Rose House Repair And Maintenance Of The Damaged Portion Of Compound Wall Providing Barbed Fencing. Maintenance Work
Tender Value
4.77 Lakhs
Estimated cost
Bid Submission
11 May 2022
0 days left
EMD
11948
Bank guarantee accepted
Document Fee
1055
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
vazhuthacaud → Kerala
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Rose House Repair And Maintenance Of The Damaged Portion Of Compound Wall Providing Barbed Fencing. Maintenance Work
BOQ
| Sl. No. | Item Description |
| 1 | Appendix - A |
| 2 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 3 | 15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar |
| 4 | 15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar |
| 5 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) |
| 6 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 7 | OD81669/2021-2022:Random rubble masonry with cement mortar 1:6 for departmental rubble |
| 8 | OD81670/2021-2022:Brick work with common burnt clay F.P.S (non modular)bricks of class designation 7.5 in coping in cement mortar 1:4 |
| 9 | 7.2.1:Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like.Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 10 | 6.4.2:Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in:Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 11 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 12 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size |
| 13 | 5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more |
| 14 | 13.1.2:12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand). |
| 15 | 16.18.1:Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for serarately) :- Payment to be made per metre cost of total length of barbed wire used.With G.I. barbed wire |
| 16 | 10.16.1:Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.Hot finished welded type tubes |
| 17 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 18 | 14.66.2:Finish walls with Acryllic Smooth exterior paint of required shade:Old work (One or more coat applied @ 0.90 ltr/10 sqm) |
| 19 | 13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work |
| 20 | 13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) |
| 21 | 50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete. |
| 22 | OD83464/2021-2022:Cutting roots of trees above any structure of girth between 40 cm to 60 cm including stacking of serviceable materials and disposal of unserviceable materials cost of labour etc without making any damages to nearby structure etc complete |
| 23 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . |
| 24 | OD91826/2021-2022:Labour engaged for cleaning permises and stacking debries |
AI Tender Summary
Tender Timeline
May 05, 2022
11:30 IST
Tender Published
Tender notice published.
CompletedMay 11, 2022
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedMay 13, 2022
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender