| 1 | Electrical Items : |
| 2 | Scaffolding Erection for Maintenance of Px and Bz Loading Arms |
| 3 | Greasing Swivel Joints of size 16\" |
| 4 | Greasing Swivel Joints of size 10\" |
| 5 | Greasing Swivel Joints of size 8\" |
| 6 | Greasing of QC/DC Coupler Guide, ERC Clamp cylinder, Mechanical LockPin etc. of Both Loading Arms |
| 7 | 3/8\" Hydraulic Hose with Gland Nut of size M 20 on both Sides |
| 8 | 1/2\" Hydraulic Hose with Gland Nut of size M 24 on both Sides |
| 9 | 5/8\" Hydraulic Hose with Gland Nut of size M 30 on both Sides |
| 10 | Valve Greasing Size 2\" 150# |
| 11 | Valve Greasing Size 3\" 150# |
| 12 | Valve Greasing Size 8\" 150# |
| 13 | Valve Greasing Size 10\" 150# |
| 14 | Valve Greasing Size 12\" 150# |
| 15 | Valve Greasing Size 12\" 300# |
| 16 | NRV Maintenance2\" 150# |
| 17 | Pump Preventive Maintenance such as Greasing, Oil Changing Etc |
| 18 | CBD PUMP Breakdown maintenance assistance,Job includes-Dismantling: decoupling ,dismantling motor &pump from installed location,opening of pump,removal of impeller,impeller sleeve,removal of bearing block,removal of bearing .Installation: installation of beating,sleeve,shaft,impeller and boxup of pump,reinstallation to position,installation of motor,coupling. |
| 19 | Spading and Despading of 12\" 300#Flange |
| 20 | Spading and Despading of 12\" 150#Flange |
| 21 | Spading and Despading of 10\" 150#Flange |
| 22 | Spading and Despading of 8\" 150#Flange |
| 23 | Spading and Despading of 2\" 150#Flange |
| 24 | Spading and Despading of 3\" 150#Flange |
| 25 | Assistance for Line Flushing of Size 12\" of Approx 25 meter length including Hose connection, Water Filling from tanker and Draining |
| 26 | Assistance for Line Flushing of Size 2\" of Approx 40 meter length with multile pipe branches including Hose connection, Water Filling from tanker and Draining. |
| 27 | 2\" Size 150#Valve Dropping & Erection |
| 28 | 8\"150#Valve Dropping & Erection |
| 29 | 10\"150#Valve Dropping & Erection |
| 30 | 12\"150#Valve Dropping & Erection |
| 31 | 12\"300#Valve Dropping & Erection |
| 32 | 12\" 150# MOV Erection after the Modification |
| 33 | Welding of CS Piping Upto 10mm Thk |
| 34 | Erection of CS Piping Upto 10mm Thk |
| 35 | Welding of SS Piping Upto 6.00mm Thk |
| 36 | Erection of SS Piping Upto 6.00mm Thk |
| 37 | Flange Bolt Replacement2\"-150#,300# due to Corrosion (Job includescutting of bolts using gascutting/cutting wheel and replacing with new stud bolts) |
| 38 | Flange Bolt Replacement3\"-150#,300# due to Corrosion(Job includescutting of bolts using gascutting/cutting wheel and replacing with new stud bolts) |
| 39 | Flange Bolt Replacement 10\"-150#,300# due to Corrosion(Job includescutting of bolts using gascutting/cutting wheel and replacing with new stud bolts) |
| 40 | Flange Bolt Replacement 12\"-150#,300# due to Corrosion(Job includescutting of bolts using gascutting/cutting wheel and replacing with new stud bolts) |
| 41 | Fabrication & welding of CS shoe support / corrosion pads |
| 42 | Wrapping coating of UG 2\" CBD Drain Line |
| 43 | Fabrication & erection of MS structures (structural steel supplied by OMPL) |
| 44 | Dismantling of Structures |
| 45 | Dismantling of Piping |
| 46 | HAND TOOL/MANUAL CLEANING TO SSPCSP-2 |
| 47 | PRIMER COAT,ONECOAT OF EPOXY MASTIC,100 MICRON DFT(SELF PRIMING TYPESURFACE TOLERANT HIGH BUILD EPOXY COATING), P-2 OF OMPL PAINT SPEC OMPL/INSP/PAINT/SPEC - REV0 |
| 48 | INTERMEDIATE COAT, ONE COAT OF EPOXY HIGH BUILD FINISH PAINT 100 MICRONS DFT, P-3 OF OMPL PAINT SPEC OMPL/INSP/PAINT/SPEC - REV0 |
| 49 | FINISH COAT OF ONE COAT OF ACYRYLIC POLYURETHANE FINISH PAINT, 40 MICRONS DFT(WHITE/GREY), P-5 OF OMPL PAINT SPEC OMPL/INSP/PAINT/SPEC - REV0 |
| 50 | M 20 X 450 Chemical Anchor Fastenerfixing( Embeded Length is 400mm) |
| 51 | M 16 X 350 Chemical Anchor Fastenerfixing( Embeded Length is 300mm) |