| 1 | Loading, Unloading and safe cartage of the following materials from Electricity Store Centre, Bahraich to the work site/dump site. All the material at Sl. No. 1 shall be given by department and rest all the material including civil material will be arranged by the contractor itself. Any other material if required for completion of work which might not have been mentioned in bid document, shall be arranged by the contractor. (Decentralized Items Provided by the Contractor as per Estimate). |
| 2 | Cartage of ST Pole 11 Mtr long |
| 3 | Cartage of PCC Pole 8.5 Mtr long |
| 4 | Cartage of Other line materials |
| 5 | Carriage of ACSR Weasel Conductor |
| 6 | Carriage of 11 KV 3x120 sq. mm. XLPE Cable |
| 7 | Carriage of 11 KV 3x185 sq. mm. XLPE Cable |
| 8 | Carriage of AB Cable 1x25+1x16 mm2 |
| 9 | Carriage of AB Cable 3x50+1x35+1x25 mm2 |
| 10 | Carriage of AB Cable 3x95+1x70+1x25mm2 |
| 11 | Carriage of AB Cable 3x120+1x95+1x70mm2 |
| 12 | Cartage of 11 KV Cable Jointing Kit |
| 13 | Cartage of 11 KV Straight Through |
| 14 | Erection of Single PCC Pole (8.5 Mtr Long) for 11 KV/HT line alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site. |
| 15 | Erection of Single ST Pole (11 Mtr Long) for 11 KV/HT line alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site. |
| 16 | Erection of Double PCC Pole (8.5 Mtr Long) for 11 KV/HT line alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site. |
| 17 | Erection of Double ST Pole (11 Mtr Long) for 11 KV/HT line alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site. |
| 18 | Earthing of Pole as per RESSPO Norms. |
| 19 | Grouting of Poles with 1:4:8 CC ratio of cement, sand & brick ballast, backfilling of pits with mud completely. All required materials shall be provided by the contractor at his own cost. |
| 20 | Erection and Grouting of stay sets alongwith complete fittings. Cement, Sand & Brick ballast provided by the contractor at his own cost. |
| 21 | Fixing of 11 KV Cable Jointing kit |
| 22 | Fixing of 11 Straight Through |
| 23 | C.I. Pipe 10\" Dia (Provided by the Contractor) |
| 24 | G.I. Pipe 6\" Dia (Provided by the Contractor) |
| 25 | PP Clamp, G.I. Pipe Clamp, E-Bracket & T/F Clamp (Provided by the Contractor) |
| 26 | Stone Pad (Provided by the Contractor) |
| 27 | Danger Board with clamp nut & bolt (Provided by the Contractor) |
| 28 | Barbed Wire (Provided by the Contractor) |
| 29 | LT Clamp with I Hook (Provided by the Contractor) |
| 30 | Clamp for T-off & Guarding (Provided by the Contractor) |
| 31 | Laying& Commissioning of 11 KV XLPE Cable 3x120mm2 and its hoistingincluding road restoration work as per respo norms. |
| 32 | Laying& Commissioning of 11 KV XLPE Cable 3x185mm2 (D/C) and its hoistingincluding road restoration work as per respo norms. |
| 33 | Errection & Commissioning of AB cable All size including fitting of Accessories (All Accessories shall be Provided by the Contractor). |
| 34 | Dismentling of Old HT/LT line |
| 35 | Carriage of old & used recvied back material from side to store |
| 36 | Laying, stringing, sagging & binding of conductors of 11 KV in 3 phase, 3 wire line with jumpering (where as required). |
| 37 | Construction of Plinth & Fencing For 100 KVA To 400 T/F. |
| 38 | Fitting of Three Phase Distribution Box |