Construction Of 3 Nos. Rebore Tubewels Of Size 300X200mm And 135 Mt. Depth By D.C. Rig Machine And Supply Installation Testing And Commissioning Of Its Associated Works In Aligarh Nagar Tender Document Of Tubewell And Associated Works- 1 Shifting And Car
Tender Overview
Project Description
Construction Of 3 Nos. Rebore Tubewels Of Size 300X200mm And 135 Mt. Depth By D.C. Rig Machine And Supply Installation Testing And Commissioning Of Its Associated Works In Aligarh Nagar Tender Document Of Tubewell And Associated Works- 1 Shifting And Carting Of Rig Machine And Its T&Pupto Site And Back With Loading And Unloading Complete In All Respect. 2 Shifting And Carting Of Air Compressor And Its T&Pupto Siteand Back With Loading And Unloading Complete In All Respect. 3 Shifting And Carting Of Op Unit & Its T&P Upto Siteand Back With Loading And Unloading Complete In All Respect. 4 Carting Of Tubewell Assembly Upto Site With Loading And Unloading Complete In All Respect. 5 Erection Of Rig Machine And Its T&P ( 11X1 ) 6 Dismantling Of Rig Machine And Its T&P ( 11X1 ) 7 Drilling Of 675 Mm Diabore From Gl To 70 M Bgl 8 Drilling Of 500 Mm Dia Bore From70 To 100 M Bgl 9 Drilling Of 500 Mm Dia Bore From100 To 135 M Bgl 10 Electrical Logging Of Borewell 11 Lowering Of 300Mm Dia M.S. Housing Pipe From Gl To 60 M Bgl 12 Lowering Of 200Mm Dia Plain / Slotted Pipe From 60 M Bgl To 100 M Bgl 13 Lowering Of 200Mm Dia Plain / Slotted Pipe From 100 M Bgl To 120 M Bgl 14 Shrouding Of Pea-Gravel 15 Erection Of 250 Psi Air Compressor For Development Of Tubewell 16 Development Of Tubewell By 250 Psi Air Compressor 17 Dismantling Of 250 Psi Air Compressor After Development 18 Erection Of Op Unitfor Development Of Tubewell 19 Development Of Tubewell By Op Unit 20 Dismantling Of Op Unit After Development 21 Chemical Test Of Water Sample 22 Barricading Of Site During The Construction Of T.W For Safety Precaution 23 Supply Of 1000 Lpm, 60 M Head Submersible Pump Motor Set 24 Supply Of Switchgear For Pumping Plant With Fully Automatic Digital Soft Starter Panel Suitable For Scada Operation 25 Supply Of Main Piping And Valves Of 100 Mm Size. Length Of Column Pipes-45 M 26 Supply Of Pressure Ce / Ul Approved ManufacturerS Smart Pressure Transmitterand Depth Gauge 27 Supply Of Lifting Tackle - 2 Tonnes Capacity 28 Supply Of Special Tools And Spanners 29 Supply Of Miscellaneous Items Such As Protection Rings, Cut-Outs, Tw Cover, Insulating Rubber Mats Etc. 30 Supply Of Servo Voltage Stabilizer 40 Kva 31 Painting Of Main Piping And Valves 32 Erection Of Pumping Plant And All Other Equipments 33 One Month Watch & Ward During The Period Of Installation 34 Testing At Works, Commissioning And Trial Run For 1 Month 35 Supply Of Electromechanical Chemical Plant 36 Three Months Operation And Maintenance Of Electrical & Mechanical Items.
BOQ
| Sl. No. | Item Description |
| 1 | Shifting and Carting of Rig Machine and its T&Pupto site and back with loading and unloading complete in all respect. |
| 2 | Shifting and Carting of Air Compressor and its T&Pupto siteand back with loading and unloading complete in all respect. |
| 3 | Shifting and Carting of OP unit & its T&P upto siteand back with loading and unloading complete in all respect. |
| 4 | Carting of Tubewell Assembly upto site with loading and unloading complete in all respect. |
| 5 | Erection of Rig Machine and its T&P (11X1) |
| 6 | Dismantling of Rig Machine and its T&P (11X1) |
| 7 | Drilling of 675 mm diabore from GL to 70 m BGL |
| 8 | Drilling of 500 mm dia bore from70 to 100 m BGL |
| 9 | Drilling of 500 mm dia bore from100 to 135 m BGL |
| 10 | Electrical Logging of borewell |
| 11 | Lowering of 300mm dia M.S. Housing Pipe from GL to 60 m BGL |
| 12 | Lowering of 200mm dia Plain/Slotted Pipe from 60 M BGL to 100 m BGL |
| 13 | Lowering of 200mm dia Plain/Slotted Pipe from 100 M BGL to 120 m BGL |
| 14 | Shrouding of Pea-Gravel |
| 15 | Erection of 250 PSI Air Compressor for Development of Tubewell |
| 16 | Development of Tubewell by 250 PSI Air Compressor |
| 17 | Dismantling of 250 PSI Air Compressor after Development |
| 18 | Erection of OP Unitfor Development of Tubewell |
| 19 | Development of Tubewell by OP Unit |
| 20 | Dismantling of OP Unit after Development |
| 21 | Chemical test of water sample |
| 22 | Barricading of site during the construction of T.W for safety precaution |
| 23 | Supply of 1000 lpm, 60 m Head Submersible Pump Motor Set |
| 24 | Supply of Switchgear for pumping plant with fully automatic digital soft starter panel suitable for SCADA operation |
| 25 | Supply of Main Piping and Valves of 100 mm size. Length of Column Pipes-45 m |
| 26 | Supply of Pressure CE/UL approved manufacturer\"s Smart Pressure Transmitterand depth gauge |
| 27 | Supply of Lifting Tackle - 2 Tonnes capacity |
| 28 | Supply of Special Tools and Spanners |
| 29 | Supply of Miscellaneous items such as Protection Rings, Cut-outs, TW Cover, Insulating Rubber Mats etc. |
| 30 | Supply of Servo Voltage Stabilizer 40 kVA |
| 31 | Painting of Main piping and valves |
| 32 | Erection of pumping plant and all other equipments |
| 33 | One month watch & ward during the period of installation |
| 34 | Testing at works, Commissioning and Trial Run for 1 month |
| 35 | Supply of Electromechanical Chemical Plant |
| 36 | Three months Operation and maintenance of Electrical & Mechanical items. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents