WORK OF DEEPENING & DESILTING OF EXISTING OPENWELL WITH HORIZONTAL BORING AT PIPED WATER SUPPLY SCHEME REODARSUB DN REODAR AGAINST FAILURE MONSOON
Tender Value
9 Lakhs
Estimated cost
Bid Submission
06 Jun 2022
0 days left
EMD
18000
Bank guarantee accepted
Document Fee
500
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
reodar → Rajasthan
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
WORK OF DEEPENING & DESILTING OF EXISTING OPENWELL WITH HORIZONTAL BORING AT PIPED WATER SUPPLY SCHEME REODARSUB DN REODAR AGAINST FAILURE MONSOON
BOQ
| Sl. No. | Item Description |
| 1 | Rates are Based on PHEDBSR 2021 Jaipur & PWD BSR 2019 Circle Sirohi |
| 2 | Location-Open well No-3 |
| 3 | Earth work in excavation over areas (exceeding 30cm depth, 1.5 mtr in width and 10 SQM in plan)for construction of open well, lift up to 1.5 Mtr. including taking out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50 meter.(18.00 to 25.00mtr) Ordinary Rock |
| 4 | Earth work in excavation in foundation trenches or drains including dressing of sides and ramming of bottoms, lift up to 1.5 Mtr. including taking out the excavated soil and depositing and refilling of jhiri with watering and ramming and disposals of surplus excavated soil as directed with a lead in a 50 meter. |
| 5 | Add extra over item No. 2.39.2-4 for every additional lift of 1.5 Mtr. or part thereof : In Ordinary rock and hard rock. |
| 6 | 18.00 to 19.50 Mt. |
| 7 | 19.50 to 21.00 Mt. |
| 8 | 21.00 to 22.50 Mt. |
| 9 | 22.50 to24.00 Mt. |
| 10 | 24.00 to 25.00 Mt. |
| 11 | Add 20% extra over item No. 2.39 for excavation in saturated soil where pumping or baling out of water is required, including shoring strutting where required and dewatering. |
| 12 | Ordinary Rock |
| 13 | Labour charges for horizontal boring 100 mm dia in open well in rocky stratawith all types of rock cutting & drilling tools etc. including all T&P required for job including dewatering arrangement. |
| 14 | Demolishing of R.C.C. work including stacking of steel bars and disposal of unserviceab le material within 50 meters lead. |
| 15 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor three level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1-Cement:3-coarse sand) and making good the joints excluding cost of centering shuttering and reinforcement : |
| 16 | 1:1.5:3 (1-Cement:1.5 coarse sand:3-graded stone aggregate 20 mm nominal size). |
| 17 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor three level. Hot rolled deformed bars |
| 18 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members andremoval of formwork for superstructure up to 4.5 mtr aboveplinth,for Walls (any thickness) including attached pilasters, buttresses, plinth and string course. |
| 19 | Add extra for shuttering in circular work in plan up to dia 10 m over item Nos. 4.12.1 to 4.12.3 |
| 20 | Structural steel work in single section fixed without connecting plate including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete above plinth level up to 4.5 mtr. height in R.S. joist flats, tees, angles and channels. |
| 21 | Location-Open well No-5 |
| 22 | Earth work in excavation over areas (exceeding 30cm depth, 1.5 mtr in width and 10 SQM in plan)for construction of open well, lift up to 1.5 Mtr. including taking out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50 meter.(18.00 to 25.00mtr) Ordinary Rock |
| 23 | Earth work in excavation in foundation trenches or drains including dressing of sides and ramming of bottoms, lift up to 1.5 Mtr. including taking out the excavated soil and depositing and refilling of jhiri with watering and ramming and disposals of surplus excavated soil as directed with a lead in a 50 meter. |
| 24 | Add extra over item No. 2.39.2-4 for every additional lift of 1.5 Mtr. or part thereof : In Ordinary rock and hard rock. |
| 25 | 18.00 to 19.50 Mt. |
| 26 | 19.50 to 21.00 Mt. |
| 27 | 21.00 to 22.50 Mt. |
| 28 | 22.50 to24.00 Mt. |
| 29 | 24.00 to 25.00 Mt. |
| 30 | Add 20% extra over item No. 2.39 for excavation in saturated soil where pumping or baling out of water is required, including shoring strutting where required and dewatering. |
| 31 | Ordinary Rock |
| 32 | Labour charges for horizontal boring 100 mm dia in open well in rocky stratawith all types of rock cutting & drilling tools etc. including all T&P required for job including dewatering arrangement. |
| 33 | Demolishing of R.C.C. work including stacking of steel bars and disposal of unserviceab le material within 50 meters lead. |
| 34 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor three level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1-Cement:3-coarse sand) and making good the joints excluding cost of centering shuttering and reinforcement : |
| 35 | 1:1.5:3 (1-Cement:1.5 coarse sand:3-graded stone aggregate 20 mm nominal size). |
| 36 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor three level. Hot rolled deformed bars |
| 37 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members andremoval of formwork for superstructure up to 4.5 mtr aboveplinth,for Walls (any thickness) including attached pilasters, buttresses, plinth and string course. |
| 38 | Add extra for shuttering in circular work in plan up to dia 10 m over item Nos. 4.12.1 to 4.12.3 |
| 39 | Structural steel work in single section fixed without connecting plate including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete above plinth level up to 4.5 mtr. height in R.S. joist flats, tees, angles and channels. |
AI Tender Summary
Tender Timeline
May 23, 2022
11:30 IST
Tender Published
Tender notice published.
CompletedJun 06, 2022
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJun 08, 2022
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender