Housing Urban and Rular Development Government Departments Closing in 0 days TDR #29891688

Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22 Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22

Issued by Government Departments · Chhatia, Odisha
Tender Value
85.21 Lakhs
Estimated cost
Bid Submission
29 Nov 2021
0 days left
EMD
Ref. Documents
Bank guarantee accepted
Document Fee
10000
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Chhatia → Odisha
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22 Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22

BOQ

Name of Work:CONSTRUCTION OF BOUNDARY WALL FOR BALANCE AREA TO H.M.V DRIVING TRAINING INSTITUTE AT CHHATIA FOR THE YEAR 2021-22
Sl. No. Item Description
1Earth work excavation in foundation trenches in all kinds of soil including hard moorum stony earth mixed with stone and boulders (except sheet rocks and boulders required blasting) including dressing and leveling the bed up to required depth and depositing the excavated materials at places away from work site with all leads and lifts T&P shoring shuttering dewatering if required etc. complete as per direction of the Engineer-in-charge.
2Supplying filling in foundation, plinth & core with sand in layers not exceeding 150mm thick including watering, ramming, cost, conveyance, royalty and taxes of all materials and cost of all labour T&P required for the work etc. complete (measurement will be taken on finished compacted section only).
3Cement concrete (1:4:8) in foundation and floors using 4cm(1½”) size hard crusher broken granite stone metal of approved quality and from approved quarry including lowering, laying concrete watering, curing etc, complete to required levels laid in layers not exceeding 0’-6” thick including cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P required for the work etc, complete as per specification & direction of the Engineer-in-charge.
4RCC M-20 usingblack hard granite crusher broken chips of 10mm to 20mm size (10mm 40% and 20mm 60% ) of approaved qualityfrom approved quarry to achieve the minimum compressive strength of 200kg/cm2 250kg/cm2, 3.00 kg/cm2 of 150mm size cubes on 28 days test confirming to codal provision including hoisting lowering and laying concrete in layers not exceeding 15cm thick compacting in vibrators and watering for 28 days including centering shuttering from works finishing the exposed surface smooth providing grooves where necessary including cost conveyance royalty taxes of all materials with all leads and lifts and cost of all labour T&P mechineries required for the work de-watering if necessary compalete in all respect as directed by Engineer-in-charge including dismantling the centering and shuttering but excluding cost conveaynce of MS rod or tor steel & bind wire and labour charges for strengthening cutting beinding binding wilding and tying the grills etc hoisting and placing in positing (to be paid separetely for RCC work)A. FOUNDATION (BASE)
5B. SUB-STRUCTURE (PLINTH BEND)
6C. COLUMN IN SUPERSTRUCTURE
7Labour charges for straightening the coiled or bent up M.S. rod / HYSD bars confirming to Gr. S 240 or S 415, cutting bending binding lapping placing welding etc. (Confirming to ISI specification) and jointing if necessary by lapping and tying the grills and placing in position as required for RCC work as per approved design hoisting lowering and laying in position including cost conveyance & taxes of M.S. rod / tor steel and binding wire of 18 to 20 gauge (as approved by the deptt.) weight of over lapping, coping, welded joints, spear bar, chair, stage, hanger andbinding wires shall not be considered for payment at all. Standard co-efficient of different size of the steel shall be considered. Welding & lapping should be confirming to relevant clause of IRC 1987.
8Fly ash Brick masonry using Fly ashBricks in FOUNDATION AND PLINTH having crushing strength not less than 75Kg/sqcm in cement mortar (1:6) after immersing the bricks for six hours in water before useincluding splays, cutting, circular moulding, corbelling, champhering and similar such type of works,scaffolding, watering, curing, including cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P required for the work etc. complete as per specification & direction of Engineer-in-charge.
9Providing 12mm thick cement plaster in cement mortar (1:6)finished smooth to inside rough surface of brick walls after racking out joints, scrapping & cleaning the surface, watering, curing, scaffolding, screening sand etc. complete with cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P, sundries required for the work etc. complete as per specification & direction of Engineer-in-charge.
10Providing 16mm thick cement plaster in cement mortar (1:6)finished smooth to inside rough surface of brick walls after racking out joints, scrapping & cleaning the surface & finishing the plaster surface smoothwatering, curing, scaffolding, screening sand etc. complete with cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P, sundries required for the work etc. complete as per specification & direction of Engineer-in-charge.
11Supplying fixing and fittings MS door and window shutters with frames, window grills, MS verandha grills and MS grill gate of approved design and drawing made out of MS flat and MS angle and square barand paintingred oxide paintat work site with one coat of anticorrosive red oxide zink chrome primer including cutting holes in brick or RCC walls and fixing with CC (1:3:6) including cost conveyance royalty and taxes of all materials all labour T&P required for the work complete (payment will be made on weight basis only).
12Finishing walls with two coats ofwater proofing cement paints to give an even shape to the surface including cleaning the surface, sand papering and using paint of approved quality and approved shade including cost conveyance, taxes of all materials all labour & T&P etc. complete as directed by the Engineer-in-charge.
13Painting two coats with approved synthetic enamel paints to M.S. window and verendah grill overwahs in sand paper or iron paper received to paints smoothlyincluding cost, conveyance, taxes, cost of all labour as per direction and specification of Engineer in charge

AI Tender Summary

OUR REF NO 29891688
AUTHORITY Government Departments
TENDER VALUE 85.21 Lakhs
LAST DATE 29-11-2021
Authority
Authority Name Road And Building Department
Work Description Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22 Construction Of Boundary Wall For Balance Area To Hmv Driving Training Institute At Chhatia For The Year 2021-22
Basic Detail
Tender No SE CBT (R and B)-17///2021-22
Bidding Type Tender
Location
City Chhatia
State Odisha
Key Dates
Publish Date 15 Nov 2021
Submission Date 29 Nov 2021
Open Date 30 Nov 2021
Finance
Tender Value 85.21 Lakhs
Tender Fee 10000
EMD Ref. Documents
Exemption Not Available
Document List
1da8d6e8-1fa2-40fb-b53e-8ff1fc648272.html
BOQ_373410.xls
DTCN.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Nov 15, 2021
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 29, 2021
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Nov 30, 2021

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
html

1da8d6e8-1fa2-40fb-b53e-8ff1fc648272.html

xls

BOQ_373410.xls

pdf

DTCN.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders