| 1 | Construction of 1.00 MLD Rapid sand filtration plant comprising of labor for DI pipe from existing Raw water main/pump, inlet box, inlet channel. Alum dozing Flash mixing , Tapered flocculate Rectangular setting tank, filter box, over head reservoir for back wash including pump sets and electric control panel, sluice valves, DI pipes, DI specials, manhole covers, air scour equipment , chemical house including chlorination equipment and arrangement of flow measurement and sand bed complete in all respect as per DNIT. Labor rate for fixing DI, S/S class K9 ISI marked pipes incluidng cost of DI specials/fitting, ISI marked PN 1.6 sluice valves incluidng cost of excavation, laying, cutting , jointing , threading and jointing material in horizontal length including connection complete in all respects. From existing raw water main pump to inlet box of filter unit to clear water tank, note DI pipe will be supplied by the department free of cost (Based on SCADA System 1.00 MLD WTP) |
| 2 | Supply and Erection of Horizontal spindle split casing type pumping sets of minimum four 4 star rating duties directly coupled to AC squarrel cage induction type motor with 1440 RPM, 3 Phase, 50 Hz and accessories as described in Schedule No. II with priming arrangement and complete base frame as per IS marked complete in all respect A) Raw Water Pump Set 1100 LPM with 12 Mtrs Head at W/W |
| 3 | B) Raw Water Pump Set 2000 LPM with 30 Mtrs Head atsump well |
| 4 | Supply, erection, testing and commissioning wall mounted electrical panel board, fabricated from 16 SWG CRCA sheet duly stouted with suitable angle iron frame work and completely powder coated of approximate size 1200 x 900 mm and 400 mm deep having following items.A) For Raw Water Pump Set for 1100 LPM x 12 Mtrs Head = 2 Nos a) Main switch 63 Amp 2 No. (L&T siemens, ABB)b) Volt meter 100 x 100 mm range 0 to 500 volt 1 No. (AE/KAPPA/L&T)c) Amp meter 100 x 100 mm range 0 to 100 Amp 2 Nos (AE/KAPPA/L&T)d) CT 100/3 Nos. (AE/KAPPA/L&T)e) VSS1 No. & ASS 2 No. each of approved make f) SPP 1 No. of approved makeg) Motor starter, star delta 2 No. for 1100 LPM x 12 m Head Motor (L&T, Simens, AAB)h) Capacity of suitable capacity -2 Nos. i) Indicating Lamp One setj) Change over switch 63 Amp-1 No |
| 5 | A) For Clear Water Pump Set for 1100 LPM x 40 Mtrs Head = 2 Nos a) Main switch 100 Amp 2 No. (L&T siemens, ABB)b) Volt meter 100 x 100 mm range 0 to 500 volt 1 No. (AE/KAPPA/L&T)c) Amp meter 100 x 100 mm range 0 to 100 Amp 2 Nos (AE/KAPPA/L&T)d) CT 100/3 Nos. (AE/KAPPA/L&T)e) VSS1 No. & ASS 2 No. each of approved make f) SPP 1 No. of approved makeg) Motor starter, star delta 2 No. for 1100 LPM x 40 m Head Motor (L&T, Simens, AAB)h) Capacity of suitable capacity -2 Nos. i) Indicating Lamp One setj) Change over switch 100 Amp-1 No |
| 6 | A) For raw Water Pump Set for 2000 LPM x 30 Mtrs Head = 2 Nos a) Main switch 100 Amp 2 No. (L&T siemens, ABB)b) Volt meter 100 x 100 mm range 0 to 500 volt 1 No. (AE/KAPPA/L&T)c) Amp meter 100 x 100 mm range 0 to 100 Amp 2 Nos (AE/KAPPA/L&T)d) CT 100/3 Nos. (AE/KAPPA/L&T)e) VSS1 No. & ASS 2 No. each of approved make f) SPP 1 No. of approved makeg) Motor starter, star delta 2 No. for 2000 LPM x 30 m Head Motor (L&T, Simens, AAB)h) Capacity of suitable capacity -2 Nos. i) Indicating Lamp One setj) Change over switch 100 Amp-1 No |
| 7 | A) For Clear Water Pump Set for 400 LPM x 30 Mtrs Head = 2 Nos a) Main switch 63 Amp 2 No. (L&T siemens, ABB)b) Volt meter 100 x 100 mm range 0 to 500 volt 1 No. (AE/KAPPA/L&T)c) Amp meter 100 x 100 mm range 0 to 100 Amp 2 Nos (AE/KAPPA/L&T)d) CT 100/3 Nos. (AE/KAPPA/L&T)e) VSS1 No. & ASS 2 No. each of approved make f) SPP 1 No. of approved makeg) Motor starter, star delta 2 No. for 400 LPM x 30 m Head Motor (L&T, Simens, AAB)h) Capacity of suitable capacity -2 Nos. i) Indicating Lamp One setj) Change over switch 63 Amp-1 No |
| 8 | Supply erection, testing of ISI marked copper wire for 2 Nos. motors with under ground system in PVC and flexible pipes copper wire size 6 mm sq complete in all respects with accessories like thimble etc complete in all respecta) 6Sq mm 3 core |
| 9 | b) 10 sq mm 3 core |
| 10 | c) 25 sq mm 3 core |
| 11 | Credit of pumping machinery and Sluice valve A) Raw Water 600 LPM x 12 Mtr Head |
| 12 | B)Clear Water 600 LPM x 40 Mtr head |
| 13 | C)Sluice valves |
| 14 | D) Credit of 450 mm i/d RCC pipe NP2 |
| 15 | Operation and Maintenance for water works complete scope of work (Disinfection material supplied by the PHED) as per schedule-IV for a period of 5 years after 12 months during defect liability period and 3 month trial run period (will be charged to the A/Mtc estimate complete in all respect Operation and Maintenance during defect liability period (Operation only) after 3 months trial run period |
| 16 | For 1st year Operation and Maintenance after defect liability period |
| 17 | For 2nd year Operation and Maintenance |
| 18 | For 3rd year Operation and Maintenance |
| 19 | For 4th year Operation and Maintenance |
| 20 | For 5th year Operation and Maintenance |