| 1 | E/W in exacavation in foundation trenches in hard soil and disposal of excavated earth as obtained to a distance up to 50 M includind all lifts, levelling, ramming the foundation trenches, removing roots of trees,shurbs all completes as per approved design,building specification and direction of E/I. |
| 2 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and wateringn in layers not exceeding 150 mm thik with all leads and lifts including cost of all materials, labour, royality and texes all complete as perbuilding specification and direction of E/I |
| 3 | Providing designation 75B, one on B/F solling joints filled with local sand including cost of watering taxes royality, all complete as per building specification and direction of E/I. |
| 4 | Providing P.C.C M-20 in nominal mix of (1:1.5:3) in foundation with approved quality of stone chips 20 mm to 6 mm size graded and clean coarse of F.M 2.5 to 3 including screening, shuttering, mixing cement concrete in mixer and placing in position, vibrating, striking,curing,taxes and royality all complete as per building specification and direction of E/I. |
| 5 | Providing designation 75B brick work in C.M (1:6) in foundation and plinth with approved quality of clean coarse sand of F.M 2 to 2.5 including approved 10mm thick mortar joints , cost of screening materials raking out joints to 15mm depth , curing , taxes and royalty all complete as per building specifition and direction of E/I. |
| 6 | Providing 12 mm thick Cement Plaster (1:4) With clean coarse sand of F.M- 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I |
| 7 | Providng 1.5 mm cement punning including curing, carriage of water with all leads as per building specification and direction of E/I. |
| 8 | Centering and shuttering including struting , proping etc and removal of form for foundation and footings , column bases etc for mass concrete |
| 9 | Providing pre cast RCC (1:1.5:3) Cover on Drainas per approved pattern and setting in position with C M (1:3) Including the cost of centering and shuttering all complete as per direction of E/I. |
| 10 | Providing Tor steel reinforcement of 10 mm,dia bars as per approved design and drawing excluding carriage of bars to work site, C/B/Bwith annealed wire with cost of wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I. |
| 11 | Providing Tor steel reinforcement of 8 mm,dia bars as per approved design and drawing excluding carriage of bars to work site, C/B/Bwith annealed wire with cost of wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I. |
| 12 | carriage of material Cost.Brick(Lead- 17KM) |
| 13 | Brick(Lead- 22KM) |
| 14 | Brick(Lead- 30KM) |
| 15 | Sand: (Lead- 9KM) |
| 16 | Sand: (Lead- 10KM) |
| 17 | Stone chips(Lead- 22KM) |
| 18 | Stone chips(Lead- 28KM) |
| 19 | Stone chips(Lead- 29KM) |
| 20 | Steel: (Lead- 6KM) |
| 21 | Steel: (Lead- 8KM) |
| 22 | Cement: (Lead-8KM) |
| 23 | Cement: (Lead-5KM) |
| 24 | Cement: (Lead-6KM) |
| 25 | Goods & Service Tax (G.S.T.) - |
| 26 | Labour Cess - |