Repair / Maint Of Central Ac Plant And Package Ac Plant At Af Station Hasimara Under Ge ( Af ) Hasimara Repair / Maint Of Central Ac Plant And Package Ac Plant At Af Station Hasimara Under Ge ( Af ) Hasimara
Tender Value
27.50 Lakhs
Estimated cost
Bid Submission
17 Dec 2021
0 days left
EMD
55000
Bank guarantee accepted
Document Fee
500
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Hasimara → West Bengal
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Repair / Maint Of Central Ac Plant And Package Ac Plant At Af Station Hasimara Under Ge ( Af ) Hasimara Repair / Maint Of Central Ac Plant And Package Ac Plant At Af Station Hasimara Under Ge ( Af ) Hasimara
BOQ
| Sl. No. | Item Description |
| 1 | Note 1: (Applicable for all parts/items) : The bidders/ contractors are advised to read tender document, all drawings & all corrigendum/amendments and general condition of contracts before entry/quoting the rates.Note 2:- Attention to bidder is hereby invited to upload revised BOQ if published during their bid submission. Uploading ofincorrect/ pre-revised BOQ shall be treated as non bonafide and rejected. Fixed credit has been given in technical documents which shall be taken into account during acceptance of bid/tender. |
| 2 | Dismantling complete Compressor set, 35 TR capacity of make Voltas, Model 5H-60and overhauling the compressor by repairand checking ofwornout holes of studs and providing over size studs with nuts & washers and gaskets.Rematlling and balancing of piston,replacement of piston ring, scrapper ring, split pin, castle nut, bushing for piston pin, and set of sealing ring of compressorincluding necessary machine work and replacement of other defective spares, re-assembling the compressor setafter the repair and tested for smooth functioning complete all as specified and directed. Note:- i)Spare parts shall be measured and paid as supply only under respective items. ii) Cost of Tansportation from site to workshop (If any ) and back shall be deemed to be included in quoted rate. iii) Refrigerant gas required for the job is supplied by the firm and paid saperately under relevant items of the schedule. |
| 3 | Supply only set of Gasket 5H-60 Complete all as specified and directed. |
| 4 | All as per item No 3 but suction reed complete. |
| 5 | All as per item No 3 but Discharge reed complete. |
| 6 | All as per item No 3 but piston with piston ring and pin complete. |
| 7 | All as per item No 3 but connecting bearingcomplete. |
| 8 | All as per item No 3 but Main bearing sealed side complete. |
| 9 | All as per item No 3 but main bearing oil pump side complete. |
| 10 | All as per item No 3 but suction springcomplete. |
| 11 | All as per item No 3 but discharge spring complete. |
| 12 | All as per item No 3 but cylinder liner complete. |
| 13 | All as per item No 3 but Oil strainercomplete. |
| 14 | All as per item No 3 but Shaft thrust bearing oil pump side complete. |
| 15 | All as per item No 3 but Shaft thrust bearing sealed side complete. |
| 16 | All as per item No 3 but Suction platecomplete. |
| 17 | All as per item No 3 but Oil sealed set with plate complete. |
| 18 | All as per item No 3 but Oil pump set complete. |
| 19 | All as per item No 3 but liquid line valve size 11/8 complete. |
| 20 | All as per item No 3 but Oil line valve size 7/8 complete. |
| 21 | All as per item No 3 but Discharge valve assembly complete. |
| 22 | Dismantling complete Compressor set, 30 TR capacity of make Accel, Model SMC-8-65and overhauling the compressor by repairand checking ofwornout holes of studs and providing over size studs with nuts & washers and gaskets.Rematlling and balancing of piston,replacement of piston ring, scrapper ring, split pin, castle nut, bushing for piston pin and set of sealing ring of compressorincluding necessary machine work and replacement of other defective spares, reassembling the compressor setafter the repair and tested for smooth functioning complete all as specified and directed. Note:- i)Spare parts shall be measured and paid as supply only under respective item. ii) Cost of Tansportation from site to workshop (If any ) and back shall be deemed to be included in the quoted rate. |
| 23 | supply only suction valve ring plate for compressor set, 30 TR capacity of Make: Accel , Model: SMC-8-65 complete all as specified and directed. |
| 24 | All as per serial item No. 23 above but Discharge valve ring plate complete. |
| 25 | All as per serial item No. 23 above but Safty valve assembly complete. |
| 26 | All as per serial item No. 23 above but connecting rod bolt complete. |
| 27 | All as per serial item No. 23 above but Lock nut crankshaftcomplete. |
| 28 | All as per serial item No. 23 above but Split pin complete. |
| 29 | All as per serial item No. 23 above but Half section of BRG0.75mm under sizecomplete. |
| 30 | All as per serial item No. 23 above but Bushing with detachable collar complete. |
| 31 | All as per serial item No. 23 above but Piston with pin and rings complete. |
| 32 | All as per serial item No. 23 above but Bushing for piston pin complete. |
| 33 | All as per serial item No. 23 above butValve spring complete. |
| 34 | All as per serial item No. 23 above butSpring for unloading pincomplete. |
| 35 | All as per serial item No. 23 above butSet of GasketSMC 8-65 complete. |
| 36 | All as per serial item No. 23 above but Set of sealing ring complete. |
| 37 | All as per serial item No. 23 above but Set of Neoprene Oring complete. |
| 38 | All as per serial item No. 23 above but Cylinder linder with suction valve complete. |
| 39 | All as per serial item No. 23 above but Seeger ring complete. |
| 40 | All as per serial item No. 23 above but Suction Stariner for SMC 8-65 complete. |
| 41 | All as per serial item No. 23 above but Oil Stainer complete. |
| 42 | All as per serial item No. 23 above but Hand shut off valve complete. |
| 43 | All as per serial item No. 23 above but Set of dowry ring complete. |
| 44 | All as per serial item No. 23 above but Set of Aluminum packing complete. |
| 45 | All as per serial item No. 23 above but Oil pump repair kit complete. |
| 46 | All as per serial item No. 23 above but Oil pump complete. |
| 47 | All as per serial item No. 23 above but Unloader cylinder assembly complete. |
| 48 | All as per serial item No. 23 above but Single frame for unloading complete. |
| 49 | All as per serial item No. 23 above but Oil pressure valve complete. |
| 50 | All as per item No 23 but angle valve assembly as per existing. |
| 51 | Dismantling complete Compressor set, 15TR capacity of make Accel, Model SMC-4-65 and overhauling the compressor by repairand checking ofwornout holes of studs and providing over size studs with nuts & washers and gaskets.Rematlling and balancing of piston,replacement of piston ring,scrapper ring, split pin, castle nut, bushing for piston pin, and set of sealing ring of compressorincluding necessary machine work and replacement of other defective spares, reassemblying the compressor setafter the repair and tested for smooth functioning complete all as specified and directed. Note:- i)Spare parts shall be measured and paid as supply only under respective item. ii) Cost of Tansportation from site to workshop (If any ) and back shall be deemed to be included in the quoted rate. |
| 52 | supply only suction valve ring plate for compressor set, 15 TR capacity of Make: Accel , Model: SMC-4-65 complete all as specified and directed. |
| 53 | All as per serial item No. 52 above but Discharge valve ring plate complete. |
| 54 | All as per serial item No. 52 above but Safety valve assembly complete. |
| 55 | All as per serial item No. 52 above but connecting rod bolt complete. |
| 56 | All as per serial item No. 52 above but Lock nut crank shaftcomplete ditto |
| 57 | All as per serial item No. 52 above but Split pin complete. |
| 58 | All as per serial item No. 52 above but Half section of BRG0.75mm under sizecomplete. |
| 59 | All as per serial item No.52 above but Bushing with collar 0.75mm under sizecomplete. |
| 60 | All as per serial item No. 52 above but Piston with pin and ringscomplete. |
| 61 | All as per serial item No. 52 above but Bushing for piston pin complete. |
| 62 | All as per serial item No. 52 above but Valve spring complete. |
| 63 | All as per serial item No. 52 above but Spring for unloading ring complete. |
| 64 | All as per serial item No. 52 above but Set of Gasket SMC 4-65 complete. |
| 65 | All as per serial item No. 52 above but Set of sealing ring complete. |
| 66 | All as per serial item No. 52 above but Set of Neoprene Oringcomplete. |
| 67 | All as per serial item No. 52 above but Cylinder liner with suction valve complete. |
| 68 | All as per serial item No. 52 above but Seeger ring complete. |
| 69 | All as per serial item No. 52 above but Suction stainer SMC 4-65 complete. |
| 70 | All as per serial item No. 52 above but Oil Stainercomplete. |
| 71 | All as per serial item No. 52 above but Hand shut off valve complete. |
| 72 | All as per serial item No. 52 above but Set of dowry ringcomplete. |
| 73 | All as per serial item No. 52 above but Set of Aluminum packingcomplete. |
| 74 | All as per serial item No. 52 above but Oil pump repair kitcomplete. |
| 75 | All as per serial item No. 52. above but Oil pumpcomplete. |
| 76 | All as per serial item No. 52 above butUnloader cylinder assemblycomplete. |
| 77 | All as per serial item No. 52 above butSingle frame for unloadingcomplete. |
| 78 | All as per serial item No. 52 above butangle valve as per existing. |
| 79 | All as per serial item No. 52 above butliquid linevalve as per existing |
| 80 | All as per serial item No. 52 above butloading solenoidvalve as per existing. |
| 81 | All as per serial item No. 52 above but liquid line valver as per existing. |
| 82 | All as per serial item No. 52 above but Oil line valve complete. |
| 83 | S&F in repair Loader / Unloader valveof existing size of model SMC-65 compressor complete all as speified and directed. |
| 84 | S&F in repair pilot control solenoid valve forSMC-65 compressor complete all as speified and directed. |
| 85 | S&F in repairs thermostat expansion valve suitable for 15 to 30 TR complete all as speified and directed. |
| 86 | S&F in repairs ofliquid line stainer filter for SMC-4-65 complete all as speified and directed. |
| 87 | S&F in repairs ofliquid line stainer filter for SMC-8-65 complete all as speified and directed. |
| 88 | S&F in repair servicevalve of compressor of ACCEL make Model SMC-4-65 complete all as specified and directed. |
| 89 | S&F in repair suction servicevalve of compressor of ACCEL make Model SMC-4-65 complete all as specified and directed. |
| 90 | S&F in repair discharge servicevalve of compressor of ACCEL make Model SMC-8-65 complete all as specified and directed. |
| 91 | S&F in repair shaft seal assembly of compressor of ACCEL make Model SMC -4-65 and 8-65 complete all as specified and directed. |
| 92 | Taking out / purging of refrigerant gas from the system of A/C plant 3 x 35 TR capacity for carrying out vacuum test by vacuuming the whole A/c plant with the help of vacuum pump and checking the complete system for leakages. Carrying out the pressure test by chargingthe nitrogen gas in the system and checking of any leakagepoint, repair / rectification of the same and removing the nitrogen gas from the system and charging of refrigerant gas including charging of additional gas as required and all as specified and directed.Note: (i) The arrangement of T&P, Nitrogen gas shall be contractors responsibility.(ii) Refrigerant gas shall be measured and paid separately. |
| 93 | All as per item No 92.00 above but for ACplant 3 x 30 TR capacity. |
| 94 | All as per item No 92.00 above but for ACplant 3 x 15 TR capacity. |
| 95 | De-scaling of the Chiller unit of 12TR capacityCompressor unit by circulating de-scaling agent (HCL) throughChiller and chillerlines by forced feed type method through the cleaning joints, flushing and washing out the units thoroughly andre-fixing back the joints withrubber washers and teflon tape which is ever is necessary complete all as specified and directed. |
| 96 | De-scaling of the condenssor unit of 12TR capacityCompressor unit by circulating de-scaling agent (HCL) throughChiller and chillerlines by forced feed type method through the cleaning joints, flushing and washing out the units thoroughly andre-fixing back the joints withrubber washers and teflon tape which is ever is necessary complete all as specified and directed. |
| 97 | All as per item No 96.00 but for 15 TR capacity. |
| 98 | All as per item No 96.00 but for 30 TR capacity. |
| 99 | All as per item No 96.00 but for 35 TR capacity. |
| 100 | Cleaning of the Evaporation coils ( AHU Coils ) of the 70 TRcapacity with cleaning solvent by forced feed method to removeunwanteddust formed on the coolingcoils fins, cleaning of the filters, greasing to the AHU blower bearings etc and testing complete all as specified and directed. |
| 101 | All as per item No 100.00 here-in-before but for 60 TR capacity. |
| 102 | All as per item No 100.00 here-in-before but for 30 TR capacity. |
| 103 | All as per item No 100.00 here-in-before but for 24 TR capacity. |
| 104 | Supply & fixing Water pressure guage with valve 5/8\" capacity 7 kg/cm2 complete as per existing one and all as specified and directed. |
| 105 | Dismantling of complete existing defective copper tubing of loader / unloader and control switches LP/HP/OP pressure gauge and S&F new copper pipe heavy-duty ¼” diasoft qualityRMfor compressor connection, loader / unloader, control device / pressure control switch, pressure gauge, hand shut off valve including S & F ¼” brass flair nut for all copper tube and clipped on copper plate of required size including copper tubing accessories as per size requirement all as specified and directed. |
| 106 | Pumping downthe total system and taking down the following unserviceable componentsand supply and fix new components including testing complete all as specified and directed. |
| 107 | Oil Pressurecut out Make : Indfoss |
| 108 | High Pressure Cut outMake Indfoss |
| 109 | Low Pressure Cut outMake : Indfoss |
| 110 | Low pressur gauge as per existing |
| 111 | High pressur gauge as per existing |
| 112 | Oil pressur gauge as per existing |
| 113 | Dismantling the power supply of electric motor any type includingand taking to workshop with necessary transportation and opening the complete motor and rewinding the rotor with super enameled copper wire as per the existing gauge with necessary insulation, sticks and varnishing, including replacement of shaft bearing 02 Nos complete of capacity 20 to 30HP complete all as specified and directed. |
| 114 | All as per item No 107.00 but for outdoor blower motor of capacity 7.5/8.5 TR package AC. |
| 115 | All as per item No 107.00 but for capacity 5 to 7.5 HP |
| 116 | Dismantling complete Centrifugal /Mono Block pump set of any type and overhauling the pump re-threading of wornout holes of studs and providing over size studs with nuts & washers.Rematlling and balancing of shaft, replacement of gunmetal bush bearing and gland packingof pump set.and refitting the same after the repair/replacement duly all as specified and tested for smooth functioning of capacity 5 to 7.5 HP complete all as specified and directed. |
| 117 | Dismantling the existing unserviceable compressor of capacity 2.5 Ton, 3 phase, 440 Volt, and S & F New comperssor 2.5 Ton, 3 phase, 440 volt, for split type air conditioner complete all as specified and as directed.Make : Carrier / Kirloskar / Tecumesh |
| 118 | Supply and fill Refrigerant Gas R- 22 in the central AC plant where ever required to fill complete all as specified and as directed. Make : Mafron or equivalent approved products. |
| 119 | Supply and fill Refrigerant Gas R- 134a in the central AC plant where ever required to fill complete all as specified and as directed. Make : Mafron or equivalent approved products. |
| 120 | Supply and fill Refrigerant Gas R- 407C in the central AC plant where ever required to fill complete all as specified and as directed. Make : Mafron or equivalent approved products. |
| 121 | Supply and filling compressor oil suitable for R-22 gas wherever required to fill complete all as specified and directed. Make : Freeze Oil or equivalent approved product. |
| 122 | Supply and filling of compressor oil suitable for R-134a gas wherever required to fill complete all as specified and directed. Make : Freeze Oil or equivalent approved product. |
| 123 | Dismantling the existing unservceable sensing unit of ductable Split AC, S & F new sensing unit of ductable split AC unit of following capacity complete all as specified and as directed. |
| 124 | 7.5 TR ductable split type AC. |
| 125 | 8.5 TR ductable split type AC |
| 126 | Dismantling the existing unserviceable outdoor/indoor blower motor of the following capacities. S & F new outdoor blower motor withsuitable size complete all as specified and as directed. |
| 127 | 7.5 TR capacity |
| 128 | 8.5 TR capaicity |
| 129 | Dis-connectingandremoving the burnt out electrical accessories i.e. Main Contactor MK - 1.5with coil Voltageof 230 Volt capacity and replacing the same with new one of the same capacity including connecting andtestingcomplete all as specified and directed.Make : L & T or equivalent approved product. |
| 130 | Dis-connectingandremoving the burnt out electrical accessories i.e. Main Contactor ML - 3with coil Voltageof 230 Volt capacity and replacing the same with new one of the same capacity including connecting andtestingcomplete all as specified and directed.Make : L & T or equivalent approved product. |
| 131 | Dis-connectingandremoving the burnt out electrical accessories i.e. Main Contactor ML - 4with coil Voltageof 230 Volt capacity and replacing the same with new one of the same capacity including connecting andtestingcomplete all as specified and directed.Make : L & T or equivalent approved product. |
| 132 | All as per item No 121.00 here-in-before but contactor 4 pole 25 Amp from existing position without any damage and S & F new contactor 4 pole 25 Amp complete all as specified and as directed. |
| 133 | All as per item No 121.00 here-in-before but for ML Relay including connector block 20 to 32 Amps complete all as specified and directed.Make : L & T or equivalent approved product. |
| 134 | All as per item No 121.00 here-in-before but for ML Relay including connector block 6 to 10 Amps complete all as specified and directed.Make : L & T or equivalent approved product. |
| 135 | All as per item No 121.00 here-in-before but for MN relay including connector block 28 to 42 Amps complete all as specified and directed.Make : L & T or equivalent approved product. |
| 136 | All as per item No 130 here-in-before but for Ammeter 0 to 100 AmpsCT type including suitable CT coils of 03 Nos complete all as specified and directed. |
| 137 | All as per item No 121.00 here-in-before but for Volt meter0 to 500 Volts complete all as specified and directed. |
| 138 | All as per item No 121.00 here-in-before but of indicating lamp set (RYB) LED type complete all as specified and directed. |
| 139 | Supply and replacement of temperature gauge (thermometer) digitaltype 0-50 degree centigrade complete all as specified and directed. |
| 140 | Supply and replacement of temperature gauge (thermometer) DRY & WETtype 0-50 degree centigrade complete all as specified and directed. |
| 141 | S & F Rotaryswitch 3 position complete all as specified and directed. Make : C&S/kaycee or equivalent approved product. |
| 142 | S & F NO/NC push switch as per existing complete all as specified and directed. |
| 143 | Dismantling the Unserviceable copper tube and insulation tube, Supply and fixing of Copper tube 5/8\" spare parts suitable for 7.5 TR ductable split type AC plant complete all as specified and as directed. |
| 144 | All as per item No 133.00 here-in-before but for copper tube 1/2\" |
| 145 | All as per item No 133.00 here-in-before but for copper tube 1/4\" |
| 146 | All as per item No 133.00 here-in-before but for copper tube 3/8\" |
| 147 | All as per item No 133.00 here-in-before but for Insulation tube 5/8\" |
| 148 | All as per item No 133.00 here-in-before but for Insulation tube 1/2\" |
| 149 | All as per item No 133.00 here-in-before but for Insulation tube 1/4\" |
| 150 | All as per item No 133.00 here-in-before but for Insulation tube 3/8\" |
| 151 | M&L for perimeter setting complete all as specified and as directed. |
| 152 | Repairs to Pakage type air conditioner in situ position of capacity mentioned belowof any make and any type by replacing unserviceable compressor and other parts from the machine including charging of refrigerant gas after vaccuming and leak testing including brazing the suction / discharge tubes where required and cleaning of condensing unit to achieve proper cooling effect, checking of electronic circuit of machine and repair where necessary by replacing electronic parts and changing of wirings with of PVC insulated wires as per existing type and testing commissioning complete all as specified and as directed. Note : (i) Compressor and other parts needed for repair shall be measured and paid separately under relevent item given in schedule \"A\" here in after as supply only. (ii)Existing refrigerant gas shall be preserved in aempty cylinder for re-use in new compressor and additional requirement of refrigerant charging shall be measured and paid separately under relevant item of this schedule. (iii) Repair of canvas cover of Blower unit (AHU) if damage by the out source shall be supplied by contractor at his own and rate for the same are deemed to included with the unit rate. (a)3X2.5 TR capacity installed at Bomb Dump, Base Ops |
| 153 | Supply only new compressor 2.5 TR capacity 3 phase 440 V Make: Emerson/Carreir or equivalent approved makes. |
| 154 | Supply & fixing multi capacitor complete as per existing one and all as directed. |
| 155 | Supply & fixing Condenser unit assembly of 3x2.5 TR complete as per existing one and all as directed. |
| 156 | All as per item No 145.00 here-in-before but for 8.5 TR capacity installed at Instrument Lab and Safety Section. |
| 157 | Servcing and overhaulling of induced draft top discharge counterflow type FRP colling tower (Rectanguler/Round bottle shape) capacitywith FRP body and base,repair / replacementto damage water spray headers & cooling tower fills, repair supporting base frame camplete all as directed and as per site requirement incl painting as per existing colour andtesting for proper fuctioning.Note : cost of spare parts required shall deemed to be included in quoted rate. |
| 158 | V-Belt for compressor smc -65, model B2080/B81 complete all as specified and directed. |
| 159 | Supply & fixing MCB Triple Pole and Neutral (TPN) of capacity 65 to 70 Amps, 415 Volts, breaking capacity 10 KA, ‘C’ series, fixedin proper position all as directed by the Engineer-in-Charge.Make Cat No4086 65 to 4086 70 of legrand or equivalent approved product. |
| 160 | S & F star delta starter for 12 TR compressor as per existing and directed by Engineer in charge. |
| 161 | Supply and Fixing AHU Filter of following size:- |
| 162 | Pre Filter of size 26\"\"x20\"\"x2\"\" for AHU of 60 TR capacity as per exiting. |
| 163 | Micro Filter of size 26\"\"x20\"\"x2\"\" for AHU of 60 TR capacity as per exiting. |
| 164 | Pre Filter of size 24\"\"x18\"\"x6\"\" for AHU of 30 TR capacity as per exiting. |
| 165 | Micro Filter of size 24\"\"x18\"\"x6\"\" for AHU of 30 TR capacity as per exiting. |
| 166 | Pre Filter of size 24\"\"x24\"\"x2\"\" for AHU of 70 TR capacity as per exiting. |
| 167 | Micro Filter of size 24\"\"x24\"\"x12\"\" for AHU of 70 TR capacity as per exiting |
| 168 | Pre Filter of size 24\"\"x20\"\"x2\"\" for AHU of 24 TR capacity as per exiting. |
| 169 | Pre Filter of size 20\"\"x20\"\"x2\"\" for AHU of 24 TR capacity as per exiting |
| 170 | Micro Filter of size 24\"\"x24\"\"x12\"\" for AHU of 24 TR capacity as per exiting |
| 171 | Micro Filter of size 24\"\"x20\"\"x2\"\" for AHU of 24 TR capacity as per exiting |
| 172 | Micro Filter of size 20\"\"x20\"\"x12\"\" for AHU of 24 TR capacity as per exiting |
AI Tender Summary
Tender Timeline
Nov 26, 2021
11:30 IST
Tender Published
Tender notice published.
CompletedDec 17, 2021
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedDec 27, 2021
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender