Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippuram To Manappally Under Es, Manappally Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippur, Manappally-Kerala

Kerala State Electricity Board-KSEB has published Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippuram To Manappally Under Es, Manappally Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippur. Submission Date for this Tender is 24-11-2021. Overhead Line Tenders in Manappally Kerala. Bidders can get complete Tender details and download the document.




Tender Notice

29826692
Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippuram To Manappally Under Es, Manappally Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippur
Open Tender
Indian
Kerala
Manappally
24-11-2021

Tender Details

Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippuram To Manappally Under Es, Manappally Dismantling Cross Country Ht Line, Constructing Alternate Ht Line Along Road And Lt Reconductoring Kuttippuram To Manappally Under Es, Manappally

Key Value

Document Fees
INR 1434 /-
EMD
INR 9200.0 /-
Tender Value
INR 6.07 Lakhs /-

BOQ Items

Name of Work:DISMANTLING CROSS COUNTRYHT LINE, CONSTRUCTING ALTERNATEHT LINE ALONG ROAD AND LT RECONDUCTORING – KUTTIPURAM TO MANAPPALLY UNDER ES, MANAPPALLY
Sl. No. Item Description
1Loading HT PSC pole from the stacking place & unloading the same at work site (transport by vehicle).
2Transporting poles by hired vehicle to a distance upto 5km & carrying upto 4 poles exclu. loading & unloading.
3Loading HT "A" type pole from the stacking place & unloading the same at work site (transport by vehicle).
4D/m one damaged 11kV TW/RSJ/Rail pole after disconnecting stays, strut etc. & stacking the same.
5D/m one damaged 11kV PSC pole after disconnecting stays, strut etc. & stacking the same.
6D/m (without damage) one 11kV PSC pole after disconnecting stays, strut etc. & stacking the same.
7D/m (without damage) one km 11kV line (3 conductors), cross arm, insulators, disc, rolling the conductor & stacking.
8D/m (without damage) one HT stay incl. back filling, & bringing back to section store.
9D/m one V cross arm/Channel cross arm from existing Pole, & bringing back to section store.
10D/m one Channel cross arm from existing DP structure, & bringing back to section store.
11D/m (without damage) one AB switch from existing structure & bringing back to section store.
12Transporting one HT PSC pole by Head load (limited to 0.3km).
13Transporting one HT TW/RSJ/Rail pole by Head load for an average distance of one km (limited to 0.3km).
14Fitting & erecting one HT PSC Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads.
15Fitting & erecting one HT "A" type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads.
16Addnl rate for providing one disc set on any type of HT pole for making cut point.
17Fitting & erecting one HT DP using PSC pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads.
18Fitting & providing one HT Stay for 11kV pole incl. digging & back filling pit.
19Fitting & providing one Strut using HT PSC pole incl. digging & back filling pit.
20Fitting & providing one HT Fly stay for 11kV pole using HT PSC pole incl. digging & back filling pits.
21Stringing of one km 11kV line with ACSR Raccoon (3 conductors) incl. cutting & removing tree branches wherever necessary.
22Addnl rate for excavation of one Pit for HT Pole/HT Stay in Laterite.
23Providing one Earth using earth pipe incl. digging separate pit at st&ard distance away from the pole/structure & backfilling.
24Addnl rate for excavation of one Earth Pit (2.5m depth) in Laterite.
25Providing one Coil Earth using GI earth wire, digging separate pit at st&ard distance away from the pole/structure & backfilling.
26Fitting one set AB switch & giving connection
27Fitting one Addnl 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials.
28D/m one damaged LT PSC/RCC pole after disconnecting stays, strut etc. & stacking the same.
29D/m (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. & stacking the same.
30D/m (without damage) LT stay incl. digging pit in all classes of soil & backfilling
31D/m one LT 2 line cross arm from existing pole.
32D/m one LT 4 line cross arm from existing pole.
33D/m (without damage) one km LT Addnl conductor line, cross arms, insulators & stacking the conductors in rolls.
34Fitting one LT 2 line cross arm on HT or LT existing poles incl. fitting insulators & binding the same with LT Line.
35D/m one section fuse
36Addnl rate for refitting/redoing one Shackle set & reshackling one span while renewing any type of pole.
37Reshackling one span LT Sph 2 wire OH line, replacing insulators, tightening stay, cutting tree branches incl. conveyance.
38Reshackling one span LT 3ph 4 wire OH line, replacing insulators, tightening stay, cutting tree branches incl. conveyance.
39Transferring LT Sph 2/3 wire OH line to newly erected HT/LT pole & refitting all items to the new pole.
40Transferring LT 3ph 4/5 wire OH line to newly erected HT/LT pole & refitting all items to the new pole.
41D/m & reconnecting Sph service connection from the OH line incl. lowering down the WP portion.
42D/m & reconnecting 3ph service connection from the OH line incl. lowering down the WP portion.
43Stringing one km LT Addl conductor (Rabbit) after fitting crossarm, but without realigning existing conductor, incl. fitting cross arm, insulator etc. removing touchings & conveyance of materials.
44Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with B&N etc.
45D/m one ordinary street light/CFL/LED fitting from existing pole & refitting the same on newly erected pole & reconnecting.
46D/m one 2x40W fluorescent tube fitting from the existing pole & refitting the same on newly erected pole & reconnecting.
47Cutting trees beyond 30cm but upto & incl. 60cm girth, cutting of trunks/branches, removing the root completely & stacking.
48Cutting trees beyond 60cm but upto & incl. 120cm girth, cutting of trunks/branches, removing the root completely & stacking.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail