| 1 | M&L for cleaning of following RCC tank/masonary sumps/water reservoirs, through 7 stages of cleaning and sterilization consisting of three stages of bacteriological screening done by Terbac-G10, Terbac-G5, Terbac-G65 and Ultra Violet ray process complete all as specified and as directed for the following :- Note 1 for cleaning stages:-(a) First stage is to drain out the water by using exit valve or our own high capacity dewatering system.(b) Second stage is cleaning all the algae formation inside the tank by using TERBAC G10 , a laboratory tested branded chemical of the company and scrubbing the walls of the tanks.(c) Third stage is fresh water cleaning by high speed jet pumpwith pressure 5 PSI.(d) Fourth stage and first bacteria screening is Sterilization by using TERBAC-G5 aLaboratory certified branded halogen compound.Test certificate of TERBAC-G5 from government laboratory mentioningsuitability for sterilization should be submitted to the office before using for sterilization. |
| 2 | (e )Fifth stage is cleaning the floor of the water tank byheavy duty industrial vacuum cleaner.(f) Sixth stage is the second bacteria screening and sterilizing method by using ultra violet ray Ejector covering 360 degree with in the tank and kills all suspended bacteria.(g) Seventh Stage of cleaning and third bacteria screening is to sterilize the floor of the water tank by using laboratory certified branded strong oxidizing agent TERBAC- G65.Test certificate of Terbac- G65 From Government Laboratory mentioningsuitability for sterilization should be submitted to the office before using for Sterilization.Note 2: Cleaning shall be done at-least three times at an interval of three months or at an early period if directed by Engineer-in-Charge. |
| 3 | Semi under ground Clear water sump 50000 gallons capacity 3.5 m in depth. |
| 4 | Semi under ground Clear water sump 30000 gallons capacity 3.5 m in depth. |
| 5 | Semi under ground Clear water sump 10000 gallons capacity 3.5 m in depth. |
| 6 | P& S overhead tank of 9600 gallons capacity |
| 7 | M&L for disconnecting existingtanks, setting aside (or lowering if required) for cleaning etc and hosting if required, reconnecting and refixing in position including cleaning and removing all scale and dirt, etc, from tanks and from mouths of circulating pipes etc. for the following capacities of tanks complete all as specified and directed for following items :-. |
| 8 | PVC water tank of capacity 250 ltr to 500 ltr |
| 9 | PVC water tank of capacity 500 ltr to 1000 ltr |
| 10 | M & L for preparation of old or previously treated internal and external steel/iron surfaces of over head pressed steel tanks and all steel surfaces of staging and applying one coat of anticorrosive synthetic enamel paint complete including writing of capacity, tank cleaned date etc with white paint of letter size 15 cm on 60 cm x 90 cm size black paint background complete all as directed. |
| 11 | Supply of calcium based granular disinfectant (Calcium Hypo Chlorite) consisting 65%-70% Chlorine Content for Water Treatment Packed in 45 Kg Drum factory sealed delivered at store yard of E/M Office, Laitkor Peak Shillong.Make:- Any brand approved by E-in-C\"s or any other brand whose product fulfills the parameters specified in Manual on Water Supply and treatment (Third Edition May 1999) issued by CPHEEO,Ministry of Urban Dovelopment, New Delhi. Note :- The brand must contain corrosion inhibitor & Anti Scalling agent to prevent damage of distribution pipelines & accessories. |
| 12 | Excavation in trenches, not exceeding 1.5 mtr wide and not exceeding 1.5 mtr deep in soft / loose soil for removing old and laying new pipes , complete all as specified and directed at site. |
| 13 | Returning, filling in, excavated soil including leveling, watering and well ramming in layers of thickness not exceeding 25 cm in each layer complete all as specified and directed. |
| 14 | Removing excavated surplus soil to a distance not exceeding 50 mtr and depositing the soil where directed at a level not exceeding 1.5 mtr above the starting point complete all as specified and directed. |
| 15 | Disconnecting and taking up or down old existing GI / DI /PPR pipe and connections of any description / grade and in any position in trenches / under floors etc including connected fittings/accessories and fixtures , all as specified and directed for the following sizes :- |
| 16 | 100 mm bore |
| 17 | 150 mm bore |
| 18 | Supplying, laying, jointing & testing in trenches DI pipes of size 100mm bore with spigot and socketed ends, Class K7 suitable for push on joints, standard bituminous finish layer not less than 70 micron, cement lining including DI specials/ fittings and jointscomplete all as specified and directed by Engineer-in-Charge. NOTE :- Earth work shall be measured and paid for separately under appropriate item of Schedule `A\". |
| 19 | Supply and fix in repairs Cast Iron Air Valves with single air outlets, conforming to IS 14845 of size 150 mm dia bore and fixing up in Cast Iron Water supply mains of size 150 mm dia complete all as specified and directed. |
| 20 | Supply, install, connecting and testing cast iron non return (reflux) valve in repairs suitable for 150 mm dia pipe, heavy duty, flanged ends with gun metal seat, class PN 1.6, IS - 5312 marked including all jointing materials such as leather gasket, bolts nuts washers etc complete all as specified and directed. |
| 21 | Supply, install, connecting and testing of Cast iron sluice valve in repairs for 150 mm dia pipe, class PN- 1.6 double flanged with CI body, iron wheel head and brass spindle and check nut etc, non rising type IS-14846-2000 marked including jointing materials i.e. rubber gaskets, nuts, bolts etc. complete all as specified and directed. |
| 22 | Supply, install, connecting and testing of sluice valve in repairs for 100 mm dia pipe, class PN- 1.6 double flanged with CI body, iron wheel head and brass spindle and check nut etc, non rising type IS-14846-2000 marked including jointing materials i.e. rubber gaskets, nuts, bolts etc. complete all as specified and directed. |
| 23 | Taking up or down steel tubingand connections and Supply and fix 150mm bore size steel water tubing, galvanized, medium grade, with all fittings like bends, sockets, reducers etc as required in new or old alignment, on floor, vertically on overhead reservoir,complete all as specified and directed. |
| 24 | Taking up or down steel tubingand connections and Supply and fix 100 mm bore size steel water tubing, galvanized, medium grade, with all fittings like bends, sockets, reducers etc as required in new or old alignment, on floor, vertically on overhead reservoir,complete all as specified and directed. |
| 25 | M&L for repairing150mm size pipe leaking flanged joints by opening the joints, replacing the rubber/ leather gasket including cleaning the joints and refixing the fittings complete all as directed. |
| 26 | Dismantling old rusted/unserviceable mild steel sheet/plate and Supply & Fixing mild steel sheet/plates plain or chequered including angle iron andwith riveted, bolted or welded attachment as required at site, of size and thickness as per existing for repair of PS tanks and forming holes for nuts and bolts, cutting, welding, bending cold or hot and necessary gasket for prevention of leakage and necesssary testing after fixing complete all as specified and asdirected. |
| 27 | Dismantling old rusted/unserviceable dosing arrangement and Supply and fixing multi-cavity water sanitiser / conditioning station with proportional dosing arrangement at zero discharge of the below specifications and all asdirected :-(a) MOC: Non metallic, Maximum Temperature : 45 degree Centrigrade,Operation : Power-free Automatic, Dosing pattern: Proportional, Capacity: 100 to 200 litres,Tank lid must have provision for mounting dosing pump on the lid / wall, Cavities are complete with lids, Attachments:(i) Overflow Valve (ii) Water Inlet Valve (iii) Outlet Valve (for offline automated gravity flow) (iv) Drain Valve. Make :- Altoch Dosing System Model ADS - PRO compatibility : Stequa 411 AE Refill/Prefill total refill or equivalent as per approval of E-in-C\"s Branch / HQ CE Eastern Command Kolkata |
| 28 | Supply only RefillChlorine tablets contained in plastic cylindrical sealed disposable sanitizer refill for disinfection of dinking water, suitable for operation through recommended dosing system.(i) Replacement indication: visual & weight variation(ii) Water contact orifice design: sealed when dry, exposed upon immersion(iii) operation type: Non contact, non inhalatory (iv) Cylinder dia: 2.5 inches + 0.5 inches (v) cylinder height: Minimum 10.0 inches + 0.5 inches(vi) Operation stipulations:(a) Heavy metal (Pb & Hg) contamination in the product media must be BDL as per AAS data(b) Minimum volume of water disinfected by each Chlorine tablets Refill to obtain disinfection activity of 1 ppm on spot (Inluent water quality variation, ambient & site condition variations apply) as per absorbance data generated at ?max 515 nm. Three Hundred Fifty Thousand litres. (c) Stability: Active ingredent stabilty (when stored at 25-45 degree Centigrade temp) must be at least 98% after one year as per data generated stability test protocol. |
| 29 | (d) safety & health hazard aspects on usage of the product media for regular drinking water disinfection: Heavy Metal contaminants (like Mercury & lead) in productmedia must be below detectable limit (BDL), and the product must pass the Acute Toxicity test (to specially confirm non toxicity for mammalian cells), based on which the product must be considered safe to use for human health safety point of view and freedom from toxicity when used in drinking water disinfection in recommended dosage. (e) The refills must ensure infrastructiral safety (as per data generated by Electrolytic Conductivity (µs/cm) test protocal) and operators health safety (f) Chlorine tablets Refill must be Complaint with operators health safety considering regular exposure. The brand and make of the sanitizer must be stated and certified by a laboratory / study centre of any Govt. university.Make :- Declibac Stequa 411 AE or as per approval of E-in-C\"s Branch / HQ CE Eastern Command Kolkata. |