| 1 | Making Roka in Old sewer Line Manhole upstrem and downstrem, incl. all labor material in all complete and opening after work incl. with all labor and material rates (M.R.) |
| 2 | Dismantling of max phalt/C.C Road*(stone flagged)iccl. all lab. material lead upto distance 60mtr directed by E/IC T & P Comp.(S.I.No.-694)2020-21 |
| 3 | Dismantling tiled floor incl. stacking of dismantled material as directed by Engineer incharge with in a distance 60mtrT & P Comp.(S.I.No.-8-698)2020-21. |
| 4 | Excavation in soil with mixed kankar bolder in foundation requiring use of all req. tools & tackles, lift upto 1.5mt & lead upto 3.00mtr and removal of surplus earth as directed by ingineer incharge upto a distance of 30mtr from foundation trench incl. [email protected] per Cu.M. (S.No.-252)2020-21 |
| 5 | L.C.C. 1:5:10 Cement,fine sand and 40mm thick ballast incl. all labor, T & P Comp.(S.No.-4.1)2020-21 |
| 6 | Dismantling old sewer hume pipe in trench manually incl. all lab. Material & lead upto the distance 60mtr directed by E/IC T&P Comp. removal silage malwa and silage water Comp. (M.R.) |
| 7 | Supply of R.C.C Pipe NP3-200mm Dia with Collar Transportation Charges & Loading - Unloading Lab. T & P Comp. (M.R.) |
| 8 | Laying & Jointing of 200mm Dia R.C.C. Pipe with a stiff mixture of cement mortar in ratio 1:1 (cement & fine sand) JN CODE -3060 |
| 9 | Earth filling in Plinth excluding supply of necessary quantity of sand frome a Distance of exceeding 8km from the side of work & incl. watering dressing etc req. for proper completion of work (Lead upto 30mtr & lift 1.5mtr)(Labor only)in item no.-255 (2020-21) |
| 10 | Dismantling & Repairing of Nala cross the sewer line nalablockage or unblockage incl. malwa, Labour, cement coarse sand & other material T&P.(M.R.) |
| 11 | Barricading of sewer line & Sewer Manholes with all req. components for all types of vehicles & for Public Safety.(3 Days) (L.S.) |
| 12 | Making connection of drain or sewer line with existing manhole incl. breaking into and making the good walls, floor with on both side with cement mortar 1:3 finished with a floating coat of neat cement and making necessary channels with cement concrete 1:2:4 for the drainage etc Comp. (M.R.) |
| 13 | M-150 B/W 1:3 cement & coarse sand mortar with supply of all material T & P Comp. (S.No.-6.8) 2020-21 |
| 14 | Struck cement pointing 1:3 cement coarse sand mortar with all material T & P Com.(S.I. No. – 13.9) 2020-21 |
| 15 | R.C.C. 1.5/2:3 Cement Coarse Sand Gauge blue Stone 12mm Delhi stone 1:1.5:3 all Complete. (S.No.-5.3)2020-21 |
| 16 | Supply of R.C.C. Sewer Manhole cower with frame cartage loading & unloading all comp. (M.R.) |
| 17 | Fixing of R.C.C. sewer manhole cower with frame cartage loading & unloading all comp. (M.R.) |
| 18 | Interconnection of house humage 110mm P.V.C. pipe in New Sewer Chamber i/c all material & Labor T & P comp. (M.R.) |
| 19 | Repairing of old water supply connections with material and labor comp. (M.R.) |
| 20 | Repairing of Main water pipe line during work. |
| 21 | Disposal of malwa & site clearance for any unwanted materials & Tools as in above 3no. With all other req. tools & tackles.(S.N. 231) 2020-21 |
| 22 | Supply & Fixing of M.S. Board. |
| 23 | Unseen work |
| 24 | Gst @ 12% |