Kerala State Electricity Board-KSEB has published Rearranging Existing 11Kv Cross Country Line Under Es, Kply North Rearranging The Existing 11Kv Cross Country Line (Thevalassery To Varavila) Under Es, Karunagappally North. Submission Date for this Tender is 19-01-2022. Transmission Line Tenders in Kerala. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
2 | Loading HT "A" type pole from the stacking place and unloading the same at work site (transport by vehicle). |
3 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
4 | Dismantling one damaged 11kV TW/RSJ/Rail pole after disconnecting stays, strut etc. and stacking the same. |
5 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
6 | Dismantling (without damage) one 11kV "A" type pole after disconnecting stays, strut etc. and stacking the same. |
7 | Dismantling (without damage) one km 11kV line (3 conductors), cross arm, insulators, disc, rolling the conductor and stacking. |
8 | Dismantling (without damage) one HT stay incl. back filling, and bringing back to section store. |
9 | Dismantling one Channel cross arm from existing DP structure, and bringing back to section store. |
10 | Dismantling one damagedAB switch from existing structure. |
11 | Fitting and erecting one HT "A" type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
12 | Additional rate for providing one disc set on any type of HT pole for making cut point. |
13 | Fitting and erecting one HT DP using "A" type pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
14 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
15 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
16 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole incl. digging & back filling pits. |
17 | Stringing of one km 11kV line with ACSR Raccoon (3 conductors) incl. cutting and removing tree branches wherever necessary. |
18 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling. |
19 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
20 | Fitting one set AB switch and giving connection |
21 | Conveyance of one km 11kV line materials from section store/stacking place to the work site (excluding poles). |
22 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials. |
23 | Fitting one Additional 2.4m/3m Channel cross arm (75x40x6mm), in existing 11kV DP incl. conveyance of materials. |
24 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
25 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
26 | Dismantling (without damage) LT stay incl. digging pit in all classes of soil and backfilling |
27 | Dismantling (without damage) one LT PSC/RCC Strut pole incl. removal of clamps and stacking. |
28 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
29 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
30 | Transferring LT Sph 2/3 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
31 | Transferring LT 3ph 4/5 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
32 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
33 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |
34 | Stringing one km LT 3ph 5 wire line (Rabbit for Ph and Weasel for N&St.main) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
35 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole and reconnecting. |
36 | Dismantling one 2x40W fluorescent tube fitting from the existing pole and refitting the same on newly erected pole and reconnecting. |
37 | Cutting trees beyond 30cm but upto and incl. 60cm girth, cutting of trunks/branches, removing the root completely and stacking. |
38 | Cutting trees beyond 60cm but upto and incl. 120cm girth, cutting of trunks/branches, removing the root completely and stacking. |
39 | Cutting trees beyond 30cm but upto and incl. 60cm girth, cutting branches, removing root completely and stacking (where space for falling trees is not enough). |
40 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
41 | Transporting one HT PSC pole by Head load (limited to 0.3km). |
42 | Transporting "A" type pole by Head load (limited to 0.3km). |
43 | Transporting one HT TW/RSJ/Rail pole by Head load for an average distance of one km (limited to 0.3km). |
44 | Additional rate for excavation of one Earth Pit (2.5m depth) in Laterite. |
45 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
46 | Additional rate for excavation of Pit for "A" type pole in Laterite. |
47 | Additional rate for refitting/redoing one Shackle set and reshackling one span while renewing any type of pole. |