Bharat Heavy Electricals Limited-BHEL has published Supply Of Lt Switchgear For Fgd Ramagundam Lt Switchgear For Fgd-Ramagundam Super Thermal Power Station Stage I Ii 3X200 Mw And 3X500mw , 415V Fgd Service Pmcc # 0Da`-- As Per Technical Specification No: Sbd-Ts-Cpbg-Fgd-Ram, Rev-00 ( Unit Rate ( At Col. Submission Date for this Tender is 18-06-2022. Switch Gear Tenders in Peddapalli Telangana. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 14-May-2022 | Due date extension - 1 | Date | 28-05-2022 |
2 | 28-May-2022 | DUE DATE EXTENSION -02 | Date | 11-06-2022 |
3 | 11-Jun-2022 | DUE DATE EXTENSION-3 | Date | 18-06-2022 |
4 | 11-Jun-2022 | TECHNICAL CORRIGENDUM-1 | Technical Bid | 18-06-2022 |
Sl. No. | Item Description |
1 | 415V FGD SERVICE PMCC # 0DA`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
2 | 415V FGD SERVICE PMCC # 0DB`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
3 | 415V AC VENT & WS PMCC# 0DC `-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
4 | 415V GYPSUM PMCC# 0DD`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
5 | 415V LHP/GHP PMCC # 0DE`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
6 | 415V BALL MILL MCC # 0DF`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
7 | 220V DCDB # 0FA`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
8 | 220V DCDB # 0FB`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
9 | 415V EMERGENCY MCC # 0MA`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
10 | 415V EMERGENCY MCC # 0MB`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
11 | 415V EMERGENCY MCC # 0MC`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
12 | DC FUSE DB`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
13 | AC FUSE DB`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
14 | Mandatory spares for LT switchgear (ANNEXURE-D)`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
15 | COMMISSIONING SPARES-ANNEXURE-E`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
16 | TOOLS & TACKLES -ANNEXURE-F`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
17 | TRAINING CHARGES FORTRAINING WORKSHOP AT SITE FOR SWITCHGEAR & NUMERICAL RELAY-ANNEXURE-G`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
18 | COMMISSIONING CHARGE FOR NUMERICAL RELAY-ANNEXURE-H`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
19 | CHARGES FOR SUPERVISION OF COMMISSIONING FOR LT SWITCHGEAR-ANNEXURE-I`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
20 | SITE MODIFICATION CHARGES (As per Annexure-J)`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |
21 | SITE MODIFICATION MATERIAL @1 % OF TOTAL EXWORKS FOR SL NO 1 TO 13`-- AS PER TECHNICAL SPECIFICATION NO: SBD-TS-CPBG-FGD-RAM, REV-00(Unit Rate (at Column 13) to be quoted including P&F Charges and Freight Charges upto destination) |