Providing Sump For Monitoring Coal Muck From 10000 Te Bunker Of M-Series Including Approach Drain At Gevra Project Of Gevra Area Providing Sump For Monitoring Coal Muck From 10000 Te Bunker Of M-Series Including Approach Drain At Gevra Project Of Gevra Ar
Tender Overview
Project Description
Providing Sump For Monitoring Coal Muck From 10000 Te Bunker Of M-Series Including Approach Drain At Gevra Project Of Gevra Area Providing Sump For Monitoring Coal Muck From 10000 Te Bunker Of M-Series Including Approach Drain At Gevra Project Of Gevra Area
BOQ
| Sl. No. | Item Description |
| 1 | PART A:- |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) in foundation trenches or drain (not exceeding 1.5m in width as well as 10sqm on plan) or in over areas (exceeding 30cm in depth, 1.5 m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 1.00 km. All kind of soil. |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) |
| 4 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for :Suspended floors, roofs, landings, balconies and access platform |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Hot rolled deformed bars |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for :Foundations, footings, bases of columns, etc. for mass concrete |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form for :Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. |
| 10 | Total impact of GST for the purpose of CTC |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender