Name:Construction of WHT near land of Gh Nabi Jehra at lone mohallah HalqaBrenwar
Sl. No.
Item Description
1
Road
2
Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed,all kinds of soils.lead 25 m from cutting edge.
3
Providing andlaying of Stone Solling duly hand packedincluding ramming, watering ,complete job.
4
Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)
5
Centering and shuttering including strutting, propping etc. and removal of form forWalls (any thickness) including attached pilasters, buttresses, plinth andstring courses etc.
6
Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
7
12mm Cement plaster of mix in 1 : 4 ( 1 cement : 4 coarse sand)
8
Supplying at site Angle iron post & strut of required size including bottom to be split and bent at right angle in opposite direction for 10 cm lengthand drilling holes upto 10 mm dia. etc. complete.
9
Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts,bolts and washers as required complete as per the direction of Engineer-incharge. Made of G.I. wire of dia 4 mm
10
Carriage of cementfor 8 Kms average lead from Source to site of work
11
Carriage of Stone Aggregatefor 5 Kms average lead from Source to site of work
12
Carriage of Sand for 25 Kms average lead from Source to site of work
13
Carriage ofBoulders for 5 Kms average lead from Source to site of work
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.