Bridge And Roof Company I Limited has published Piping Works And Erection Of Equipments For 414Kt Smelter Project At Balco Utility Piping Works And Erection Of Equipments Including Erection Of Overhead Eot/Ptm/Fta, Bake Oven Fta, Erection Of Equipment And Prefabricated Steel Tanks / Structural / Ducts . Submission Date for this Tender is 05-05-2022. Tanks and Cylinders Tenders in korba Chhattisgarh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 21-Mar-2022 | Corrigendum - I | Date | 28-03-2022 |
2 | 28-Mar-2022 | Corrigendum - II | Date | 07-04-2022 |
3 | 07-Apr-2022 | Corrigendum - III | Date | 20-04-2022 |
4 | 21-Apr-2022 | Corrigendum - IV | Date | 28-04-2022 |
5 | 29-Apr-2022 | Corrigendum - V date | Date | 05-05-2022 |
6 | 02-May-2022 | Corrigendum - VI | Technical Bid | 05-05-2022 |
Sl. No. | Item Description |
1 | MECHANICAL ERECTION |
2 | Pot Tending Machine (PTM) with Rails : Erection of PTM with Rails |
3 | Unloading, loading, Transportation and installation of PTM 14 Sets, each weighing 120 MT,Total Wt = 1680 MT ( Material: Equipment) |
4 | Unloading, loading, Transportation, installation and welding of Rails-QU120, Total WT 688 MT (Material: Steel) |
5 | Unloading, loading, Transportation and installation of Transfer Gantry: 1 Set with weight 20 MT (Material: Equipment) |
6 | Unloading, loading, Transportation, installation and welding of Rail lifting beam: 8 Sets, each 4 MT,Total wt 32 MT (Material: Equipment) |
7 | Pot Overhaul shop - Erection Of Bridge Crane and Cathode Sealing / Lining Eqpts |
8 | Unloading, loading, Transportation and installation of 5t Bridge Crane(Lk=30.5m, A6), 2 Sets, each weighing 5 MT, total wt 10 MT (Material: Equipment) |
9 | Unloading, loading, Transportation and installation of 40t Bridge Crane (Lk=30.5m, A6), 2 sets, each weighing 23 MT, Total wt 46 MT (Material: Equipment) |
10 | Unloading, loading, Transportation and installation of Cathode sealing/lining equipment 01 No, Wt 70 MT (Material: Equipment) |
11 | Pot Auxiliaries: Loading, transportation, unloading, assembly, installation/fixing in position as per drawing, tender specification. |
12 | Tapping ladle 25 Nos, each weighing 12 MT, Total 300 MT (Material: Equipment) |
13 | Anode pallet: 384 Nos, each wt 2.02 MT, Total 775.68 MT (Material: Equipment) |
14 | Fully Automatic Anode Lifting Frame 04 Nos, each 25 MT, Total 100 MT (Material: Equipment) |
15 | High amperage pot stop switch 1 No, 1.00 MT (Material: Equipment) |
16 | Online welding device: 1 No, 5.00 MT (Material: Equipment) |
17 | Fuel gas baking device: 12 Nos, each weighing 10 MT, Total 120.000 MT (Material: Equipment) |
18 | Temporary short-circuit busbar between pots (Material: Equipment) |
19 | Video Monitoring System (Material: Equipment) |
20 | Oil-immersed Power Transformer (Material: Equipment) |
21 | Al ladle transfer vehicle (Material: Equipment) |
22 | Ladle tipping vehicle (Material: Equipment) |
23 | Anode trailer Q=12, qty 6 Nos (Material: Equipment) |
24 | Bath tanker (Material: Equipment) |
25 | Fluorides feeding vehicle (Material: Equipment) |
26 | Ladle cleaning Shop |
27 | Unloading, loading, Transportation and installation of 25/5t Bridge crane/double-hook bridge crane.(LK-28.5m, A5), 01 set, Wt 45.8 MT (Material: Equipment) |
28 | Unloading, loading, Transportation and installation of Ladle cleaning machine and other equipments: 1 No, Wt 119 MT (Material: Equipment) |
29 | Dismantling and shifting of Existing Ladle cleaning machine: 1 No, 89.30 MT (Material: Equipment) |
30 | Cast House |
31 | Unloading, loading, Transportation and installation of PFA 90Kt 2 Eqpt, Each 40 MT, Total 80 MT (Material: Equipment) |
32 | Unloading, loading, Transportation and installation of ICM-100Kt (existing revamping), 2 Eqpt, Each 25 MT, Total wt 50 MT (Material: Equipment) |
33 | Unloading, loading, Transportation and installation of Wire Rod-100Kt, 1 Equipment, Wt 70 MT (Material: Equipment) |
34 | Unloading, loading, Transportation and installation of Cast House-Miscellaneous/Furnaces/utilities: 7 Equipments, Each wt 40 MT, Total wt 280 MT (Material: Equipment) |
35 | Carbon |
36 | Unloading, loading, Transportation and installation of Rodding- 60 RPH, 1 Equipment, Wt 600 MT (Material: Equipment) |
37 | Bake oven |
38 | Unloading, loading, Transportation and installation of Firing control system- 2 sets, 65 MT Each, Total wt 130 MT (Material: Equipment) |
39 | Unloading, loading, Transportation and installation of FTA (Material: Equipment) |
40 | Unloading, loading, Transportation and installation of Anode Baking furnace equipments (Material: Equipment) |
41 | Unloading, loading, Transportation and installation of Anode transport system and other equipment (Material: Equipment) |
42 | Unloading, loading, Transportation, installation and welding of Bakeoven -FTP (erection of equipments and Prefabricated steel, tanks/structural) (Material: Equipment) |
43 | Unloading, loading, Transportation, installation and welding of Bakeoven -FTP (fabrication and erection of steel, tanks/structural/ducts) (Material: Steel) |
44 | Unloading, loading, Transportation and installation of Stacking crane (Material: Equipment) |
45 | Total Auxiliary Prod systems |
46 | Unloading, loading, Transportation and installation of Air compressor station (HP&LP compressors) (Material: Equipment) |
47 | Unloading, loading, Transportation and installation of Plant Compressor Air Cooling Pumping Station. (Material: Equipment) |
48 | Unloading, loading, Transportation and installation of Fire Control Pumping Station (Material: Equipment) |
49 | Rectifier cooling water circulation system (Material: Equipment) |
50 | Unloading, loading, Transportation and installation of Fuoride storage (equipment and steel silo/structures) (Material: Equipment) |
51 | Unloading, loading, Transportation and installation of Aluminium reduction plant / carbon plant laboratory. (Material: Equipment) |
52 | Unloading, loading, Transportation and installation of new sewage treatment plant. (Material: Equipment) |
53 | Unloading, loading, Transportation and installation of EOT cranes-15. (Material: Equipment) |
54 | Unloading, loading, Transportation and installation of Erection cranes_EOT cranes. (Material: Equipment) |
55 | UTILITIES- Piping |
56 | Unloading, loading, Transportation, installation, welding, eretion, installation of support, testing and comissioning of Fire line Pipe- 250mm-150mm (schedule 40, MS), Inch Mtr 144000 (Material: Piping) |
57 | Unloading, loading, Transportation, installation, welding, eretion, installation of support, testing and comissioning of Water Line 450mm-150mm(schedule 40, MS), Inch Mtr 100000 (Material: Piping) |
58 | Unloading, loading, Transportation, installation, welding, eretion, installation of support, testing and comissioning of Airline 700-200mm(Schedule 80, Seamless,MS)) Inch Mtr 120000 (Material: Piping) |
59 | TOTAL AMOUNT OF THE WORK AGAINST SL NOSABOVE INCLUDES ALL TAXES DUTIES, ROYALTIES, CESS ENVIRONMENTAL AND POLLUTION FITNESS AND SAFETY CLEARANCE CHARGES ( IF ANY ) OR OTHER INCIDENTAL CHARGES ETC. BUT EXCLUDING GST. |