M / T Works On Link Road From Nirmand To Johad Via Ambika Mata Temple At Nirmand Km. 0 / 00 To 4 / 435. Under Mnp. ( Sh- Repair Of Pot Holes By Providing And Laying Wbm G-Ii And Tarring Works In Km. 0 / 850 To 1 / 200 And 1 / 280 To 1 / 4
Tender Overview
Project Description
M / T Works On Link Road From Nirmand To Johad Via Ambika Mata Temple At Nirmand Km. 0 / 00 To 4 / 435. Under Mnp. ( Sh- Repair Of Pot Holes By Providing And Laying Wbm G-Ii And Tarring Works In Km. 0 / 850 To 1 / 200 And 1 / 280 To 1 / 450 ) Under Deposit Of Teleco M / T Works On Link Road From Nirmand To Johad Via Ambika Mata Temple At Nirmand Km. 0 / 00 To 4 / 435. Under Mnp. ( Sh- Repair Of Pot Holes By Providing And Laying Wbm G-Ii And Tarring Works In Km. 0 / 850 To 1 / 200 And 1 / 280 To 1 / 450 ) Under Deposit Of Teleco
BOQ
| Sl. No. | Item Description |
| 1 | Providing and laying, spreading and compacting stone aggregates of specific size to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 KN static roller in stages to proper grade and camber, applying and brooming, stone screening/ binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density Grading II as per Technical Specification Clause 405, including carriage of materials, plants/equipments by all modes of transportation within all leads and lifts and as per directions of The Engineer – in – Charge complete. |
| 2 | Providing and applying primingcoat with bitumen emulsion(SS-1) using bitumen distributor at the rate of 0.85 kg. (Zero point eight five Kilogramme) per square metre on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specificationsclause of 502 including carriage of materials, plants/equipments by all modes of transportation within all leads and lifts and as per directions of The Engineer – in – Charge complete. |
| 3 | Providing and applying tack coat with bitumen emulsion (RS-I) using emulsion pressure distributor@ 0.275 kg (Zero point two seven five Kilogramme) per square metreofthe prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specifications of clause 503including carriage of materials, plants/equipments by all modes of transportation within all leads and lifts and as per directions of The Engineer – in – Charge complete. |
| 4 | Providing and laying 25 mm (twenty five milimetre) thick bitumenous concrete with 100-120 PH batch type hotmix plant producing and average output of 75 tonne (Seventy five tonne) usingcrushed aggregates of specified grading premixed with bituminous binder @ 5.5 (Five point five) percent or mix and filler including addition Zycotherm @ 0.10 % (zero point ten percent) of weight of bitumen, transorting the hot mix to work site lying with a hydro static paver finisher with sensor control to the required grade,level and alignment, rolling with smooth wheeled vibratory and tendom roller to achieve the desired compection as per MORTH specification No. 50 including carriage of materials, plants/equipments by all modes of transportation within all leads and lifts and as per directions of The Engineer – in – Charge complete. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender