Border Security Force-BSF has published Shifting And Fixing Of Vertical Rope, Monkey Rope And Beam From Flc Ground To Training Ground Near 120 Men Barrack At Cswt Campus Under Stc Bsf Indore Shifting And Fixing Of Vertical Rope, Monkey Rope And Beam From Flc Ground To Training Ground Ne. Submission Date for this Tender is 02-11-2021. Civil Work Tenders in STC BSF Indore training area at CSWT Campus Madhya Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 15.2.1 Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
2 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. |
3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). |
4 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size). |
5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. |
6 | Centering and shuttering including strutting, propping etc. and removal of form for :Foundations, footings, bases of columns, etc. for mass concrete. |
7 | Structural steel work in single section, fixed with or without connecting plate,including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
8 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. |
9 | Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length ( hold fast lugs or dash fastener shall be paid for separately). Sal wood. |
10 | Applying priming coat:With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) sqm 57.05 |
11 | Paintingwithsyntheticenamelpaintofapprovedbrandand manufacture to give an even shade : Two or more coats on new work |
12 | Hiring of crane including fuel, operator & labour charges for shifting built up tubular (round, square or rectangular hollow tubes etc.) trusses etc.without dismembering or damaging all complete as per direction of Engineer-in-charge. |
13 | Add 8.47% cost index on DSR 2018 items (i.e. item No. 1 to 11) |