| 1 | Item Description/ Heading |
| 2 | Supplying & erecting mains with 2x2.5 sq.mm FRLSH copperPVC insulated wire laid in provided conduit/trunking/insidepole/Bus bars or any other places. as per specification No: WGMA/BW INCLUDINGDismantling the existing aluminium /copper mains, submains wiring upto 10 sq.mm. along with accessories etccomplete as per specification No: WG-DM/PW. (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 1-3-4 & 1-15-3) |
| 3 | Supplying & erecting mains with 2x4 sq.mm FRLSH copperPVC insulated wire laid in provided conduit/trunking/insidepole/Bus bars or any other places. as per specification No: WGMA/BWINCLUDINGDismantling the existing aluminium /copper mains, submains wiring upto 10 sq.mm. along with accessories etccomplete as per specification No: WG-DM/PW (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 1-3-6) |
| 4 | Point wiring for light/fan/bell in 20 mm ISI marked HMSPVC conduit with 1.5 sq.mm (2+1E) FRLSH grade copper wirewith flush type switch and required accessories as perspecification No: WG-PW/SW (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 1-9-6) |
| 5 | Wiring for plug on board with Switch socket, copper wiringand earthing as per specification No: WG-PW/SW (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 1-9-13) |
| 6 | Supplying and erecting double pole metal clad switch with fuse and neutral link 240V, 16A on iron / GI frame as per specification no. SW-SWR/MDP. (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 5-1-2) |
| 7 | Supplying and erecting metal clad distribution board 240V, 3 way, 16A per way & neutral bar connector complete erected on iron/ GI frame as per specification no. SW-SWR/MDB (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 5-2-2) |
| 8 | Supplying and erecting metal clad distribution board 240V, 4 way, 16A per way & neutral bar connector complete erected on iron /GI frame as per specification No. SW-SWR/MDB (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 5-2-3) |
| 9 | Supplying, erecting & marking SPMCB 6A to 32A, B- series (for lighting) in provided distribution board as per specification no. SWSWR/ MCB(INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 5-3-3) |
| 10 | Supplying & erecting HMS P.V.C. conduit 32 mm. dia. withnecessary accessories in wall/floor with chiselling appropriately as per specification No: WG-MA/CC.(INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 1-1-11) |
| 11 | Supplying and erecting double pole metal clad switch with HC type fuse and neutral link 240V, 32A on iron / GI frame as per specification no. SW-SWR/MDP . (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 5-1-3) |
| 12 | Supplying erecting and marking four pole isolators only switch version of miniature circuit breakers of 40A in provided distribution board complete.(INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 5-3-24) |
| 13 | Supplying and erecting flush type shockproof plug socket 6A & 16A (6 pin) with 16A switch combined with indicator lamp and fuse with gang box on wooden board.(INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE)(SOR 1-7-13) |
| 14 | Providing earthing with galvanized iron earth plate size 60 x 60 x 0.6 cm with funnel with a wire mesh for watering and brick masonry block C.l. cover complete with all materials, testing & recording the results as per specification no. EA-EP. (INCLUDING MATERIAL RATE, LABOUR RATE AND EPF ON LABOUR RATE) (SOR 9-1-3) |
| 15 | Total impact of GST for the purpose of CTC |