Construction Of Kitchen Room And Reparing , Renovation Of 2Nd Floor School Building At Kerur High School Mouza Kerur Jl No 278 Plot No 557 And 448 Under Sabang Development Block In The District Of Paschim Medinipur. Pin 721155
Tender Overview
Project Description
Construction Of Kitchen Room And Reparing , Renovation Of 2Nd Floor School Building At Kerur High School Mouza Kerur Jl No 278 Plot No 557 And 448 Under Sabang Development Block In The District Of Paschim Medinipur. Pin 721155
BOQ
| Sl. No. | Item Description |
| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.Depth of excavation not exceeding 1,500 mm. |
| 2 | Filling in foundation or plinth by fine sand in layers not exceeding 150 mm as directed and consolidating the same by through Saturation with water,ramming complete including the cost of supply of sand (Payment to be made on measurement of finished quantity) |
| 3 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) |
| 4 | Cement concrete with Graded Stone ballast(40mm. Size) Excluding shuttering,if any ground floor(A) Pakur Variety(a)1:3:6 |
| 5 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes. a) Pakur Variety |
| 6 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. |
| 7 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) inground floor. |
| 8 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor). 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge. |
| 9 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor). 25 mm to 30 mm shuttering without staging in foundation |
| 10 | Ordinary grating bars made of round or square M.S. rods fitted and fixed in holes of window frames etc, complete. |
| 11 | Asbestos corrugated (Trafford or similar approved quality) sheet (6 mm thick) work (excluding the supporting framework) fitted and fixed with 9.5mm. dia. J or L hookbolt and nuts, limpet and bitumen washers and putty with 150 mm end lap & one corrugation minimum side lap complete. (Payment should be made on area of finished work) |
| 12 | Galvanised iron sheet ridging fitted with necessary bolts, screws, washers etc complete.(225mm end lapping)300 mm lapping each wayWith 0.60 mm sheet |
| 13 | Wood work in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame exluding cost of concrete,Iron Butt Hinges and M.S clamps. (The quantum should be correted upto three decimals). |
| 14 | Z-batten shutters of door and window as per design havings tongued and groovehalflap jointed as per direction of the Engineer-in-Charge including fitting and fixing shutter in position, but excluding the cost of hinges and other fittings in ground floor. |
| 15 | Iron butt hinges of approved quality fitted and fixed with steel screws, with ISI mark.100mm. X 75mm. X 3.50mm. |
| 16 | Iron butt hinges of approved quality fitted and fixed with steel screws, with ISI mark. 75mm. X 60mm. X 3.15mm. |
| 17 | Iron door ring of approved quality fitted and fixed with nut and washer complete.50 mm dia |
| 18 | Supplying, fitting and fixing M.S. clamps for door and window frame made of flat bent bar, end bifurcated with necessary screws etc. by cement concrete(1:2:4) as per direction. (Cost of concrete will be paid separately)40mm X 6mm, 250mm Length |
| 19 | Supplying, fitting and fixing M.S. clamps for door and window frame made of flat bent bar, end bifurcated with necessary screws etc. by cement concrete(1:2:4) as per direction. (Cost of concrete will be paid separately) (a) 40mm X 6mm, 200mm Length |
| 20 | Iron skeleton bolt of approved quality fitted and fixed complete. |
| 21 | M.S. structural works in roof trusses with tubular sections conforming to IS: 806-1968 & IS: 1161- 1998 cnnected to one another with bracket, gusset cleats as per design, direction of Engineer-in-charge complete including cutting to requisite size, fabrication with necessary metal arc welding conforming to IS: 816- 1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all t ools and plants and labour reqired for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural tubular memebrs as specified in relevent IS code in finished work. Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a height of erection 8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate for each additional floor or 4m. beyond the initial 8 m. or part thereof. |
| 22 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) inground floor. |
| 23 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface]. |
| 24 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface]. |
| 25 | Applying decorative cement based paint of approved quality after preparing the surface including scraping the same thorough (plastered or concrete surface) as per manufacturer\"s specification. |
| 26 | M.S.or W.I. Ornamental grill of approved design joints ontinuously welded with M.S, W.I. Flats and bars of windows, railing etc. fitted and fixed with necessary screws and lugs in ground floor.Grill weighing above 16 Kg./sq.mtr and above |
| 27 | Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75 kg/sq.m all complete including all materials and labour.Above roof waring course. |
| 28 | Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75 kg/sq.m all complete including all materials and labour.2nd floor. |
| 29 | GST 12% |
| 30 | Labour Cess 1% |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender