Chennai Petroleum Corporation Limited-CPCL has published Epcm Services For Group-Ii Lobs Project At Manali Refinery Of Cpcl Epcm Services For Group-Ii Lobs Project At Manali Refinery Of Cpcl , Total Lumpsum Charges For Consultancy Services For Phase-I And Phase-Ii , Phase-I :Lump-Sum Charges For Consultancy S. Submission Date for this Tender is 16-05-2022. Consultancy Service Tenders in manali Tamil Nadu. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 02-Mar-2022 | Corrigendum No 1 - EPCM Services for Group-II LOBS Project at Manali Refinery of CPCL | Date | 16-03-2022 |
2 | 15-Mar-2022 | Replies to Pre Bid Queries - EPCM Services for Group-II LOBS Project at Manali Refinery of CPCL | Other | 30-03-2022 |
3 | 15-Mar-2022 | Corrigendum No 2 - EPCM Services for Group-II LOBS Project at Manali Refinery of CPCL | Date | 30-03-2022 |
4 | 18-Mar-2022 | LOBS-II EPCM Corrigendum No. 3 | Technical Bid | 30-03-2022 |
5 | 30-Mar-2022 | EPCM Services for Group-II LOBS project at CPCL- Corrigendum No. 4 | Date | 06-04-2022 |
6 | 04-Apr-2022 | EPCM Services for Group-II LOBS Project-Corrigendum No. 5 | Date | 18-04-2022 |
7 | 13-Apr-2022 | EPCM Services for Group-II LOBS project- Corrigendum No. 6-Extension of Bid Due Date | Date | 23-04-2022 |
8 | 23-Apr-2022 | EPCM Services for Group-II LOBS Project at CPCL-Modification of terms and conditions and extension of bid due date | Date | 30-04-2022 |
9 | 28-Apr-2022 | EPCM Services for Group-II LOBS Project at Manali Refinery of CPCL -Corrigendum No. 8 on Extension of Bid due date (BDD) | Date | 09-05-2022 |
10 | 10-May-2022 | Corrigendum for Date Extension | Date | 16-05-2022 |
Sl. No. | Item Description |
1 | Total Lumpsum charges for consultancy services for phase-I and Phase-II |
2 | Phase-I :Lump-sum charges for Consultancy services for carrying out following activitities (13 % of Total Lumpsum Consultancy Charges for Phase-I and Phase-II) |
3 | a) Review & Finalization of BDEP of CDWU-II Unit and OHCU revamp & preparation of BDEP for O&U b) Preliminary FEED preparation c) Submission of +/-10% cost estimate & DFR d) Tendering and recommendation for placement of Pos for LLIs e) Documentation for statutory approvals |
4 | Phase-II :Lump-sum charges for Consultancy services (87% of Total Lumpsum Consultancy Charges for Phase-I and Phase-II) |
5 | Total Lump sum charges for Consultancy-EPCM (Head Office services). |
6 | Charges for services towards construction management & supervision; consultant shall be paid on man-month basis for EPCM Package. |
7 | RCM (Engineer-in-charge) for EPCM |
8 | Dy. RCM / Area Managers For EPCM Construction management (85% of RCM Rate) |
9 | Engineers for various disciplines and other Officers for HSE, Labor Welfare, Stores Management, Documentation Controller etc. for EPCM (75% of RCM Rates) |
10 | Charges for services towards assistance in pre-commissioning, start-up, commissioning & performance test run etc.,; consultant shall be paid on man-month basis. |
11 | Commissioning Specialist |