Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petroleum Corporation Limited ( Cpcl ) , India Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petrol, Nagapattinam-Tamil Nadu

Chennai Petroleum Corporation Limited-CPCL has published Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petroleum Corporation Limited ( Cpcl ) , India Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petrol. Submission Date for this Tender is 08-11-2021. Hosiery Tenders in Nagapattinam Tamil Nadu. Bidders can get complete Tender details and download the document.




Tender Notice

29612990
Corrigendum : Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petroleum Corporation Limited ( Cpcl ) , India Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petrol
Open Tender
Indian
Tamil Nadu
Nagapattinam
08-11-2021

Tender Details

Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petroleum Corporation Limited ( Cpcl ) , India Topography Survey And Geotechnical Investigation Works Of Epcm-2 Package For Cbr Project Of Chennai Petroleum Corporation Limited ( Cpcl ) , India , Providing And Constructing Permanent Bench Mark Pillars Of Size 1000Mm X 1000 Mm X 1500 Mm In Plain Cement Concrete Of Nominal Mix 1:2:4 ( 1 Cement : 2 Coarse Sand: 4 Graded Stone Aggregates Of 20 Mm Nominalsize ) With 500 Mm Below Ground Level And 1000 Mm Above Ground Including Embedding Steelplate Of Size 150 Mm X 150Mm X 10 Mm On Top Of Thepillar By Two Nos.10 Mm Dia Torr. M.S. Anchor Bars Of Total Length 450Mm Each, Welded To The Above Plate For Marking The Permanent Reference Points, Including Shuttering, Tamping, Ramming, Vibrating, Curing, Finishing The Top And Sides Rough Or Smooth As Directed Or Specified, Supply Of All Labours And Materials, Etc., Complete In All Respect Asper Drawings Specifications And Directions Of Engineer-In - Charge. , Conducting Topographical Ground / Land Survey Including Mobilization And Demobilization Of Equipment / Machinery / Manpower Etc. In The Specified Area By Total Station Method, Covering Details Of Physical Features Like Rivers, Nallahs, Lakes, Ponds, Wells, Pits, Forest, Trees, Roads, Culverts, Transmission Lines, Telegraph / Telephone And Electric Poles, Underground Or Any Other Services, Cross Drainage Works Including Cross Sectional Details Of Nallah Etc. Including Establishing High Flood Level With Source Of Information, Identification Of Any Monument, Historical Structure, Wild Life Sanctuary In The Vicinity, Storm Water Disposal Point With Levels, Cross-Section Details Of Nallah, Recording Spot Levels, Including Providing In Tabulation Girth Wise No. Of Trees Etc As Specified, Plotting And Developing Topographical Contour Maps, Showing True North Including Establishing Survey Reference Stations, Key Plan Etc. Including All Equipments, Instruments, Personnels, Clearing Of Bushes As Per Requirement For Intervisibility To Carry Out Survey Work Etc. , Complete Work In All Respects As Per Drawings, Specifications And Directions Of Engineer-In-Charge Including Submitting Hard Copies Of Drawings / Map And Supply Of Electronic Files. , Survey Work For Establishing Co-Ordinates & Rls , Carrying Out Survey Work For Establishing Coordinates And Rls At All Test Locations With Reference To Nearby Available Reference Co-Ordinates & Rls Including Mobilisation Of Survey Instruments And Personnel. , Boring In Soil ( Boring Vertically Through All Kinds Of Soils, Weathered Rock And Soft Rock With Suitable &Adequate Equipment Of Diameter 150 Mm, For Depths As Below Including Backfilling Of Boreholes With 1:1 Cement : Bentonite / Mud Grout As Per Specifications. , Boring Of Min. 150 Mm Nominal Dia. Boreholes As Per Specification From Gl Upto & Inclusive Of 10 M. , Boring Of Min. 150 Mm Nominal Dia. Boreholes As Per Specification Beyond 10M And Upto & Inclusive Of 20M. , Boring Of Min. 150 Mm Nominal Dia. Boreholes As Per Specification Beyond 20M And Upto & Inclusive Of 30M. , Coring In Rocks ( Drilling Vertically Through Boulders & Bedrock Strata ( Hard Rock ) For A Depth Of Upto 3.0 M Depth In Such Strata, Using Nx Size Diamond Bit, Using Double Tube Core Barrel With Suitable Core Catcher, Including Collection & Logging Of Cores, Placing Them In Wooden Core Boxes In A Proper Sequence, Numbering Each Core Etc. ) , Coring In Rock Of Nx Size With Double Tube Core Barrelwith Diamond Bits , Field Tests , Conducting Standard Penetration Tests In Boreholes , Collecting Undisturbed Samples From Boreholes , Excavation Of Trial Pits , Conducting Static Cone Penetration Test ( Scpt ) , Conducting Plate Load Test ( Plt ) , Dynamic Soil Test , Conducting Cross Hole Test , Conducting Field Vane Shear Test , Installation Of Piezometer , Conducting Electrical Resistivity Tests ( Ert ) , Soil Resistivity Tests ( Sr ) , Thermal Resistivity Tests ( Trt ) , Field Cbr , Conducting Unsoaked Field Cbr Test , Conducting Soaked Field Cbr Test , Laboratory Tests Onsoil Samples , Conducting Atterbergs Limit ( Liquid Limit & Plastic Limit ) , Conducting Natural Water Content On Soil Samples , Conducting Bulk And Dry Density Tests On Soil Samples , Conducting Specific Gravity And Void Ratio Tests On Soil Samples , Grain Size Analysis On Soil Samples , Conducting Sieve Analysis For Grain Size Distribution On Samples , Conducting Hydrometer Analysis For Grain Size Distribution On Samples , Triaxial Shear Tests On Soil Samples , Conducting Triaxial Unconsolidated Undrained ( Uu ) Test On Soil Samples , Conducting Triaxial Consolidated Undrained ( Cu ) Test On Soil Samples , Conducting Direct Shear Test On Soil Samples , Conducting Consolidation Tests On Soil Samples . , Conducting Standard Proctor Density Test On Soil Samples , Conducting Modified Proctor Density Test On Soil Samples , Laboratory Cbr Tests On Soil Samples , Conducting Laboratory Unsocked Cbr Tests On Soil Samples , Conducting Laboratory Socked Cbr Tests On Soil Samples , Laboratory Tests On Rock Samples , Conducting Unconfined Compression Test On Rock Samples , Conducting Point Load Test On Rock Samples , Conducting Crushing Strength Test On Rock Samples As Specified ( In Case Of Rock ) , Un-Soaked Condition , Soaked Condition , Chemical Tests On Soil / Water Samples , Conducting Chemical Tests On Soil Samples As Specified , Conducting Chemical Tests On Ground Water Samples , Conducting Swelling Potential And Swelling Pressure Tests On Soil Samples As Specified, If Soil Is Expansive Nature , Hydrological Data , Collect And Provide Hydrological Data From Local Government Authority , Soil Report Preparation And Submission In 6 Copies As Per Specific Requirements , Geotechnical Contractor To Prepare Detailed Soil Report As Per Specifications And Specific Requirements, As Soon As Field & Laboratory Tests Completed. All The Information As Mentioned In Specific Requirements Shall Be Furnished In The Draft Copy Of Final Report For Our Review And Comments. After Reviewing, Geotechnical Contractor Shall Be Informed About Our Comments / Remarks, If Any And The Same Shall Be Incorporated And Final Report Shall Be Submitted In 6 Nos Copies.

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 29-Oct-2021 Commercial Amendment No-1 Technical Bid 08-11-2021
2 29-Oct-2021 Reply to Pre-Bid Queries Other 08-11-2021
3 01-Nov-2021 Pre-Bid Queries Technical Bid 08-11-2021

Key Value

Document Fees
Refer document
EMD
Refer document
Tender Value
Refer document

BOQ Items

CPCL’s 9 MMTPA Cauvery Basin Refinery (CBR) Project at Nagapattinam, Tamilnadu, India –EPCM-2
Sl. No. Item Description
1Providing and constructing Permanent Bench Mark Pillars of size 1000mm x 1000 mm x 1500 mm in plain cement concrete of nominal mix 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregates of 20 mm nominalsize) with 500 mm below ground level and 1000 mm above ground including embedding steelplate of size 150 mm x 150mm x 10 mm on top of thepillar by two nos.10 mm dia Torr. M.S. Anchor Bars of total length 450mm each, welded to the above plate for marking the permanent reference points, including shuttering, tamping, ramming, vibrating, curing,finishing the top and sides rough or smooth as directed or specified,supply of all labours and materials, etc., complete in all respect asper drawings specifications and directions of Engineer-in - Charge.
2Conducting topographical ground/land survey including mobilization and demobilization of equipment/machinery/manpower etc. in the specified area by Total Station method, covering details of physical features like Rivers, Nallahs, Lakes, Ponds, wells, pits, Forest, Trees, Roads, culverts, transmission lines, telegraph/ telephone and electric poles, underground or any other services, cross drainage works including cross sectional details of nallah etc. including establishing high flood level with source of information, identification of any monument, historical structure, wild life sanctuary in the vicinity, storm water disposal point with levels, cross-section details of nallah, recording spot levels, including providing in tabulation girth wise no. of trees etc as specified, plotting and developing topographical contour maps, showing true north including establishing survey reference stations, key plan etc. including all equipment"s, instruments, personnel"s, clearing of bushes as per requirement for intervisibility to carry out survey work etc. , complete work in all respects as per drawings, specifications and directions of Engineer-in-Charge including submitting hard copies of drawings/map and supply of electronic files.
3Survey work for establishing Co-ordinates & RLs
4Carrying out SURVEY WORK for establishing coordinates and RLs at all test locations with reference to nearby available reference co-ordinates & RLs including mobilisation of survey instruments and personnel.
5BORING IN SOIL ( Boring vertically through all kinds of soils, weathered rock and soft rock with suitable &adequate equipment of diameter 150 mm, for depths as below including Backfilling of boreholes with 1:1 cement : bentonite / mud grout as per specifications.
6Boring of min. 150 mm nominal dia. boreholes as per specification from GL upto & inclusive of 10 m.
7Boring of min. 150 mm nominal dia. boreholes as per specification beyond 10m and upto & inclusive of 20m.
8Boring of min. 150 mm nominal dia. boreholes as per specification beyond 20m and upto & inclusive of 30m.
9CORING IN ROCKS (Drilling vertically through boulders & bedrock strata (hard rock) for a depth of upto 3.0 m depth in such strata, using NX size Diamond bit, using double tube core barrel with suitable core catcher, including collection & logging of cores, placing them in wooden core boxes in a proper sequence, numbering each core etc. )
10Coring in Rock of Nx size with double tube core barrelwith Diamond bits
11FIELD TESTS
12Conducting Standard Penetration Tests in boreholes
13Collecting undisturbed samples from boreholes
14Excavation of Trial Pits
15Conducting Static Cone Penetration Test (SCPT)
16Conducting Plate Load Test (PLT)
17DYNAMIC SOIL TEST
18Conducting Cross Hole Test
19Conducting field Vane Shear Test
20Installation of Piezometer
21Conducting Electrical Resistivity Tests (ERT)
22Soil Resistivity Tests (SR)
23Thermal Resistivity Tests (TRT)
24FIELD CBR
25Conducting Unsoaked field CBR Test
26Conducting Soaked field CBR Test
27LABORATORY TESTS ONSOIL SAMPLES
28Conducting Atterberg"s limit (Liquid Limit & Plastic Limit)
29Conducting Natural water content on soil samples
30Conducting Bulk and dry density tests on soil samples
31Conducting Specific gravity and void ratio tests on soil samples
32GRAIN SIZE ANALYSIS ON SOIL SAMPLES
33Conducting Sieve analysis for grain size distribution on samples
34Conducting Hydrometer Analysis for grain size distribution on samples
35TRIAXIAL SHEAR TESTS ON SOIL SAMPLES
36Conducting triaxial Unconsolidated Undrained (UU) test on soil samples
37Conducting triaxial Consolidated Undrained (CU) test on soil samples
38Conducting Direct Shear Test on soil samples
39Conducting Consolidation tests on soil samples .
40Conducting Standard Proctor Density test on soil samples
41Conducting Modified Proctor Density test on soil samples
42LABORATORY CBR TESTS ON SOIL SAMPLES
43Conducting Laboratory Unsocked CBR Tests on soil samples
44Conducting Laboratory Socked CBR Tests on soil samples
45LABORATORY TESTS ON ROCK SAMPLES
46Conducting Unconfined Compression Test on Rock samples
47Conducting Point Load test on Rock samples
48Conducting crushing strength test on rock samples as specified (in case of rock)
49Un-soaked condition
50Soaked condition
51CHEMICAL TESTS ON SOIL/WATER SAMPLES
52Conducting Chemical tests on SOIL SAMPLES as specified
53Conducting Chemical tests on GROUND WATER samples
54Conducting Swelling Potential and Swelling Pressure tests on soil samples as specified, if soil is EXPANSIVE nature
55Hydrological Data
56Collect and provide Hydrological Data from local government authority
57SOIL REPORT PREPARATION AND SUBMISSION IN 6 COPIES AS PER SPECIFIC REQUIREMENTS
58Geotechnical Contractor to prepare detailed soil report as per specifications and specific requirements, as soon as field & laboratory tests completed. All the information as mentioned in Specific Requirements shall be furnished in the draft copy of final report for our review and comments. After reviewing, Geotechnical Contractor shall be informed about our comments/ remarks, if any and the same shall be incorporated and final report shall be submitted in 6 nos copies.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail