Electrification Of Giving New Connection To Various Consumers In The Area Of Edd-Tiloi, Distt. Amethi. Electrification Of Giving New Connection To Various Consumers In The Area Of Edd-Tiloi, Distt. Amethi. (Deposit Scheme/Vidhayak Nidhi/Sansad Nidhi Throu
Tender Overview
Project Description
Electrification Of Giving New Connection To Various Consumers In The Area Of Edd-Tiloi, Distt. Amethi. Electrification Of Giving New Connection To Various Consumers In The Area Of Edd-Tiloi, Distt. Amethi. (Deposit Scheme/Vidhayak Nidhi/Sansad Nidhi Through Running Contract)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 26-Jul-2022 | Date Extension I | Date | 29-Jul-2022 |
BOQ
| Sl. No. | Item Description |
| 1 | Loading, carriage of following items from Store Centre, Gauriganj/Sultanpur to dump store including unloading and proper stacking (distance 0-70 km.) (Sl. No. 2 - 18) |
| 2 | STP/PCC pole. |
| 3 | ACSR Weasel Conductor |
| 4 | V type X Arm |
| 5 | 11 KV XLPE cable |
| 6 | 25/63/100 KVA Transformer |
| 7 | 250 KVA Transformer |
| 8 | Pilfer proof metering cubical |
| 9 | 11 KV cable box indoor/outdoor |
| 10 | Pole mounted CT/PT combined unit |
| 11 | 11 KV pin/disk insulator with nuts & bolts |
| 12 | Top Channel. |
| 13 | G.I. wire |
| 14 | Stay Set complete |
| 15 | L.T. ABC Three phase/Single Phase |
| 16 | LT Distribution BOX |
| 17 | Other Line Materials |
| 18 | Dragging of STP/PCC Pole from dump store to pit site. |
| 19 | Digging of pits up to the depth of 1650/2200 mm. as per site requirement. Fabrication & erection of single pole support on PCC/STP pole support including digging of pit & fixing of all accessories and clamps as per RESPO norms . |
| 20 | Digging of pits up to the depth of 1650/2200 mm. as per site requirement.Fabrication & erection of double pole support on P.C.C./STP pole includingdigging of pit & fixing of all accessories and clamps as per RESPO norms. |
| 21 | Grouting of STP/PCC pole in ratio 1:4:8 with cement stone ballast, coarse sand and plinthing 300 mm above ground level as well as muffing of plinth. |
| 22 | Spreading, laying & stringing of ACSR weasel conductor for construction of 11 KV line as per RESPO norms. |
| 23 | Spreading, Laying & Stringinging of AB cable Three phase/Single Phase |
| 24 | Ordinary earthing by 11 KV MS earth rod 2500 mm long as per RESPO norm. |
| 25 | Concreting & nuzzling of stay complete including fixing of necessary clamps with the help of nuts & bolts other accessorise required for completing the work as well as its grouting by civil material viz.Sand, stone ballast and cement. The contractor will provide all civil material as well as stay insulator |
| 26 | Guarding of line as per RSPO norms. |
| 27 | Installation of 25/63/100 KVA Transformer on newly constructed Double/single pole making proper connections from 11 KV system and proper testing as well as commissioning of Transformer. |
| 28 | Underground laying of 11 KV XLPE cable as per RESPO norms. |
| 29 | High pressure testing of 11 KV XLPE cable testing equipment will be arrenge by the contractor. |
| 30 | Installation and commissioing of pilfer proof metering cubical in metering room. |
| 31 | Installation and commissioing of pole mounted CT/PT combined unit |
| 32 | Fixing & jointing of cable box indoor/outdoor |
| 33 | Construction of plinth for 250 KVA transformer of 2x2x1.2 mtr. with help of first class brick and masonry 1:4 cement & coarse sand. Filling the structure completely as per norm with RCC to 1:2:2 cement & stone grit with M.S. bar & M.S. for restling the transformer. |
| 34 | Installation of 250 KVA Transformer on newly constructed plinth making proper connections from 11 KV system and proper testing as well as commissioning of Transformer. |
| 35 | construction of 250 KVA Transformer fencing. |
| 36 | Fixing of LT distribution box & other complete works as per RESPO norms. |
| 37 | Earthing of 11/0.4 KV T/F with sutable G.I. pipe and fixing sutable G.I. Strip including all material requaired to complete the work. |
| 38 | Dismenteling of 11 KV line. |
| 39 | Dismenteling of AB cable single phase/ three phase. |
| 40 | Tree cutting for clearance of 11 KV/LT line. |
| 41 | Note: Any quantity of item from sl no. 1 to sl no. 40 may vary to any limit within the financial value of agreement against this tender. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender