Highways Department-HD has published Special Repairs To Rajamadam - Eripurakkarai Road Special Repairs To Rajamadam - Eripurakkarai Road At Km 0 / 0-2 / 0. Submission Date for this Tender is 05-01-2022. Road Work Tenders in Pattukottai Tamil Nadu. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Picking the existing BT surface upto 80mm depth as directed by the departmental officers and levelling the surface including all labour charges for pickig and all other tools and plants employed of the work and including all other incidental charges etc., complete as per standard specifications as per MORTH Nos., 111, 112, 201, 202. |
2 | Wet Mix Macadam (Table 400-13) (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density, Complete as per clause 406) .as per MORT&H Rev.-V specifications No.111. 112. 406. 900. |
3 | Prime coat (Providing and applying primer coat with bitumen emulsion (SS-I type) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per clause 502) - over WMM .as per MORT&H Rev. V specifications No.111, 112, 502, 900. |
4 | Tack coat - Providing and applying tack coat with bitumen emulsion (RS-I type) using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous/granular surface cleaned using mechanical means as per clause 503 - over granular surfaces treated with primer.as per MORT&H Rev. V specifications No.111, 112, 503, 900. |
5 | Tack coat - Providing and applying tack coat with bitumen emulsion (RS-I type) using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned using mechanical means as per clause 503 - over the existing BT surfaces as per MORT&H Rev. V specifications No.111, 112, 503, 900. |
6 | Advance Patch work to an average thickness of 50mm using 45mm IRC size HBG metal with 44Kg of 80/100 grade bulk bitumen per 1 cum of metals including premixing, laying over the existing BT surface and compaction including all other incidental charges etc., completed as per MORTH Clause 111, 112, 501, 900 |
7 | Bituminous Macadam with hot mix plant using crushed aggregates of specified grading premixed with bituminous binder (Viscosity Grade-30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction, complete as per clause 504 and in accordance with standard specifications for Grading II as per MORTH Vth Rev. 111, 112, 504 & 900 |
8 | Bituminous Concrete (Table 500-17) (Providing and laying bituminous concrete with hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder (Viscosity Grade - 30) at percentage specified by JMF of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects) - Grading II as per MORT&H Rev. V specifications No.111, 112, 507, 900. |
9 | Earth work excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation backfilling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For Carted Earth with compaction for making up of low berms with conveyance of 30 Km as per MORTH Clause.111, 112, 301, 3003 and 900 |
10 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
11 | Basic cost of value put to tender as per estimate |
12 | Add GST at 12% |
13 | Total Value put to Tender |
14 | Negotiated Percentage |
15 | Final Negotiated Value |
16 | Add GST at 12% of Final Negotiated Value |
17 | Total Value of Contract Including 12% of GST |
18 | Basic cost of value put to tender as per Estimate |
19 | Quoted Rate in Figures (Total Value of Contract Including 12% of GST ) |