Nabard 2021-22 Panagudi Town Panchayat Earthen Road To Bt Road From Thandayarkulam Burial Ground Road In Panagudi Town Panchayat.
Tender Value
1.07 Crore
Estimated cost
Bid Submission
24 Mar 2022
0 days left
EMD
1.07 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
panagudi → Tamil Nadu
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Nabard 2021-22 Panagudi Town Panchayat Earthen Road To Bt Road From Thandayarkulam Burial Ground Road In Panagudi Town Panchayat.
BOQ
| Sl. No. | Item Description |
| 1 | Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401. |
| 2 | Providing and Laying, Spreading and Compacting graded stone aggregates to WET MIX MECADAM Specification in 250mm thickspecification including premixing the materials with water at OMC in mechanical mix plantCarriage of mixed materials by tipper to work site laying in uniform layers with pavers in sub base/base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of materials,labour charges,rentals for machinery,fuel and all other incidental charges etc complete as per clause406 of MORTH Specification |
| 3 | Providing and layingPriming coat over WBM/WMM surface using 7Kg ofEmulsion Bitumen (SS1) for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 502 ofMORTH Rev-5. |
| 4 | Providing and layingTack coat over WBM/WMM surface (Preaped with primer) using 2.50Kg ofBitu Emulsion (RS1)for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 503 ofMORTH Rev-5. |
| 5 | Providing and laying 50 mm conslidated thick Dense Bituminuous macadam using 0.24 cum of 26.50-13.20 mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm and below and with 53.20kg of vg 30 bitumen premixing 10 sqm including cost and conveyance of all materials to CMP site,heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 tons capacity,conveying the mix by tipper trucks to work site,spreading the mixuniform thickness of 50mm with paver to the specified grade and cross sections and compaction byvibratory/ pneumapic roller to the required density etc., including labour for accending to pavor at sites etc., including hire charges and fuel chargesfor 20-30 CMP with bitumen tipper trucks, paver finisher/9 m paver finisher,vibratory/ pneumapic rollers and all other tools and plant required including to all other incidental charges etc., complete as per specification using CMP as clause 505MORTH Rev-5. |
| 6 | Providing and layingBituminous concrete to 40mm thick using 0.13 cum of 19.00-9.50 mm, 0.13cum of 9.50-2.36 mm and 0.26cum of 2.36mm and blow with 45.27kgs of VG 30 /VG 40 bitumen and5.0.3kg of shreded plastit wast for premixing for 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20–30 tonnes capacity, conveying the mix by tipper trucks to paver site spreading the mix to uniform thickness of 40 mm with mechanical Paver to the specified grades and cross sections and consolidated by 80 - 10 tonne vibratory/ pneumatic roller to the required density etc., including labor for attending to paver site etc., including hire charges and fuel charges for 20 – 30tCMP with bitumen boiler, tipper trucks, paver finisher,/ 9m paver finisher, vibratory/ pneumatic rollers and all other tools and plant required including fule and all other incidental charges etc., complete as per specification using CMP as for clause 507of MORTH Rev-5. |
| 7 | Collection and Spreading of Red gravel including cost and conveyance of all materials from approved quarries as noted in lead chart to the road side including loading, unloading and stacking the well gravel at road side to departmental gauge for pre-measurement including labour charges for laying spreading leveling to camper etc., complete as per as per MORTH Specifications.401 and 1015 |
| 8 | Road Marking with ht applied thermoplastic compound with reflectorising glassbeads @ 250gms per sqm area, thickness of 2.5mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and fee from streaks and holes etc complete as per MORTH specifications |
| 9 | Providing and fixing of Retro Refectories Cautionary, Mandatory Signs made out of wide Angle Cube Corner Micro Prismatic grade conforming to IRC - 67:2010 & Type XI standard of ASTM D 4956 - 09 specification with 7 years warranty for Reflective Sheeting as per Clause 6.9 of IRC 67: 2010 and fixed over 2mm thick aluminium sheet fixed on back supporting on Vertical Post of 65 NB GI pipe, Medium Thick firmly fixed to the ground by means of property designed foundation with M15 grade cement concrete 45cm x 45cm x 60cm as per standard drawing 90cm equilateral triangle.a)upto 0.90 Sq.Mtr. |
| 10 | Towards charges for routine mainatanace of the road work executed under NABARD SCHEME including dressing of berms by refilling the gully with the earth from borrow pits ,cleaning of wild seasonal growth on berms,desiltling of side drains and CD Works white washing gaurd stones painting of KM,HM Stones ,parapets ,cutting branches of trees ,refixing displaced gaurd stones ,caution boards ,speed limit boards etc with the Periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers execept for the constructional defects which has to be rectifieed by the contractor at his own cost. |
| 11 | Upkeeping 1st year (50%) |
| 12 | Upkeeping 2nd year (60%) |
| 13 | Upkeeping 3rd year (60%) |
| 14 | Upkeeping 4th year (60%) |
| 15 | Upkeeping 5th year (60%) |
| 16 | Earth work open excavation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc., as per SS 20 A for making up berms as per clause 111,112,201,202,301,305,900of MORTH Vth revision (Twice in a year ). |
| 17 | Upkeeping 1st year (40%) |
| 18 | Upkeeping 2nd year (40%) |
| 19 | Upkeeping 3rd year (40%) |
| 20 | Upkeeping 4th year (40%) |
| 21 | Upkeeping 5th year (40%) |
| 22 | Providing and layingtack coat of 2 kgs/10 sqmbituminous Emulsion (RS -I Type )for 10 square meter areaion the preapared bituminious granular surface cleaned with mechanical broom as per clause 503. |
| 23 | 4th year 3% |
| 24 | 5th year 5% |
| 25 | Providing and laying Bituminous Concrete 40mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading themix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M,Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5 |
| 26 | 4th year 3% |
| 27 | 5th year 5% |
AI Tender Summary
Tender Timeline
Mar 16, 2022
11:30 IST
Tender Published
Tender notice published.
CompletedMar 24, 2022
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedMar 24, 2022
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents