| 1 | Laying Sewer Line |
| 2 | Conveying, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete (excuding cost of pipes):150 mm diameter. |
| 3 | Laying UPVC pipesof class 2 to class 6 andspecials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure(excluding cost of pipes and specials).160 mm nominal outer dia pipes. |
| 4 | \"Conveying, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete (excuding cost of pipes):200 mm diameter. |
| 5 | Supply of glazed Stoneware Pipe (SP1)150mm nominal dia, 0.6m long conforming to IS 651:2007 |
| 6 | Supply of SW Pipe 200mm, 0.6m long. |
| 7 | Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 8 | Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m :All kinds of soil |
| 9 | Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not exceeding 3 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m: 1.50m to 3.0mAll kinds of soil |
| 10 | Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth not exceeding 1.5m |
| 11 | Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not exceeding 3 m |
| 12 | Fencing one side of trenches, 1.50 m height with two rows of 10 cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2 m intervals. |
| 13 | Construction of manholes |
| 14 | Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 15 | Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 16 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. |
| 17 | Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar |
| 18 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 19 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m for 2nd depth of 1.50m to 3.0m in all kinds of soil. |
| 20 | Fencing 1.50m high with two rows ofcasuarina poles (girth 15cm to 24cm) tied with coir yarn on verticalcasuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals. |
| 21 | Close timbering in case of shafts, wells, cesspits, manholes and the like including strutting, shoring and packing cavities (wherever required) etc. complete (Measurements to be taken of the face area timbered).Depth not exceeding 1.5 m |
| 22 | Close timbering in case of shafts, wells, cesspits, manholes and the like including strutting, shoring and packing cavities (wherever required) etc. complete (Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not exceeding 3 m |
| 23 | Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 24 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) |
| 25 | Centering and shuttering including strutting propping etc and removal for Cover slab (circular) |
| 26 | Centering and shuttering including strutting, propping etc and removal of form etc for Well steining - circular work |
| 27 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size |
| 28 | Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size) |
| 29 | Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelHot rolled deformed bars |
| 30 | Making connection of drain or sewer line with existing manhole including breaking into and making goodthe walls, floors with cement concrete 1:2:4 mix( 1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 ( 1 cement: 3 coarse sand) finished with a floating coat of neat cement and making necessary channels for the drain etc. complete. |
| 31 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 32 | Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat cement. |
| 33 | Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS: 10910 on 12 mm dia steeel barconforming to IS:1786, having minimum cross section as 23 mm x 25 mm and over allminimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufactures permanent identification mark to be visible even after fixing including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 ( 1cement: 3 coarse sand: 6 graded stone aggregate 20 mm nominal size)Complete as per design |
| 34 | Conveying from casting yard and fixing the RCC cover slab of size 1.60 M dia,18 cm thick including 5 kg cement/each |
| 35 | Taking out C.I cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually / by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials with 50 metres lead as per direction of Engineer -in- Charge. |
| 36 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. |
| 37 | Removal of excess earth by lorry for minimum mechanical conveyance and less royalty of earth |
| 38 | Maintenance Works |
| 39 | Plugging the full portion of the mouth of 100mm dia sewer main using clay filled gunny bags and removing the same after completion of work etc complete. |
| 40 | Plugging the full portion of the mouth of 150mm to 200mm dia sewer main using clay filled gunny bags and removing the same after completion of work etc complete |
| 41 | Manhole cleaning upto 3m depth- Cleaning the manhole at main line and branches up to a depth of 3m including removing the silt and other floated matters and destroying the debries at convenient places as directed by deptl officers |
| 42 | Bailing out water with5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete.NEW DATA (Prepared based on PHED SDB - Item No.1070 |
| 43 | Engaging Coolie |
| 44 | Supply of sewer man. |
| 45 | General Items |
| 46 | Supplying, conveying and laying 25mm dia PVC best quality pipe (10kg/cm2) including specials for diverting near manholes |
| 47 | Supply of uPVC Pipe, IS 4985:2000 , 6kg/cm2, 110mm Dia. |
| 48 | Laying UPVC pipesof class 2 to class 6 andspecials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure(excluding cost of pipes and specials).110 mm nominal outer dia pipes. |
| 49 | Providing protection works to the Electric post by using 3 no. of Kattadi poles and removing the same after completion of work |
| 50 | Removal of Dumped earth, silt, deposits received from manhole, well etc, conveying by lorry for minimum mechanical conveyance and disposing safely |
| 51 | Removing the CI or RCC manhole cover with frame (Heavy duty), after chipping the existing cement concrete and refixing the Cover after raising the manhole by 10cm with CC 1:2:4 as per specification. |
| 52 | Removing the CI or RCC manhole cover with frame (Heavy duty), after chipping the existing cement concrete and re fixing the Cover after raising the manhole by 15cm to 24cm with CC 1:2:4 as per specification |
| 53 | Removing the CI or RCC manhole cover with frame,chipping the existing bitumen surface, cement concrete and re-fixing the cover after raising the manhole cover by 25cm to 35cm with CC 1:2:4 as per specification. |
| 54 | Supplying and fixing in position 560 mm dia. CI Cover (heavy duty-HD20) with frame the weight to be not less than 208 kg |
| 55 | COST OF PIPE |
| 56 | Supply of uPVC Pipe, IS 4985:2000 , 8kg/cm2, 160mm Dia. |