Tribal Welfare Department-TWD has published Infrastructural Development Of Padum Pukhuri Archaeological Site, Sadiya Under Directorate Of Archaeology, Assam Under The Scheme Cms Special One Time Assistance To Chutia Community For The Year 2021-22. Submission Date for this Tender is 15-07-2022. Archaeological service Tenders in guwahati Assam. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Item of Work:- |
2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2.8.1 All kinds of soil |
3 | Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna sand, with common burnt clay non modular bricks. |
4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 4.1.5 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) |
5 | Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : 7.1.1 Cement mortar 1:6 (1 cement : 6 coarse sand) |
6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.5.22.5 Hard drawn steel wire fabric |
7 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete above plinth level.5.22A.5 Hard drawn steel wire fabric |
8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 5.1.2 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
9 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) |
10 | Centering and shuttering including strutting, propping etc. and removal of form for : |
11 | Foundations, footings, bases of columns, etc. for mass concrete |
12 | Lintels, beams, plinth beams, girders, bressumers and cantilevers |
13 | Columns, Pillars, Piers, Abutments, Posts and Struts |
14 | Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level. 6.13.2 Cement mortar 1:4 (1 cement :4 coarse sand) |
15 | 15 mm cement plaster on the rough side of single or half brick wall of mix :1:4 (1 cement: 4 fine sand) |
16 | Providing and fixing M.S. grills of required pattern in frames of windowsetc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. 9.48.1 Fixed to steel windows by welding. |
17 | Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): 13.31.2 Raised and cut pointing |
18 | Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gms/litre, of approved manufacturer, of required shade and colour complete, as per manufacturer’s specification. Two or more coats on new work |
19 | Finishing walls with Acrylic Smooth exterior paint of required shade : 13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) |
20 | Finishing walls with water proofing cement paint of required shade : 13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm) |
21 | Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer"s specifications including appropriate priming coat, preparation of surface, etc. complete. 13.52.1 On steel work |
22 | Clearing Jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30cm measured at a height of 1m above ground level and removal of rubbish upto a distance of 50m outside the peripheri of the area cleared. |
23 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
24 | Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-incharge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.). |
25 | Providing and fixing bolts including nuts and washers complete. |
26 | Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. 12.1.1 1.00 mm thick with zinc coating not less than 275 gm/m² |
27 | Applying priming coat: 13.50.3 With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works |
28 | Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : 13.48.3 Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/ 10 sqm of approved brand and manufacture |
29 | Letter writing with Florecent letter complete as per dirtection and specification and fixing with the frame |
30 | Scientific debris clearance engaging highly skilled labour, semi skilled labour and unskilled labours including supplying necessary equipents like site bags, hunter shoes, etc and construction of temporary huts for klitchen, dining with thatched / PVC roof for Archaeological officials and staff. The item also include supply of stationary items/ materials, different tools for excavation, camp cot folding, quilt etc. including providing water supply and sanitary facilities at camp area. The item also include documentation like printing of photographs - 200 Nos. , printing of reports etc. under the supervision of Archaeological deptt. Bill to be countersigned by representative of Directorate of Archaeology, Govt. of Assam for payment. (All materials recovered during excavation will be the property of Archaeology Deptt., Govt. of Assam) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy