Up-Gradation Of Existing Internal Road Of Length 1500 Rm And 7.50 M Wide And Construction Of 4 ( Four ) Nos. Of Box Culvert At Astcl, Noapara, Bijni, Assam Under Sopd Scheme
Tender Value
4.46 Crore
Estimated cost
Bid Submission
19 Feb 2022
0 days left
EMD
8.94 Lakhs
Bank guarantee accepted
Document Fee
10000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
bijni → Assam
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Up-Gradation Of Existing Internal Road Of Length 1500 Rm And 7.50 M Wide And Construction Of 4 ( Four ) Nos. Of Box Culvert At Astcl, Noapara, Bijni, Assam Under Sopd Scheme
BOQ
| Sl. No. | Item Description |
| 1 | Upgradation of existing Internal road |
| 2 | Clearing Grass and Removal of Rubbish Clearing grass and removal of rubbish up to a distance of 30 m outside the periphery of the area as per Technical Specification Clause 201.By Manual Means |
| 3 | Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 |
| 4 | Compacting original ground supporting subgradeLoosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per TechnicalSpecification Clause 303.5.2. |
| 5 | Construction of Subgrade and Earthen ShouldersConstruction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000m as per Technical Specification Clause 303.1.(i) Private Land |
| 6 | Haulage excluding Loading & UnloadingHaulage of materials by tipper excluding cost of loading, unloadingand stacking.Case-I : Surfaced Road(for 10 km) |
| 7 | Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by Mechanical Means |
| 8 | (ii) Loading of earth,sand,moorum,manure,fly ash by mechanical means including a lead upto 30 M |
| 9 | (iii) Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry Work by mechanical means. |
| 10 | Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC,and compacting with vibratory roller to achieve the desired density,complete as per cl. 401 |
| 11 | For Grading I Material |
| 12 | For Grading II Material |
| 13 | Haulage excluding Loading & UnloadingHaulage of materials by tipper excluding cost of loading, unloading and stacking. |
| 14 | Case-I : Surfaced Road(for 7 km) |
| 15 | Case-II: Unsurfaced Gravel Road(for 3 km) |
| 16 | Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by Mechanical Means |
| 17 | (i) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by mechanical means including a lead upto 30 m |
| 18 | (iii) Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry Work by mechanical means. |
| 19 | Water Bound Macadam Sub-base/base |
| 20 | WBM Grading 1Using stone screening Type-A 13.2 mm for Gr.IProviding, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification includingspreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fillup the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical SpecificationClause 404.(B) By Mechanical Means |
| 21 | WBM Grading 2Using stone screening Type-B 11.2 mm for Gr.IIProviding, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification includingspreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fillup the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical SpecificationClause 405.(B) By Mechanical Means |
| 22 | Haulage excluding Loading & UnloadingHaulage of materials by tipper excluding cost of loading, unloadingand stacking. |
| 23 | Case-I : Surfaced Road(for 7 km) |
| 24 | Case-II: Unsurfaced Gravel Road(for 3 km) |
| 25 | Loading and Unloading Lime, Aggregate, Stone Boulder, BrickAggregate, Kankar, Building Rubbish, Crushed Slag, Stone forMasonry Work by Mechanical Means |
| 26 | (i) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by mechanical means including a lead upto 30 m |
| 27 | (iii) Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry Work by mechanicalmeans. |
| 28 | Providingand layingInterlocking Concrete Block Pavement (ICBP) conforming to IS:15658-2006 including all lead and lift complete as per technical specification and as directed. b) 100mm thick interlocking precast blocks having compressive strength of 50N/sq.mm. |
| 29 | c) Providing and layingM-40 grade cement concrete Edge block/ Edge restraints complete as per Technical specificationclause 1504. |
| 30 | Construction of 4 nos of Culvert |
| 31 | Excavation for StructuresEarthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.Ordinary soilUpto 3 m depth |
| 32 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 With crushed Stone |
| 33 | P.C.C grade M 10Nominal mix 1:3:6 |
| 34 | R.C.C Grade M25 |
| 35 | Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 |
| 36 | Loading and Unloading of Structural Steel and Steel Bars by manual means |
| 37 | Loading of Structural Steel, Steel Bars by manual means including a lead upto 30 m |
| 38 | Unloading of Structural Steel, Steel Bars by manual means including a lead upto 30 m |
| 39 | Brick SolingLaying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross-section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering and rolliing the same with three wheel road roller 80-100 kN as per Technical Specification Clause 412 |
AI Tender Summary
Tender Timeline
Jan 31, 2022
11:30 IST
Tender Published
Tender notice published.
CompletedFeb 19, 2022
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedFeb 19, 2022
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents