Kv , Hv Bushing Metal Parts , Lv Bushing Metal Parts , Set Of Gaskets ( Rubberized Cork ) , Silicagel Breather With Fresh Silicagel , Magnetic Type Oil Level Gauge With Low Level Alarm Contact , Tapping Switch 33 / 37.5 Kv Complete With Handle , Tapping Switch Handle , Oil Drainvalve Incorporating Sampling Device ( With Narrow Orifice ) & Having Suitable Arrangement For Locking , Filter Valve , Dial Type Thermometer Of Minimum 150 Mm Dia With Maximum Temperature Indicator Complete With Resetting Device And Alarm Contacts , Double Float Bucholz Relay Complete With Alarm And Trip Contacts , Air Release Plug , Replacement Of Damaged Core , Pair Of Arcing Horns , Radiator Valve , Replacement Of Un Repairable Radiator Of Equivelent Size With Equal Fins. , Overhauling Of Oltc , Replacement Of Oltc Contact , Replacement Of Oltc Terminal Barrier Board , Replacement Of Gaskets, Lubrication Of Mechanical System , M. S. Clamping Ring , Winding Temperature Indicator ( Complete Set ) , Fresh Transformer Oil Of Standard Quality As Per Is:335 / 83 And Latest Amendment Thereof. ( Variable Base Date 01.07.22 ) , Sundry Item Viz Cover Bolt, Plug, Caps, Screw, Washers, Insulation Material, Minor Repairs Of Tank, Other Parts Required If Any, Aluminium Name Plate Etc. , Painting Inside & Outside Of Transformer Including Radiator Tubes Concervatorwith Suitable Primer And Two Coats Of Suitable Paint Of Grey Colour And Marking Etc. , Burnt / Damaged Leg Coils To Be Retained By The Contractor ( Variable Base Date 01.07.22 ) , Damaged Metal Parts Of Bushing To Be Retained By Contractor , Transportation / Carriage Charges , Upto 10 Kms. , Above 10 Kms. To 25 Kms. , Above 25 Kms. To 50 Kms. , Above 50 Km. To 100 Kms. , Above 100 Kms. To 150 Kms. , Above 150 Kms. To 200 Kms. , Above 200 Kms. But Upto 300 Kms.
BOQ
| Sl. No. | Item Description |
| 1 | Preliminary inspection of transformers at PVVNL site/workshop involving minor repairs at site/workshop |
| 2 | Preliminary inspection of transformers at PVVNL site/workshop for estimation involving major repairs unloading of trnasformers, at contractors work & repair of transformer cover, draining of oil, if any, di-tanking core and coil assembly, and replacement of damaged parts, minor repair of core and tank (if required) cleaning washing of dust & dirt etc. from all parts including core tank & cooling tubes of radiators removal of damaged parts, requiring replacement, fitting, fixing of new parts, making connection & assembly, complete in all respect, re-tanking after repairs, filling fresh transformer oil, making transfomer ready for tests & testing for all tests as per clause 16.0 of Technical specification. |
| 3 | HV leg coils complete with insulation, varnishing by vacuum impregnation (if required as per sample) and baking of coil assembly (variable base date 01.07.22) |
| 4 | LV leg coils complete with insulation, vanishing by vacuum impregnation (if required as per sample) and baking of coil assembly (variable base date 01.07.22) |
| 5 | HV bushing 33/37.5 KV |
| 6 | LV Bushing 11 KV |
| 7 | HV bushing metal parts |
| 8 | LV bushing metal parts |
| 9 | Set of gaskets (rubberized cork) |
| 10 | Silicagel breather with fresh Silicagel |
| 11 | Magnetic type oil level gauge with low level alarm contact |
| 12 | Tapping switch 33/37.5 KV complete with handle |
| 13 | Tapping switch handle |
| 14 | Oil drainvalve incorporating sampling device (with narrow orifice) & having suitable arrangement for locking |
| 15 | Filter valve |
| 16 | Dial type thermometer of minimum 150 mm dia with maximum temperature indicator complete with resetting device and alarm contacts |
| 17 | Double float Bucholz relay complete with alarm and trip contacts |
| 18 | Air release plug |
| 19 | Replacement of damaged core |
| 20 | Pair of arcing horns |
| 21 | Radiator valve |
| 22 | Replacement of un repairable radiator of equivelent size with equal fins. |
| 23 | Overhauling of OLTC |
| 24 | Replacement of OLTC contact |
| 25 | Replacement of OLTC terminal barrier board |
| 26 | Replacement of gaskets, lubrication of mechanical system |
| 27 | M. S. Clamping ring |
| 28 | Winding temperature indicator (complete set) |
| 29 | Fresh transformer oil of standard quality as per IS:335/83 and latest amendment thereof.(variable base date 01.07.22) |
| 30 | Sundry item viz cover bolt, plug, caps, screw, washers, insulation material, minor repairs of tank, other parts required if any, Aluminium Name Plate etc. |
| 31 | Painting inside & outside of transformer including radiator tubes concervatorwith suitable primer and two coats of suitable paint of grey colour and marking etc. |
| 32 | Burnt/damaged leg coils to be retained by the contractor(variable base date 01.07.22) |
| 33 | Damaged metal parts of bushing to be retained by contractor |
| 34 | Transportation/Carriage charges |
| 35 | Upto 10 kms. |
| 36 | Above 10 kms. To 25 kms. |
| 37 | Above 25 kms. To 50 kms. |
| 38 | Above 50 km. To 100 kms. |
| 39 | Above 100 kms. To 150 kms. |
| 40 | Above 150 kms. To 200 kms. |
| 41 | Above 200 kms. But upto 300 kms. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender