| 1 | Items : |
| 2 | Supply of Automated Water Level Sensor (non-contact Radar type) for River & Reservoirs having 15m range with all necessary hardware and software complete as per technical specifications |
| 3 | Supply of Automated Rainfall Gauge (ARG) Sensor (tipping bucket type) with all necessary hardware complete as per technical specifications. |
| 4 | Supply of data logger with 2 channel input type with GSM & GPRS based telemetry system including antenna and all necessary equipment for data transmission as per technical specifications. |
| 5 | Supply of Solar panel with all connectors, cables, and conduit as per technical specifications |
| 6 | Supplies of Battery, charger regulator with all interconnecting connectors, cables for DCP as per technical specifications |
| 7 | NEMA4X OR Equivalent Enclosure box to suit master unit equipment with locking, other ancillary equipment, fittings earthling, lightening arrestor with all connectors, cables and conduit for cables, mast to mount Solar panel & other equipment, sensor mount complete as per technical specifications |
| 8 | Supply of Air Temperature & Relative Humidity sensor, cable with radiation shield, Equipment set with all necessary hardware as per technical specifications |
| 9 | Supply of Wind speed & wind direction sensor with all necessary hardware as per technical specifications |
| 10 | Supply of Atmospheric Pressure sensor with all necessary hardware as per technical specifications |
| 11 | Supply of Solar Radiation sensor and cable with all necessary hardware as per technical specifications |
| 12 | Supply of Automated pan Evaporimeter Equipment s with all necessary hardware as per technical specifications |
| 13 | Supply of Data Logger with 8 channels input type with GSM & GPRS based telemetry including external digital display, antenna, and all necessary equipment for data transmission as per technical specifications. |
| 14 | Supply of Solar panel with all connectors, cables, and conduit as per technical specifications |
| 15 | Supplies of Battery, charger regulator with all interconnecting connectors, cables for DCP as per technical specifications |
| 16 | Supply of NEMA 4 or Equivalent enclosure box for mounting the Datalogger unit with lockable door, other ancillary equipment, fittings earthling, lightening arrestor with all connectors, cables and conduit for cables, 10-meter tower with guy rope support to mount DCP, sensor mount complete as per technical specifications. |
| 17 | Installation, testing, commissioning of Automated Water Level Sensor (non-contact Radar type) for River & Reservoirs having 15m range with all necessary hardware & software complete as per technical specifications |
| 18 | Installation, testing, commissioning of Automated Rainfall Gauge (ARG) Sensor (tipping bucket type) with all necessary hardware complete as per technical specifications. |
| 19 | Installation, testing, commissioning of data logger with 2 channel input type with GSM & GPRS based telemetry system including antenna and all necessary equipment for data transmission and integration with SDC server complete as per technical specifi cations. |
| 20 | Installation, testing, commissioning of Solar panel with all connectors, cables, and conduit as per technical specifications |
| 21 | Installation, testing, commissioning of Battery, charger regulator with all interconnecting connectors, cables for DCP as per technical specifications |
| 22 | Installation, testing, commissioning of NEMA4X OR Equivalent Enclosure box to suit master unit equipment with locking, other ancillary equipment, fittings earthling, lightening arrestor with all connectors, cables and conduit for cables, mast to mount Solar panel & other equipment, sensor mount complete as per technical specifications |
| 23 | Installation, testing, commissioning of Air Temperature & Relative Humidity sensor, cable with radiation shield, Equipment set with all necessary hardware as per technical specifications |
| 24 | Installation, testing, commissioning of Wind speed & wind direction sensor with all necessary hardware as per technical specifications |
| 25 | Installation, testing, commissioning of Atmospheric Pressure sensor with all necessary hardware as per technical specifications |
| 26 | Installation, testing, commissioning of Solar Radiation sensor and cable with all necessary hardware as per technical specifications |
| 27 | Installation, testing, commissioning of Automated pan Evaporimeter Equipment s with all necessary hardware as per technical specifications |
| 28 | Installation, testing, commissioning of Data Logger with 8 channels input type with GSM & GPRS based telemetry including external digital display, antenna, and all necessary equipment for data transmission and integration with SDC server complete as per technical specifications. |
| 29 | Installation, testing, commissioning of Solar panel with all connectors, cables, and conduit as per technical specifications |
| 30 | Installation, testing, commissioning of Battery, charger regulator with all interconnecting connectors, cables for DCP as per technical specifications |
| 31 | Installation, testing, commissioning of NEMA 4 or Equivalent enclosure box for mounting the data logger unit with locking system, other ancillary equipment, fittings earthling, lightening arrestor with all connectors, cables and conduit for cables, 10-meter tower with guy rope support to mount DCP, sensor mount complete as per technical specifications. |
| 32 | Installation of Chain-Link fencing of (5m * 5m) * 2m along with lockable gates for external protection pf sensors and DCP at RTDAS asper technical specifications. |
| 33 | Integration of all DCPs GSM & GPRS data with the existing Sever installed at state Data Center, Jaipur Rajasthan along with all ancillary equipment, as per technical specifications. |
| 34 | Operation & Maintenance during Five Years Comprehensive Warranty period, for entire RTDAS with Telemetry system as specified in Schedule of Requirement along with accessories, installed at designated locations and Data Center equipment under this contractafter final acceptance of RTDAS systems. This includes replacement of material/ goods & consumables as & when required at bidders’ cost. The cost of Communication for, GSM & GPRS telemetry for data transmission shall be borne by bidder. |
| 35 | Training of the purchaser\"s personnel at the supplier’s plant and/or/onsite in assembly, startup, operation, maintenance and/or repair manual of the supplied goods. Course topics will include sensor calibration, data logger configuration, data downloading, data retrieval, collection, Trouble shooting, processing maintenance requirements and procedure for equipment configuration, installation, site testing and commissioning including training kit containing course material in soft and hard copies as per technical specification. |