| 1 | Reconnaissance Survey & Inception Report |
| 2 | Topographic Survey including fixing of GPS pin |
| 3 | Conducting survey for L.S. & C.S. |
| 4 | Fixing Horizontal Alignment and Vertical Alignment as per IRC standards |
| 5 | Conducting 7-days traffic volume study at 4 locations |
| 6 | Conducting Origin- Destination study at 4 locations |
| 7 | Clearing the light jungle to a width of30m |
| 8 | Soil sample collection and conducting atterber limits and CBR for road work |
| 9 | *Only if applicable Exploratory Bores at the locations of interchanges, Bridges, ROB\"s etc., and other cross Drainage works |
| 10 | Sub soil exploration machine boring |
| 11 | Test Bore |
| 12 | Detailed report on alignment (including three alternations) fixing Horizontal Alignment and vertical Alignment as per IRC standards |
| 13 | Materials survey for road and bridge works and preparation of rate analysis,SBC calculations, Drawings etc., complete including Design for pavement composition based on kilometre - wise field data |
| 14 | Preparation of land plan schedule and its report |
| 15 | Preparation of detailed estimate and Abstract estimate including power point presentation |
| 16 | Report on Environment & Social impacts Assessment, Report writing and submission of report like inspections report Traffic report etc., complete. |
| 17 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
| 18 | Basic cost of value put to tender as per estimate |
| 19 | Add GST at 18% |
| 20 | Total Value put to Tender |
| 21 | Quated Percentage |
| 22 | Final Quated Value |
| 23 | Add GST at 18% of Quated Value |
| 24 | Total Value of Contract Including 18% of GST |
| 25 | Basic cost of value put to tender as per Estimate |
| 26 | Quoted Rate in Figures (Total Value of Contract Including 18% of GST) |