Repair / Maint / Servicing / Cleaning Of Central Ac Plants / Cold Storage Chamber At Ch Cc, Cmdc, Base Hosp Area Uder Ge E / M Lucknow
Tender Overview
Project Description
Repair / Maint / Servicing / Cleaning Of Central Ac Plants / Cold Storage Chamber At Ch Cc, Cmdc, Base Hosp Area Uder Ge E / M Lucknow
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 23-Jun-2022 | Bid Auto Extn Corrigendum | Bid Auto Extn Corrigendum | 30-Jun-2022 |
BOQ
| Sl. No. | Item Description |
| 1 | Attending the complaint of AC PLANT ,Walking Cooler , by Refg mechanic /electrician/ technician for non functiong part of compressor , Blower motor , compressor pump , chiller pump , CT fan ,AHU Electric paneland all parts of AC Plantat any location ,any capacity make and modelandrectified the same all as directed by EIC.Note : - (i) Complaint Should be attended immediately within one hrs & to be Rectified the same day at the earliest without effecting of service .( II ) Complaint should be attended 24 hrs through phone , ( III ) Complaint should be detail / attended by Specified Electrician / technician / Mechanic knowldge of AC Plant ( IV ) Contractor are provide toallnecessary T&Pto attending and rectified complaints |
| 2 | M&L for 3 x 15 TR capacity AC plant Descalingof all sets ofcondensor tubes of central AC plant by disconnecting the condensor from the system, cleaning by descaling pump of suitable capacity of 110 ft head using descaling solution of Make:-MAIC / HIBIRD or Hydrochloric acid 20%, cleaning the system through cooling tower by using descaling solution, cleaning condensor tubes by nylon brushes & mild steel rods of suitable size, renewal of suction water filter as per below AC Plants. (Note:- T&P such as pumps, tube etc & descaling solution etc shall be arranged by the contractor at his own cost.) |
| 3 | All as per item No 02 but 3x9 TR capacity plant |
| 4 | All as per item No 02 but 2x7.5 TR capacity plant |
| 5 | All as per item No 02 but 3x45 TR capacity plant |
| 6 | All as per item No 02but 3x80 TR capacity |
| 7 | All as per item No 02 but 3X37.5 TRcapacity |
| 8 | All as per item No 02 but 1X60TRcapacity |
| 9 | All as per item No 02but 3X50 TRcapacity |
| 10 | All as per item No 02but 3X75 TRcapacity |
| 11 | Carrying out pressure leak testing by nitrogen gas of the system of AC plant for leak proof valve joints, seal & other connected controls etc. including identifying & rectifying of leaks, defects (if any) & maintaining constant pressure of 160 LBS PSI on low side & 200 PSI on high side at least for 24 Hrsof any size and capicityCentral AC plant .complete all as specified and directed. :- (Note: The arrangement of T&P & nitrogen gas shall be contractors responsibility). |
| 12 | Cleaning of AHU cooling coil (after Opening front portion of AHU) by applying high air pressure followed by descaling solution Chemical agent& then washing with water pressure using jet pump and reassembling there after complete all as specified and directed by EIC including servicing of AC ducts cleaning etc and setting of grills, louvers and position of proportioning dampers & also minor repair to duct insulation for missing section completefor the following central AC plant :- 3 x 15 TR capacity AC plant |
| 13 | All as per item No 12 but 3x9 TR capacity plant |
| 14 | All as per item No 12 but 2x75 TR capacity plant |
| 15 | All as per item No 12 but 3x45 TR capacity plant |
| 16 | All as per item No 12 but 3x80 TR capacity |
| 17 | All as per item No 12 but 3X37.5 TRcapacity |
| 18 | All as per item No 12 but 1X60TRcapacity |
| 19 | All as per item No 12but 3X75 TRcapacity |
| 20 | All as per item No 12 but 3X50 TRcapacity |
| 21 | S&F Nylon \"V\" belts of A -34 as below sizes |
| 22 | All as per item No 21 but B- 64 |
| 23 | All as per item No 21 but B- 82 |
| 24 | All as per item No 21 but B- 68 |
| 25 | All as per item No 21 but C-120 |
| 26 | All as per item No 21but B-78 |
| 27 | All as per item No 21 but B-76 |
| 28 | Taking out oil filter of compressor Make :- ACCEL, Model SMC 4 - 65 cleaning the filter by using kerosene or diesel and fixing in its original position with gasket set all as specified and directed. |
| 29 | Taking out oil filter of compressor Make :- Freeze king, FK - 750 cleaning the filter by using kerosene or diesel and fixing in its original position with gasket set all as specified and directed. |
| 30 | Taking out oil filter of compressor Make :- ACCEL, Model SMC 3 - 65 cleaning the filter by using kerosene or diesel and fixing in its original position with gasket set all as specified and directed. |
| 31 | Taking out oil filter of compressor Make :- ACCEL, Model SMC 4 - 100 cleaning the filter by using kerosene or diesel and fixing in its original position with gasket set all as specified and directed. |
| 32 | Taking out the defective hand shut off valve of pressure gauge and supply & fixing new handshut off valve ¼\" dia complete all as specified and directed. |
| 33 | Taking out the defective safety valve of compressor Make:- ACCEL, Model - SMC - 4 - 65 and supply & fixing new safety valve complete all as specified and directed by EIC. |
| 34 | Taking out the defective condensor safety valve suitable for working pressure of 350 PSI all as specified and directed. |
| 35 | Taking out unserviceable defective finned strip heater and supply and fixing strip heater 3 KW suitable for AC plantincluding provision of nuts, bolts & washers etc all as specified and directed. |
| 36 | Dismantling defective GM gate valve 20 mm dia at drain pipe of cooling tower of AC Plant supply & fixing new GM gate valve 15 mm dia with GI Nipple, bends etc nuts & bolts and necessary electric welding all as specified and directed. |
| 37 | Dismantling and removing defective Finns of FRP type cooling tower and supply and fixing new PVC Finns brick containing eleven layers size of brick 600 x 30 x 150 mm complete all as specified and directed. |
| 38 | Taking down carefully rotating sprinkler from cooling towers and S&F new rotating sprinkler assembly from comprising of coupling made out of aluminium alloy with one side 50 to100 mm threaded, and other side with fixing arrangement of 04 Nos sprinkler arm distributed four way with one side ball bearing for easy rotation complete including 04 Nos of PVC heavy duty sprinkler arm pipe of 25 mm dia 300 mm long with six holes of 20 mm dia at equal interval complete with one side threaded check nut and other side dead end complete all as specified and directed. |
| 39 | Taking out wire mesh filter from AHUs , cleaning the filter with castic soda and water with pump pressure and reassembling in their position complete all as specified.( Note Ceaning shall be done three times in a season and payment shall be made in once only .) |
| 40 | Supply , assembly and erection of GI sheet with C & SS rectangular/square duct made out of \"L\"shaped hollow profile, duly factory boxed, incl all accessories such as Corner, Cleat, Carriage bolt, Gasket and appropriate sealant on longitudinal joints etc complete of size 26 Gauge. |
| 41 | Supply and lay M S Pipesof size 50 mm heavy grade with all fittings laid in floors or fixed to walls andceilings etc of sizes as shown |
| 42 | Supply and lay M S Pipesof size 65 mm heavy grade with all fittings laid in floors or fixed to walls andceilings etc of sizes as shown |
| 43 | Supply and lay M S Pipesof size 80mm heavy grade with all fittings laid in floors or fixed to walls andceilings etc of sizes as shown |
| 44 | Dismantling defective butterflyof size 50 mm dia at drain pipe of cooling tower of AC Plant supply & fixing new butterflyvalve 65 mm dia with complete accessoriesall as specified and directed. |
| 45 | Dismantling defective butterflyof size 65 mm dia at drain pipe of cooling tower of AC Plant supply & fixing new butterflyvalve 65 mm dia with complete accessoriesall as specified and directed. |
| 46 | Dismantling defective butterflyof size 80 mm dia at drain pipe of cooling tower of AC Plant supply & fixing new butterflyvalve 65 mm dia with complete accessoriesall as specified and directed. |
| 47 | Dismantling defective butterflyof size 100 mm dia at drain pipe of cooling tower of AC Plant supply & fixing new butterflyvalve 65 mm dia with complete accessoriesall as specified and directed. |
| 48 | Supply, installation,commissioning and testing of induced draft top discharge counterflow type FRP Cooling Tower10TR (Rectangular/Round bottle shape) with FRP body and base, water spray eaders, cooling tower fills, fan with motor, supporting base frames, as per manufacturer\"standard instructions.Note- Oll dmtrl will be deposited in MES store yard. |
| 49 | S& FHigh Efficiency Particulate Air Filters,(HEPA) Efficiency 99.97% (EU13)down to 0.3 micron filter,mediaThe filters all use a pleated fiberglass media, folded,and separated by aluminum spacers in a metal frame. all as specified and directed |
| 50 | S& Ffine filter (EU-7)Efficiency 99 % down to 03 micron Filter Media: HDPE Media / Non Woven Synthetic Media Type: HDPE 1 ply+Non Woven Synthetic Media 1 ply+ al. mesh 1, ply, Type - BOX Type, MICRON -3, Frame MOC - Aluminium all as specified and directed |
| 51 | S& F Pre filter (EU-4)Efficiency 90 % down to 10 micron Filter Media: HDPE Media / Non Woven Synthetic Media Type: HDPE 1 ply+Non Woven Synthetic Media 1 ply+ al. mesh 1, ply Type - BOX Type, MICRON -10, Frame MOC - GI SHEET |
| 52 | Cleaning of AC supply and return duct, diffusers, dampers, coilinstalled components by Robotic vedio camera at CH (CC) for 05 nos OT including carry outBaceriogical test after cleaning of duct and submission of test report complete all as directed. Note - If Air culture report not as per OTstandard,it will be re-done by the contractortill saturationreport by OT userwithout any extra cost to the department. |
| 53 | Cleaning of AC supply and return duct, diffusers, dampers, coilinstalled components by Robotic vedio camera at Base Hospital for 04 nos OT including carry outBaceriogical test after cleaning of duct and submission of test report complete all as directed. |
| 54 | Cleaning of AC supply and return duct, diffusers, dampers, coilinstalled components by Robotic vedio camera atICU ACplants CH CC /NEFRO/X -RAY AC PLANTS/CMDC AC PLANTSincluding carry outBaceriogical test after cleaning of duct and submission of test report complete all as directed. |
| 55 | Taking out defective / burnt power contractor from electric panel board and S&F in replacement new Power contactor 3 TF 49 (Make :- seimens) with NO & NC contact , of coil Volatge 220 V all as specified and directed. |
| 56 | S&F in replacement new Power contactor 3 TF 30 in existing LT panelall as specified and directed. |
| 57 | S&F in replacement new Power contactor 3 TF 31 in existing LT panelall as specified and directed. |
| 58 | Supply and fixing in replacement power contactor MNX 18, 3 phase in existing LT panel all as specified and directed. |
| 59 | Supply and fixingin replacement water flow meter of model HFS-25 having maximum working pressure10 bar and liquid temperature 01 to 100 degree centigrade all as specified. |
| 60 | Taking out defective / burnt power contactor from electric panel board and S&F in replacement new power contactor 3 TS 47. (make :- Seimens) all as specified and directed. |
| 61 | Supply and fixing in replacement auxillary contactor MNX A1, 3 phase in existing LT panel all as specified and directed. |
| 62 | Supply and fixing in replacement auxillary contactor MNX A2, 3 phase in existing LT panel all as specified and directed. |
| 63 | Supply and fixing in replacement three ways mixing valve switchmodel No GLB 331.9E of siemence in existing LT panel all as specified and directed. |
| 64 | Taking out carefully defective electronic timer from panel board and S&F new electronic timer Cat No. 800-S/7PU rating 30 to 0/60 to 20 in position complete all as specified Make Siemens/ Selectron |
| 65 | Taking out carefully defective/burnt single phase preventor complete with wiring from LT panel and supply & fixing in replacement in position single preventer complete with wiring all asspecified and directed. |
| 66 | Taking out carefully defective / burnt power contactor type ML-1.5from the LT panel board and supply & fixing new in position in replacement power contractor ML-1.5 all as specified and directed. |
| 67 | Taking out carefully defective / burnt power contactor type MNX 12from the LT panel board and supply & fixing new in position in replacement power contractor MNX 12 all as specified and directed. |
| 68 | S&F (in replacement) motor terminal plates complete with nut, bolts and washers etc suitable for 75/10/15/20 HP capacity electric motor all as specified and directed. |
| 69 | Disconnecting electrically unserviceable CT fan motor andSupply installation testing and commissioningof CT fan motor complete with other accessories like fan blades etc. 3 phase, 415 Volts, 7.5 HP capacity complete all as specified and directed by EIC. |
| 70 | All as per item No 69 above but CT fan 3 HP. |
| 71 | All as per item No 69 above but CT fan 2 HP. |
| 72 | All as per item No 69 above but CT fan 1.5 HP. ( Note -for item no 69 to 72 , Old motor will be deposited in mES store yard ) |
| 73 | S& Ffresh compressor oil into the plant at different locations in Lucknow Canttwith in a distance of not exceeding 6 Km complete all as specified and directed. |
| 74 | Disconnecting electrically three phase 440 volt induction motor 20 HPunbolting it and transporting to the contractor workshop opening it to taking out burnt out copper windings, cleaning of stator slots by means of CTC or petrol and rewinding it with suitable size/gauge copper enameled wire including insulating/varnishingmaterial, replacement of damaged ball bearing of suitable sizeand transporting it to the site and refixing to its original position and making necessary electrical connection and testing complete all as directed by Engr-in-Charge. |
| 75 | All as item No 74 above but capicity of 50 HP |
| 76 | All as item No 74 above but capicity of 37.5 HP |
| 77 | All as item No 74 above but capicity of 12.5 HP |
| 78 | Dismantling of monoblock pump of capacity 5 HP from its foundation after unbolting it and servicing/overhauling of pump complete including replacemnt of worn out spares such as ball bearings,gland bush,gland packing,nuts and bolts of gland,greasing and oiling of all moving parts,grinding/turning etc. and reassembling the pump including re-installation to its original position including testing of water leakageall as specified and directed. |
| 79 | Scarpping of old painted surfaces of central type AC plant of any capacity and M&L for spray paintingand arrow marking with approved colour after preparing all equipments for smooth surfaces of compressor,condensor,monoblock pumps,compressor motors,motor starter,LT panel boards,water supply/dischargepipe lines,cooling tower,supply and discharge lines,liquid lines,AHUs etc including all connected accessories and marking of refrigerant system,water supply system etc with approved colour and marking of SM/MES nos with black enamelled paint of approved size and marking of incomng/outgoing electrical connection on LT panel board,operator room,glow sign boards of AC plant with approved colour on blue back ground all as directed at site by EIC. |
| 80 | Supply and chargingrefrigerant gasCFC compatible to R-22 in returnable sealed cylinder all as specified and directed. |
| 81 | S&F in replacement 13 TR Water cooled condenser suitable for existing plant complete with drier filter to connection between condensor and compressor testing and commisioning complete all as specified and directed. ( Note - , Old mtrlwill be deposited in mES store yard ) |
| 82 | S&F in replacement 13 TR scrolled compressor suitable for existing plant including R-407 refrigerant gas of suitable quantity with testing and commisioning complete all as specified and directed. ( Note - Old mtr shall be deposited in MES store yard ) |
| 83 | Material & labour for taking down and S &fixing new door forcold storage plantsof size 1200x2100 mmwithleaf panels are injected with high pressure polyurethane.doors have a smooth metal surface which can be easily and hygienically cleaned with pench, screw for fixingall as specified and directed . |
| 84 | Material & labour for Hermetic scroll compress for cold storage plantof capacity 7.5TRincludingchargingsuitable gas appropirate qtyincluding testing and commissiningcompleteall as specified and directed. |
| 85 | Material & labour for Hermetic scroll compress for cold storage plantt of capacity 05 TRincludingchargingsuitable gas appropirate qtyincluding testing and commissiningcompleteall as specified and directed. |
| 86 | Material & labour for Hermetic scroll compress for package type ac plantof capacity6.5TRincludingchargingsuitable gas appropirate qtyincluding testing and commissiningcompleteall as specified and directed. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.