Execution Of Misc. Civil And Allied Works At Atchutapuram, A.P. Execution Of Misc. Civil And Allied Works Such As Pcc, Rcc, Formwork, Reinforcement, Brickwork, Plastering, Paver Block And Concrete Road Works For Different Civil Structures With Their Own
Tender Overview
Project Description
Execution Of Misc. Civil And Allied Works At Atchutapuram, A.P. Execution Of Misc. Civil And Allied Works Such As Pcc, Rcc, Formwork, Reinforcement, Brickwork, Plastering, Paver Block And Concrete Road Works For Different Civil Structures With Their Own Materials, Machinery And Manpower At Atchutapuram, A.P.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 04-Mar-2022 | Drawing | Other | 14-Mar-2022 |
| 2 | 15-Mar-2022 | Corrigendum - II | Date | 21-Mar-2022 |
| 3 | 22-Mar-2022 | Corrigendum - III | Date | 25-Mar-2022 |
BOQ
| Sl. No. | Item Description |
| 1 | MISC CIVIL WORKS IOCL VISHAKHAPATNAM |
| 2 | Clearing grass and removal of the rubbish within the project site & disposal of the same outside site premises and at unobjectionable place.Note: a. Dismantling & disposing of existingRCC poles/pillars etc up to ground level is inlcuded in the rate.b. Dismantled items shall be the property of Contractor. Rates to be quoted accordingly. |
| 3 | Uprooting and Transplantion oftrees (within the plot) by pruning it suitably as directed including the excavation of trench around the root ball of the tree, backfilling the pit after uprooting the tree with available earth, cleaning of the site where the trees are to be transplanted, excavation of receiving pit, filling it with good quality soil & Farm Yard Manure alongwith saturating it with water. The uprooting of the roots of trees (without damaging them), wrapping of the whole trunk of tree with hessian cloth to avoid damage to the bark while lifting /transplanting & shifting of the trees to the site of transplantation (plot boundry). (Cost includes cutting, transportation, shifting, labour and necessary equipments, safety net / rope etc.)The item also includes:- Taking videograph & photographs of the specified trees before & after transplantation showing its number and other details including the entire operation such as removal of tree, root treatment, lifting by crane,transplantation at specified locations, excavation of pits, filling with soil, manure, watering.The videography of each tree to be recorded & submitted through CDs.- Providing proper support after transplantation and taking care of the transplanted trees with watering ( water to be supplied by vendor) etc for their proper growth and submitting report to the Tree officer about the condition of trees after Six months of transplantation as per guidelines.- Supply of good quality soil and farm yard manure including watering (water to be supplied by vendor) free from grass roots, weeds, stones, pebbles etc, at the site as per direction of Tree Officials.- Pruning of the tree branches, disposing and clearing of site etc. all as required. The entire work is to be carried out in coordination/approval with Architect / concerned Tree Officials/APPCB statuatory Authority. -The scope of the work also include drip irrigation with green grass development of 1 m width on both sides of the planted tree. |
| 4 | Drip irrigation with green grass development of 1 m width on both sides of the planted tree for already transplanted trees. The item also includes: - Providing proper support after transplantation and taking care of the transplanted trees with watering ( water to be supplied by vendor) etc for their proper growth and submitting report to the Tree officer about the condition of trees after Six months of transplantation as per guidelines.- Supply of good quality soil and farm yard manure including watering (water to be supplied by vendor) free from grass roots, weeds, stones, pebbles etc, at the site as per direction of Tree Officials.- Pruning of the tree branches, disposing and clearing of site etc. all as required. The entire work is to be carried out in coordination/approval with Architect / concerned Tree Officials/APPCB statuatory Authority.The scope of work includes all post-transplantation care of trees as described above. |
| 5 | Grassing with selection No.1 grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn, free from weeds and fit for mowing including supplying good earth if needed (the good earth shall be paid for separately). |
| 6 | With grass turf |
| 7 | Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.for WATER and AIR, External work - B class 80 mm dia. nominal bore |
| 8 | Making connection ofG.I.Distribution branchwithG.I.mainof followingsizes by providing & fixing C class tee, including cutting and threading the pipe etc. complete : 25 to 40 mm nominal bore |
| 9 | Making connection ofG.I.Distribution branchwithG.I.mainof followingsizes by providing & fixing C class tee, including cutting and threading the pipe etc. complete : 50 to 80 mm nominal bore |
| 10 | Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) : 25 mm nominal bore |
| 11 | Preparation of beds for hedging and shrubbery by excavating 60cm deep and trenching the excavated base to a further depth of 30cm, refillingtheexcavated earth after breaking clods and mixing with sludge or manure in the ratio of 8:1 (8 parts of stacked volume of earth after reduction by 20% : one part of stacked volume of sludge or manure after reduction by 8%), flooding with water, filling with earth if necessary, watering and finally fine dressing, levelling etc. including stacking and disposal of materials declared unserviceable and surplus earth by spreading and levelling as directed, within a lead of 50m lift up to 1.5 m complete (cost of sludge, manure or extra earth to be paid for separately). |
| 12 | Supplying and stacking at site dump manure from approved source, including carriage up to 1 km (manure measured in stacks will be reduced by 8% for payment) : Screened through sieve of I.S. designation 16mm |
| 13 | Earthwork: Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains or land development including dressing of sides & ramming of bottoms, lift, including removal of the excavated soil, providing shoring, strutting, dewatering as required & disposalofsurplusexcavatedsoilas directed within or outside the site at an unobjectionable place.Note: a. Payment shall be restricted to PCC lines only for building works.b. Tenderers to note that initial & final level survey shall be undertaken jointly by the Contractor &/or representatives with IOC Site Engineer for calculation of earth volume using Simpson\"s Rule in case of land development/ cutting works.c. Tenderers to note that the scope of works inlcude provision of permanent & temporary bench marks (RCC pedestal of size 300 mm x 300 mm approx with necessary base plate) for land development/ cutting works as per the instructions of the Site-in-charge. |
| 14 | In any kind of Soil up to 1.5 m depth |
| 15 | In any kind of Soil above 1.5 m depth & up to 3.0 m depth |
| 16 | Excavating trenches of required width for pipes, cables, etc including excavation for sockets & dressing of sides, ramming of bottoms,depth upto 1.5m including getting out excavated soil & then returning the soil as required, in layers not exceeding 20 cm in depth including consolidating each deposited layer by ramming, watering, etc. and disposing surplus excavated soil as directed, within or outside site at unobjectionable place IN ALL KIND OF SOILS |
| 17 | for Pipes, cables etc. Up to 300 mm dia in depths up to 1.5 m |
| 18 | Filling available excavated earth (excluding rock) in Roads, Driveways,plinth, sides of foundations etc as per EIC in layers not exceeding 20 cm in depth, consolidation each deposited layer by ramming (mechanical means) with roller of 8T capacity and watering , within premises and including all leads, lifts. Note: Compaction under plinth should be done with plate or other vibrator as per direction of EIC. |
| 19 | Supply & filling imported earth of approved quality, inplot, trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth each deposited layer by ramming and watering. Item includes compaction using Vibratory Roller of 8 to 10 ton capacity for earth work in under optimum moisture conditions to give at least 95% of the maximum dry density (Proctor Density).Note:a. Tenderer to note that initial & final level survey shall be undertaken jointly by the Contractor &/or representatives with IOC Site Engineer.b. Tenderers to note that the scope of works inlcude provision of permanent & temporary bench marks (RCC pedestal of size 300 mm x 300 mm approx with necessary base plate) as per the instructions of the Site Incharge.c. Tenderers to note that approval from IOC shall be obtained for the imported earth & quarry used for mass filling & necessary test reports from a Govt Engg Colleges/Universities have to be submiited for the parameters specified by IOC prior to undertaking filling in the site.d. Item rate is inclusive of applicable Royalty for the imported earth/ Specific approval to be obtained from concerned Statutory Authorities. Necessary Royalty receipts/ NOC to be submitted by the Contractor.f. Net quantity of compacted earth shall be paid & no compensation whatsoever on account of subsidence of soil etc shall be permitted. |
| 20 | Supplyingand Local sand filling within the grading zone V or as approved by site incharge of fine aggregates specifiedinattached specifications, in plinth, under floors, pipeline corridors, landscaping, drain beds etc. in layers not exceeding 20cm in depth, each deposited layer to be compacted by ramming watering and dressing complete. |
| 21 | Centeringand shutteringincludingstrutting,proppingetc. and removal of form work for PCC/RCC in foundations, footings, bases of column (with Props or Tubular/ MS Structure or Metallic sheets or 12 mm thk waterproof ply as applicable, directions of the Site Engineer & per enclosed specifications) |
| 22 | for PCC/RCC in foundations, footings ( R/ wall/ Culvert etc), bases of column etc |
| 23 | Suspendedfloors,roofs,landings,balconies, access platform and Shelves (Cast in situ) |
| 24 | Lintels,pedestal, beams plinth beams,girders bressumers and cantilevers for RCC |
| 25 | Columns, Pillars, Piers, Abutments ( Retaining Wall/ Culvert Wall),Posts and Struts for RCC. |
| 26 | Plain & Reinforced Concrete Works (PCC/RCC): Providing and laying in position, machine batched, machine mixed design mix of specific grade of cement concrete for plain /reinforced cement concrete work, using cement as per approved design mix, including pumping of concrete to site of laying (if required) but excluding the cost of centering, shuttering, finishing and reinforcement. Item includes Admixtures in recommended proportions as per IS 9103 to accelerate/retard setting of concrete,improve workabilitywithout impairing strength and durability as per direction of Site Engineer. (Minimum Cement content shall be as specified for individual grade of Concrete. Less cement used as per design mix (if any) will be recoverable separately. No extra payment against extra cement if used shall be payable. Note:a. For production of Concrete , Batching Plant will be supplied by B&R. B&R will provide Transit Mixer, Concrete Pump & Hydra for transportation fresh concrete to pouring point. All Manpower for running Mechineries (except Batching Plant) and its Maintanance in Contractor\"s scope. Fuel for running mechineries will be in Contracor\"s scope.b. Contractor shall be permitted to convert design mix of concrete to be arrived at based on laboratory testing into suitable volumetric mix in to order to achieve required design strength.c. All materials like Aggregate, cement, admixure, Water etc. and its testing as per Engineer-in-charge will be in Contracor\"s scope.Handling of material in Batching Plant in Contractor\"s scope. |
| 27 | d. Hacking of exposed surface of green concrete (wherever applicable) as Key to plaster shall be done at no extra cost to IOC. Item rate is inclusive of necessary surface finishes like broom/ rough finish as per the scope of works & directions of Site- Incharge.e. Curing of concrete inlcuding supplying & providing water & Compaction shall be part of the rates.f. Item to be operated for all types of floors, footings, beams, columns, copings, pipe/ drain culverts, Cable tunnel or other concrete structures as required at site at all levels. Payment shall be made as per drawing dimensions.g. Item rate is inclusive of Submitting Design Mix reports & test reports from Govt Engg Colleges/Universities as per the directions of the Site Engineer. |
| 28 | 1 CEMENT:4 COARSE SAND:8 AGG. 40MM grade plain cement concrete (Min cement content considered @ 220 kg/cum) - At all levels |
| 29 | 1 CEMENT:3 COARSE SAND:6 AGG. 20MM grade plain cement concrete (Min cement content considered @ 240 kg/cum) - At all levels |
| 30 | M-25 grade Reinforced cement concrete (Min cement content considered @ 330 kg/cum) - Above Plinth & Up to Floor Level 5 |
| 31 | M-30 design mix cement concrete(Min cement content considered @ 340 kg/cum)grade for all uses |
| 32 | Providing grouting underbase plates with cement mortar 1:1 (1 cement : 1 coarse sand) including anti shrinkage compound with necessary finishing etc all complete as per directions of engineer-in-charge. |
| 33 | Providing weep holes using PVC pipe of 75 mm dia (6 kg/sqcm) at regular intervals, inlcuding providing pebbles & sand packing/mesh for draining seepage water & as per directions at site. |
| 34 | Supply of Reinforcement for RCC including straightening, cutting, bending, placing in position & binding all complete at all levels using Thermo Mechanically Treated (TMT) Bars Fe 500 grade,Conforming to IS1786.Note: a. Rateincludes the cost of binding wire, laps, chairs & spacer barswhich shall not be measured for the purpose of payment.b. Reinforcement shall range from6 mm dia to 32 mm dia as per drawings.c. Rate also inlcudes providing necessary cover blocks in CM 1:2 as per required thickness & as per drawings. |
| 35 | BRICKWORK |
| 36 | Brick work with F.P.S. (non modular) clay fly ash bricks class designation 7.5 conforming to IS: 12894in Cement mortar 1:4 (1 cement : 4 coarse sand) in superstructureABOVE PLINTH ANDUP TO FLOOR V LEVEL |
| 37 | Half brick masonry (115 mm thick) with F.P.S. (non modular) clay fly ash bricks class designation 5.0 in Cement mortar 1:4 ( 1 cement : 4 coarse sand) IN superstructureABOVEPLINTH & UP TO FLOOR V LEVEL inlcuding providing and placing in position 2 Nos. 6mm dia. M.S. bars, includingproviding 75mm thk. horizontal band in CC mix 1:2:4 atevery third course of half brick masonry. |
| 38 | STONE PITCHING:stone pitching 225 mm thick including supply of stones and with raised & cut pointing with cement mortar 1:3 and preparing surface complete. |
| 39 | Plastering & FinishingNote: a. Rate is inclusive of curing of plaster including supplying & providing water, scaffolding as required & associated labour.Providing and laying cement plaster on surfaces with Coarse/ Fine sand (as applicable) including curing, scaffolding etc. |
| 40 | In 20 mm thick cement plaster of mix 1:4 (1 cement: 4 coarse sand) with sponge/ rough texture finish |
| 41 | In 6 mm thick cement plaster of mix 1:3 (1 cement: 3 coarse sand) with providing Neat cement punning for drains & other places as per the instructions of Site Engineer |
| 42 | In 12 mm thick Cement plaster of mix1:4 (1 cement: 4 coarse sand) |
| 43 | In 6 mm thick plaster of mix 1:3 (1 cement: 3 fine sand) |
| 44 | Structural steel work in all sections fixed with or without connecting plate includingbolts, cutting, hoisting, fixing in position and including Surface preparationof the structuresas per SA 2.5 & painting the same with 2 coats of P3 primer, and 2 coats of F6 finish paint of approved colour and shade as per enclosed specifications & as per site direction. |
| 45 | Structural steel work inbuilt up sections/ framed workin gratings, frames,guard bar,ladder,railing,gates and similar works includingcutting,hoisting,fixing inposition & applying a priming coat of approved steel primer wtc. As required. |
| 46 | Providing and fixing concertina coil fencing with punched tape concertina coil 600mm dia 10metre openable length(total length 90m) having 50 nos. rounds per 6 metre length, upto 3 m height of wall with angle iron \"X\" shaped placed3.00 m apart and with 6 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal including necessary bolts or G.I. barbed wire tied to angle iron all complete as per direction of Site In-Charge with reinforced barbed tape (RBT)/ Spring core(2.5mm thick)wire of high tensile strength of 165 kg/sq.mm with tape (0.52 mm thick) and weight 43.478gm/metre. (cost of M.S. angle, C.C.blocks shall be paid separately) |
| 47 | Preparation and consolidation of sub grade with Vibratory road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm. depth dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth within premises. |
| 48 | Providing & laying 100mm thick factory made Pre-cast cement concrete interlocking paver block of M 40 grade made by block making machine with strong vibratory compaction & of approved size and design/ shape /shade and as per IOCL\"s specifications. The paver block will have peripheral chamfer,with average crushing strength more than 40 N/Sq.mm as/ BS6717 Part -1(1986), maximum water absorption of 2% after 10 minutes and 5% after 24 hrs. as per BS 1881, maximum dimensional deviations of +/- 2mm on length & width and +/- 3mm on on thickness. The job includes supplying & laying a layer of 50mm thick clean course sand on thoroughly compacted sub-base below the paver blocks, cutting the paver blocks wherever required with hydraulic splitter, filling in the joints at the edges of paver blocks with sand,compacting with machine vibrator to required line and level, etc. complete.(Payment for provision of edge restraints shall be made separately);- Grey or Coloured 100mm thick paver blocks. |
| 49 | Providing & laying 80mm thick factory made Lacquered finish Grey/ Coloured Pre-cast cement concrete, interlocking paver block of M 40 grade made by block making machine with strong vibratory compaction & of approved size and design/ shape ,shade and manufacturers and as per IOCL\"s specifications. The paver blocks shall have peripheral chamfer, with average crushing strength than 40 N/Sq.mm as per IS15658 maximum water absorption of 2% after 10 minutes and 5% after 24 hrs. as per BS 1881, maximum dimensional deviations of +/- 2mm on length & width and +/- 3mm onthickness. The job includes supplying & laying a layer of 50mm thick clean course sand onthoroughly compacted sub-base below the paver blocks, cutting the paver blocks wherever required with hydraulic splitter, fillingin the joints at the edges of paver blocks with sand,compacting with machine vibrator to required line and level, etc. complete .(Payment for provision of edge restraints shall be made separately) |
| 50 | Providing and laying design mix cement concrete of M-30 grade, in roads/ taxi tracks/ runways, using cement content as per design mix, using coarse sand and graded stone aggregate of up to 40 mm nominal size in appropriate proportions as per approved & specified design criteria, providing dowel bars with sleeve/ tie bars wherever required, aying at site, spreading and compacting mechanically by using needle and surface vibrators, levelling to required slope/ camber,Vacumm dewatering, finishing with required texture, including steel form work with sturdy M.S. channel sections, curing, making provision for contraction/ expansion, construction & longitudinal joints ( 10 mm wide x 50 mm deep) by groove cutting machine, providing and filling joints with approved joint filler and sealants, painting for consruction joint etc complete as per direction of Engineer-in-charge (Item of joint fillers & sealants for expansion joint, dowel bars with sleeve/ tie bars to be paid separately). Item also includes provision of hardners.Note:- Cement content considered in M-30 is @ 340 kg/cum. Less cement used asper design mix is recoverable separately. No extra payment for excess cement if used shall be payable. Note:a. For production of Concrete , Batching Plant will be supplied by B&R. B&R will provide Transit Mixer, Concrete Pump & Hydra for transportation fresh concrete to pouring point. All Manpower for running Mechineries (except Batching Plant) and its Maintanance in Contracor\"s scope. Fuel is alsofor running mechineries will be in Contracor\"s scope.b. Contractor shall be permitted to convert design mix of concrete to be arrived at based on laboratory testing into suitable volumetric mix in to order to achieve required design strength.c. All materials like Aggregate, cement, admixure, Water etc. and its testing as per Engineer-in-charge will be in Contracor\"s scope.Handling of material in Batching Plant in Contractor\"s scope. d. Hacking of exposed surface of green concrete (wherever applicable) as Key to plaster shall be done at no extra cost to IOC. Item rate is inclusive of necessary surface finishes like broom/ rough finish as per the scope of works & directions of Site- Incharge.e. Curing of concrete inlcuding supplying & providing water & Compaction shall be part of the rates.f. Payment shall be made as per drawing dimensions.g. Item rate is inclusive of Submitting Design Mix reports & test reports from Govt Engg Colleges/Universities as per the directions of the Site Engineer. |
| 51 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to .075 mm) (in layers of not more than 150 mm ) wet mix macadam (WMM) specifications including premixing the material with water at OMC in mechanical mix plant, carriage of mixed material by tipper to site, for all leads and lifts, laying in uniform layers with mechanical paver finisher in sub-base/base course on well prepared surface and compacting with vibratory roller of 8 to 10 ton capacity to achieve the desired density, complete as per specifications of Engineer-in- charge. |
| 52 | Providing and making expansion joint 25 mm wide including supplying & providing 25 mm thick bitumen impregnated fiber board (Shalitex of M/s.Shalimar or approved equivalent). The top 15mm of the joint shall be cleaned and filled with putty sealing compound (M/s.Fosroc - NITOFLOR FC 140 / Pidilite or equivalent) including cleaning, providing 32 mm dia Dowel bar with 40 mm Dia, 150 long G.I. pipe (Heavy Duty) with cap & filled with cotton waste etc complete as per drawings and as per directions of the site engineer. Note: a. The joint & the fiber board shall be for the entire depth of the concrete slab |
| 53 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement in position to the required line, level and curvature jointed with cement mortar 1:3 (1 cement:3 coarse sand) including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm) including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment) (Precast C.C. kerb stone shall be approved by Engineer-in-charge. |
| 54 | Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 12.00 |
| 55 | Demolishing C.C. /R.C.C.work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a leadof 1000m,stackingserviceableandunserviceable material separately includingcutting reinforcement bars. |
| 56 | \"NOTE:-THE ABOVE RATE SHALL BE INCLUSIVE OF ALL TAXES & DUTIES, ROYALTIES, CESS, ENVIORMENTAL & POLLUTION, FITNESS & SAFETY CLEARANCE CHARGES (IF ANY), OR ANY OTHER INCIDENTAL CHARGES ETC BUT EXCLUDING GST.\" |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-3 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender