| 1 | Providing and constructing 50 mm. thick ModifiedPenetration Macadam (MPM)road surface including all mataerials, preparing the existing road surface, spreading 40mm. stone metal layers 100% crusher broken metal with conical crusher plant heating and spraying thebitumen of specified grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting withstatic roller having weight 8 to 10 MT. to achive the desired degree of compaction as per Technical Specification Clause 506etc. complete.Including picking of existing WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates) |
| 2 | Providing and applying tack coat on the prepared surface heating by fames in Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5 kg/10 sqm.(VG-30 bulk bitumen rates are considered to arrive at rates) |
| 3 | BITUMINOUS MACADAM:--Providing and laying bituminous macadam using crushed aggregate of Grading 1, premixed with bituminous binder, transported at site with VTS, laid over a previously prepared surface , finished to the required grade ,level, alignment,and rolling to achieve the desired density for 80/100 mm compacted thickness with drum mix type hot mix plant with SCADA having complying essential features of Hot mix plant as per IRC-27 2009 specified conditions and attachments such as electronic load sensor based belt conveyers,automatic synchronization of bitumen and aggregate fedder,built in dust controller system and PLC for Drum Mix plant ,Sensor paver,and Vibratory roller excluding prime/Tack coat etc. complete --Bitumen3.30% of specified grade (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 4 | BITUMINOUS CONCRETE:- Providing and laying bituminous concrete using crushed aggregates of grading 1, premixed with bituminous binder @ 5.20 per cent by weight of total mix and filler, transported to site with VTS , laid over a previously prepared surface, finished to the required grade, level, alignment, and rolling to achieve the desired compactionfor 50 mm compacted thickness with specified grade of Bitumen,Excluding prime / tack coat. For Bitumen of specified grade -- USING Batch mix type hot mix plant with SCADA, Sensor Paver, Vibratory roller with Stone Dust filler. (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 5 | Supplying hard murum/ kankar at the road site, including conveying and stacking complete. |
| 6 | Spreading hard murum/ soft murrum/ gravel or kankar for side width complete |
| 7 | Providing and fixing board displaying information such as Name of work, Tender cost, Name of Contractor, Work completion and liability period etc.having rectangular shape of 1.20 x 0.90 cm.size made out 18 gauge (1.25 mm) thick mild steel sheet painted with one coat of zinc chromate stoving primer and two coats of enamel paints on front side and gray stove enamel on back side and borde / messages / symbols etc.with apprved coloured shade paint complete.on M.S.angle of size 35 x 35 x 3 mm fame with properly cross braced M.S.angles of size 35 x 35 x 3 mm duly painted including two M.S.angle iorn posts of size 65 x 65x 6 mm, 3.65 m long painted with alternate black and white bunds of 25 cm. width including all fixtures etc.and fixing the board in 1:4:8 concrete block of size 60 cm x 60cm x 75 cm.including excavation, refilling, transportation, and labour etc.complete. |
| 8 | Add for Royalty charges of material etc. |
| 9 | Add for Test Result chargesetc. complete. |
| 10 | Add GST 12 % |
| 11 | Add Insurance 1% |