Supply Erection And Commissioning Of Revomax D 850 Kg Per Hr Boiler To Feed Milling Plant At S V Gosamrakshanasala Ttd Tirupati With 5 Years Maintenancesub Estimate , Boiler 01 Set Including Steam Separatorpressure Part Assembly Consisting Of Closely Woun-Andhra Pradesh

Tirumala Tirupati Devasthanams-TTD has published Supply Erection And Commissioning Of Revomax D 850 Kg Per Hr Boiler To Feed Milling Plant At S V Gosamrakshanasala Ttd Tirupati With 5 Years Maintenancesub Estimate , Boiler 01 Set Including Steam Separatorpressure Part Assembly Consisting Of Closely Woun. Submission Date for this Tender is 20-07-2022. Kitchen Equipment Tenders in Andhra Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

32961983
Supply Erection And Commissioning Of Revomax D 850 Kg Per Hr Boiler To Feed Milling Plant At S V Gosamrakshanasala Ttd Tirupati With 5 Years Maintenancesub Estimate , Boiler 01 Set Including Steam Separatorpressure Part Assembly Consisting Of Closely Woun
Open Tender
Indian
Andhra Pradesh
20-07-2022

Tender Details

Supply Erection And Commissioning Of Revomax D 850 Kg Per Hr Boiler To Feed Milling Plant At S V Gosamrakshanasala Ttd Tirupati With 5 Years Maintenancesub Estimate , Boiler 01 Set Including Steam Separatorpressure Part Assembly Consisting Of Closely Wound Helical Vertical Membrane Coil Fabricated Out Of High Temperature Resistant Erw Tubes And Flatsdouble Jacketed Air Casing With An Aluminum Radiator To Enclose The Pressure Parts And Serve As An Integral Combustion Air Pre Heater Auxilaries 01 Setpressure Atomised Forced Draft Down Firing Burner Assembly Suitable For Ldo Hsd Firingblower Coupled With Motor Mounted On Bottom Chassis Duly Connected To The Jacketfuel Pump Coupled With Motor Mounted On Pumping Modulewater Pump With Surge Suppressor And Relief Valve Mounted On Pumping Moduleatmospheric Economizer And Heat Optimizer To Pre Heat Feed Waterdust Protected Pre Wired Control Panel With Necessary Switch Gear Power And Control Circuitryset Of Tool Kit Piping 01 Setfeed Water Line Between Optimizer Economizer Feed Pump And Boilerfuel Oil Line Between Fuel Pump Ystrainer Burner Mountings And Fittings 01 Setset Of Isolating Needle Valves For Indicating Instrumentsa Steammain Steam Stop Valve Auxiliary Steam Stop Valvesingle Port Spring Loaded Safety Valvespring Loaded Safety Valveb Water Y Strainer Drain Valve For Economizerrelief Valve On Feed Water Pumpnon Return Valve On Feed Water Lineball Valve For Coil Blow Downc Fueloil Linestrainer Y Type On Fuel Oil Linemain Fuel Filter Loose Supply Instruments Controls And Safeties 01 Set Burner Programmer With Matching Flame Detectorset Audiovisual Alarms For Abnormal Conditionsa Steamsteam Pressure Switch For Burner On Off Controlsteam Pressure Gauge Steam Temperature Indicator Cum Switch For High Alarmb Water Low Water Level Alarm Switch On Economizerblow Down Valve Limit Switchc Fuel Fuel Pressure Indicator,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 40 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfuel Circuit 25 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit Ms Tank 500 Ltrs Capacity Of Size 1000 Mm Into 750 Mm Into 750 Mm Into 5 Mm Thick,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit Level Indicator,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfuel Circuit 15 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 40 Nb Ball Valve Ci F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 40 Nb Strainer C I F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 25 Nb Ball Valve C I F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 3 By 8 Inch Into 1 Mtr Mettalic Hose,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit 15 Nb Brass Nrv S By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Fuel Circuit M S Structurals,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Feed Water Circuit 40 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfeed Water Circuit 25 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Feed Water Circuit Water Tank Triple Layer Sintex 3000 Ltrs Capacity,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfeed Water Circuit Level Indicator,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfeed Water Circuit 40 Nb Strainer Ci F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurementsfeed Water Circuit 40 Nb Ball Valve C I F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Feed Water Circuit 25 Nb Ball Valve C I F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Feed Water Circuit 15 Nb Ball Valve C I S By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Feed Water Circuit Structurals,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 50 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 25 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 25 Nb Globe Valve Cs F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 65 Nb Ms Pipe Line,20 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 40 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit 15 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit Moisture Seperator,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Boiler Circuit Structurals,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Prv Circuit Prs,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Prv Circuit 15 Nb M S Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Prv Circuit Structurals,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit 50 Nb Ms Pipe,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit Pressure Gauage,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit 50 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit 50 Nb Globe Valve Cs F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements 25 Nb Ms Pipe Line,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit 25Nb Globe Valve Cs F By E,Supply And Fixing Of Revomax D 850 Kg Per Hr Boiler Piping And Accessories Noteall Pipes Are Jindal Make C Classglobe Valves Gate Valves Strainers Are Marck Make Insulation Measurements Are As Per Is Standard Means Bends Flange And Valve Box Are Double Measurements Process Circuit 15 Nb M S Pipe Line,15 Nb Globe Valve S By E,15 Nb Steam Trap Td3,Structturals,Fuel Gas Circuit Chimney Self Supported Monkey Ladder Chimney Is 350 Mm Into 350Mm Into 6Mm Thick 12 Mtrs 6 Mtrs 2 Parts With Cowl Foundation Bolt Base Plate Soot Door With Two Coats Of Heat Resistant Aluminum Paint,Fuel Gas Circuit Ducting 250 Nb M S Ducting 5 Mm Thick,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 50 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 40 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 65 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 25 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 15 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd 20 Nb Pipe Insulation,50 Mm Thick Mineral Wool 24 Swg Aluminim Clading Measurements Are Is Standerd Ducting Insulation,Rxd 850 Boilerboiler And Accessories Leading And Erection,Pressure Reducing Stationpressure Reducing Station Tprs With Direct Acting Prv Withstd Globe Valves And Fabricated Moisture Seperatori By L Into O By L Line Size 40 Into 65 Nbi By L Into O By L End Connection Fl Ash 150 By Ash 150Steam Flowrate Equals 800 Kg Per Hrinlet Pressure Equals 10 Kg Per Sq Cmoutlet Pressure Equals 4 Kg Per Sq Cmsafety Valve Pressure Equals 4 Point 5 Kg Per Sq Cmprv Size Equals 25 Nb,Supply Of Thermax Water Softener Capacity Of 1 Cubic Metre Per Hr As Per Scope Of Supply With Raw Water Pump,Annual Maintenance Contract For 850 Kgs Steam Boiler

Key Value

Document Fees
Refer document
EMD
INR 32900.0 /-
Tender Value
Refer document

BOQ Items

Sl. No. Item Name
1BOILER 01 Set Including Steam separator Pressure part assembly consisting of closely wound helical vertical membrane coil fabricated out of high temperature resistant ERW tubes and flats Double jacketed air casing with an aluminum radiator to enclose the Pressure parts and serve as an integral combustion air pre heater AUXILARIES 01 Set Pressure atomised forced draft down firing burner assembly suitable for LDO HSD firing Blower coupled with motor mounted on bottom chassis duly connected to the Jacket Fuel pump coupled with motor mounted on pumping module Water pump with surge suppressor and relief valve mounted on pumping module Atmospheric economizer and heat optimizer to pre heat feed Water Dust protected pre wired control panel with necessary switch gear power and control circuitry Set of tool kit PIPING 01 Set Feed Water line between optimizer economizer feed pump and boiler Fuel oil line between Fuel pump Ystrainer burner MOUNTINGS AND FITTINGS 01 Set Set of isolating needle valves for indicating instruments A STEAM Main steam stop valve Auxiliary steam stop valve Single port spring loaded safety valve spring loaded safety valve B WATER Y strainer Drain valve for economizer Relief valve on feed Water pump Non return valve on feed Water line Ball valve for coil blow down C FUEL Oil Line Strainer Y type on fuel oil line Main Fuel filter loose supply INSTRUMENTS CONTROLS AND SAFETIES 01 Set Burner programmer with matching flame detector Set Audiovisual alarms for abnormal conditions A STEAM Steam Pressure switch for burner on OFF control Steam Pressure gauge Steam temperature indicator cum switch for high alarm B WATER Low Water level alarm switch on economizer Blow down valve limit switch C FUEL Fuel Pressure indicator
2Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 40 NB M S pipe line
3Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 25 NB M S pipe line
4Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit MS TANK 500 Ltrs capacity of size 1000 mm into 750 mm into 750 mm into 5 mm thick
5Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit Level Indicator
6Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 15 NB M S Pipe Line
7Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 40 NB BALL VALVE CI F by E
8Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 40 NB STRAINER C I F by E
9Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 25 NB BALL VALVE C I F by E
10Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 3 by 8 inch into 1 Mtr mettalic hose
11Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit 15 NB Brass NRV S by E
12Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Fuel Circuit M S Structurals
13Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 40 NB M S pipe line
14Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 25 NB M S pipe line
15Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit WATER TANK Triple Layer Sintex 3000 Ltrs capacity
16Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit Level Indicator
17Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 40 NB Strainer CI F by E
18Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 40 NB BALL VALVE C I F by E
19Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 25 NB BALL VALVE C I F by E
20Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit 15 NB BALL VALVE C I S by E
21Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Feed Water Circuit Structurals
22Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit 50 NB MS Pipe line
23Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit 25 NB MS Pipe line
24Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler circuit 25 NB Globe valve CS F by E
25Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit 65 NB MS Pipe Line
2620 NB MS pipe line
27Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit 40 NB MS Pipe Line
28Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit 15 NB MS Pipe Line
29Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit Moisture Seperator
30Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements Boiler Circuit Structurals
31Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PRV Circuit PRS
32Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PRV Circuit 15 NB M S Pipe line
33Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PRV Circuit Structurals
34Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PROCESS CIRCUIT 50 NB MS PIPE
35Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PROCESS CIRCUIT PRESSURE GAUAGE
36Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PROCESS CIRCUIT 50 NB MS PIPE LINE
37Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PROCESS CIRCUIT 50 NB GLOBE VALVE CS F by E
38Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements 25 NB MS Pipe line
39Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements process circuit 25NB GLOBE VALVE CS F by E
40Supply and fixing of Revomax D 850 kg per hr Boiler Piping and Accessories Note All Pipes are Jindal Make C Class Globe valves Gate valves strainers are Marck make Insulation Measurements are as per IS Standard Means Bends Flange and Valve Box are Double Measurements PROCESS CIRCUIT 15 NB M S PIPE LINE
4115 NB Globe valve S by E
4215 NB Steam Trap TD3
43Structturals
44FUEL GAS CIRCUIT Chimney Self supported Monkey Ladder Chimney is 350 mm into 350mm into 6mm thick 12 Mtrs 6 Mtrs 2 parts with Cowl Foundation Bolt Base Plate Soot door with two coats of Heat resistant aluminum paint
45FUEL GAS CIRCUIT Ducting 250 NB M S Ducting 5 mm thick
4650 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 50 NB pipe insulation
4750 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 40 NB pipe insulation
4850 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 65 NB pipe insulation
4950 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 25 NB pipe insulation
5050 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 15 NB pipe insulation
5150 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD 20 NB pipe insulation
5250 MM THICK MINERAL WOOL 24 SWG ALUMINIM CLADING MEASUREMENTS ARE IS STANDERD Ducting Insulation
53RXD 850 Boiler Boiler and Accessories Leading and Erection
54Pressure Reducing Station Pressure Reducing Station TPRS With Direct Acting PRV With Std Globe Valves and Fabricated Moisture seperator I by L into O by L Line Size 40 into 65 NB I by L into O by L End Connection FL ash 150 by ash 150 Steam Flowrate equals 800 kg per hr Inlet Pressure Equals 10 kg per sq cm Outlet Pressure Equals 4 kg per sq cm Safety Valve Pressure Equals 4 point 5 kg per sq cm PRV Size Equals 25 NB
55Supply of THERMAX Water Softener capacity of 1 Cubic metre per hr As per scope of supply with raw water pump
56Annual Maintenance contract for 850 Kgs Steam Boiler
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail